SMITH CS (0910-16-147)

Items: 57

County: SMITH
Length: N/A
Highway: CS
District: TYLER
Control Number: 0910-16-147
DBE Goal: N/A
Project: BR 2020(895)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $1,258,233.40
Date: 01/07/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (9)
E
Engineer's Estimate
$1,258,233.40
$1,258,293.70
Over/Under Est: 0% $60.30
Over/Under Est: 2.52% $31,644.78
Amt Left: 2.51% $31,584.48
Over/Under Est: 4.38% $55,103.00
Amt Left: 4.37% $55,042.70
Delta: -1.82% -$23,458.22
$1,365,597.05
Over/Under Est: 8.53% $107,363.65
Amt Left: 8.53% $107,303.35
Delta: -3.98% -$52,260.65
Over/Under Est: 8.58% $108,018.09
Amt Left: 8.58% $107,957.79
Delta: -0.05% -$654.44
Over/Under Est: 10.12% $127,394.45
Amt Left: 10.12% $127,334.15
Delta: -1.42% -$19,376.36
Over/Under Est: 25.12% $316,075.70
Amt Left: 25.11% $316,015.40
Delta: -13.62% -$188,681.25
Over/Under Est: 28.72% $361,353.30
Amt Left: 28.71% $361,293.00
Delta: -2.88% -$45,277.60
Over/Under Est: 51.81% $651,882.55
Amt Left: 51.8% $651,822.25
Delta: -17.94% -$290,529.25
Subcontractor Percentage Amount
PEACHTREE CONSTRUCTION, LTD. 10.88% $137,119.95
HODGES AND SON CONSTRUCTION COMPANY, INC. 6.45% $81,288.94
MORRIS COUNTY CONTRACTORS, L.L.C. 4.20% $52,932.34
PANOLA SIGN & BARRICADE, INC. 1.01% $12,728.97
TORO BRAVO CONSTRUCTION, LLC 0.45% $5,671.32
SOUTHWEST ENVIRONMENT SERVICES LLC 0.18% $2,268.53
Total: 23.17% $292,010.05

