SMITH VA (0910-16-182)
Items: 13
County: SMITH
Length: N/A
Highway: VA
District: TYLER
Control Number: 0910-16-182
DBE Goal: N/A
Project: STP 2024(336)HES
Guaranty: N/A
Time: 33 WORKING DAYS
Engineer's Estimate: $271,182.00
Date: 11/02/2023 (2 years ago)
Contract Number: N/A
Type: INSTALL ILLUMINATION
Mail/Deliver Bids To: N/A
JUANITA DANIELSWEST
STEVEN SWINDELL
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$271,182.00 | |||
| $232,606.44 |
-14.22%
-$38,575.56
|
|||
| $263,882.00 |
-2.69%
-$7,300.00
|
13.45%
$31,275.56
|
||
| $312,721.90 |
15.32%
$41,539.90
|
34.44%
$80,115.46
|
-18.51%
-$48,839.90
|
|
| $326,342.61 |
20.34%
$55,160.61
|
40.3%
$93,736.17
|
-4.36%
-$13,620.71
|
|
| $357,332.00 |
31.77%
$86,150.00
|
53.62%
$124,725.56
|
-9.50%
-$30,989.39
|
|
| $682,021.00 |
151.5%
$410,839.00
|
193.21%
$449,414.56
|
-90.86%
-$324,689.00
|
E
Engineer's Estimate
$271,182.00
1
Awarded
$232,606.44
Over/Under Est:
-14.22%
-$38,575.56
$263,882.00
Over/Under Est:
-2.69%
-$7,300.00
Amt Left:
13.45%
$31,275.56
$312,721.90
Over/Under Est:
15.32%
$41,539.90
Amt Left:
34.44%
$80,115.46
Delta:
-18.51%
-$48,839.90
$326,342.61
Over/Under Est:
20.34%
$55,160.61
Amt Left:
40.3%
$93,736.17
Delta:
-4.36%
-$13,620.71
$357,332.00
Over/Under Est:
31.77%
$86,150.00
Amt Left:
53.62%
$124,725.56
Delta:
-9.50%
-$30,989.39
$682,021.00
Over/Under Est:
151.5%
$410,839.00
Amt Left:
193.21%
$449,414.56
Delta:
-90.86%
-$324,689.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| FLEX SUPPLY, LLC | 2.36% | $5,489.51 |
| Total: | 2.36% | $5,489.51 |
Bid Items & Bid Tabulations
13
Total
0 of 13