Bid Items & Bid Tabulations

57 Total 0 of 57
SMITH  |  CS  |  TYLER  |  0910-16-147  |  01/07/2022  |  $1,258,233.40  |  BR 2020(895)  |  BRIDGE REPL  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
BAKER & COMPANY CONSTRUCTION, LLC
HIGHWAY 19 CONSTRUCTION LLC
PIERCE R & B LLC
FRITCHER CONSTRUCTION SERVICES
EAST TEXAS BRIDGE, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
HODGES AND SON CONSTRUCTION COMPANY, INC.
L. S. EQUIPMENT CO., INC.
PREPARING ROW
STA 7.500 $1,000.000 $1,500.000 $2,285.000 $2,500.000 $1,500.000 $3,075.000 $5,500.000 $4,000.000 $8,000.000 $1,000.000
REMOVING CONC (CURB AND GUTTER)
LF 120.000 $10.000 $20.000 $11.650 $10.000 $25.000 $5.000 $15.000 $10.000 $20.000 $20.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 188.000 $7.000 $15.000 $19.450 $15.000 $20.000 $57.000 $10.000 $10.000 $20.000 $7.000
EXCAVATION (ROADWAY)
CY 275.000 $8.000 $15.000 $24.900 $25.000 $20.000 $8.000 $15.000 $25.000 $20.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 423.000 $20.000 $15.000 $24.300 $30.000 $25.000 $15.000 $25.000 $28.000 $40.000 $25.000
FURNISHING AND PLACING TOPSOIL (4")
SY 763.000 $1.500 $11.000 $9.000 $5.000 $5.000 $2.500 $4.000 $5.700 $5.000 $2.000
BLOCK SODDING
SY 38.000 $5.000 $11.530 $12.850 $5.000 $14.000 $10.250 $13.000 $12.000 $75.000 $5.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 725.000 $0.750 $1.280 $6.450 $5.000 $1.750 $2.560 $1.450 $1.350 $8.000 $0.750
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 382.000 $0.650 $1.250 $6.450 $0.100 $1.550 $2.560 $1.400 $1.350 $5.000 $0.600
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 382.000 $0.630 $1.230 $6.450 $0.100 $1.550 $2.560 $1.400 $1.300 $5.000 $0.650
VEGETATIVE WATERING
MG 16.700 $10.000 $20.000 $120.000 $100.000 $50.000 $100.000 $20.000 $65.000 $1.000 $1.000
CEMENT
TON 27.000 $152.000 $300.000 $262.000 $250.000 $290.000 $223.450 $250.000 $240.000 $300.000 $220.000
CEMENT TREAT (EXIST MATL) (6")
SY 2,003.000 $6.000 $15.000 $14.400 $16.000 $11.000 $2.500 $8.000 $8.250 $15.000 $6.000
CEM STABIL BKFL
CY 430.700 $165.000 $151.000 $181.300 $180.000 $220.000 $140.000 $200.000 $178.000 $250.000 $150.000
TRENCH EXCAVATION PROTECTION
LF 43.000 $3.000 $10.000 $407.450 $10.000 $30.000 $2.500 $50.000 $350.000 $10.000 $2.000
DRILL SHAFT (24 IN)
LF 387.000 $240.000 $240.000 $144.500 $180.000 $245.000 $170.000 $260.000 $265.000 $210.000 $225.000
CL C CONC (ABUT)
CY 47.200 $900.000 $950.000 $1,070.000 $1,000.000 $1,200.000 $1,200.000 $1,075.000 $1,200.000 $1,600.000 $1,240.000
CL C CONC (WINGWALLS)
CY 0.600 $1,300.000 $4,000.000 $2,140.000 $6,000.000 $9,500.000 $1,780.000 $5,000.000 $2,400.000 $3,000.000 $2,900.000
CL E CONC (SEAL SLAB)
CY 17.300 $375.000 $500.000 $749.000 $350.000 $425.000 $800.000 $500.000 $725.000 $500.000 $1,500.000
REINF CONC SLAB (SLAB BEAM)
SF 2,891.000 $19.000 $17.000 $16.600 $15.000 $23.000 $20.000 $18.000 $21.000 $28.000 $24.000
PRESTR CONC SLAB BEAM (4SB12)
LF 316.000 $190.000 $218.000 $212.650 $215.000 $200.000 $170.000 $220.000 $170.000 $205.000 $200.000
PRESTR CONC SLAB BEAM (4SB15)
LF 396.000 $190.000 $211.000 $205.800 $215.000 $192.000 $182.000 $210.000 $170.000 $205.000 $200.000
RIPRAP (CONC)(4 IN)
CY 1.800 $600.000 $1,500.000 $1,070.000 $1,000.000 $2,000.000 $980.000 $1,000.000 $1,800.000 $800.000 $900.000
RIPRAP (CONC)(6 IN)
CY 5.400 $600.000 $700.000 $909.500 $650.000 $690.000 $1,050.000 $800.000 $640.000 $800.000 $870.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 644.000 $130.000 $120.000 $130.650 $160.000 $140.000 $150.000 $165.000 $220.000 $150.000 $149.000
RIPRAP (MOW STRIP)(4 IN)
CY 29.000 $465.000 $700.000 $535.000 $450.000 $575.000 $750.000 $550.000 $660.000 $550.000 $620.000
STR STEEL (MISC NON - BRIDGE)
LB 1,776.000 $6.000 $2.000 $10.700 $10.000 $15.000 $8.000 $18.000 $7.700 $5.000 $21.000
RAIL (TY T223)
LF 228.000 $110.000 $131.000 $155.200 $120.000 $135.000 $200.000 $120.000 $194.000 $125.000 $145.000
RAIL (TY C221)
LF 111.000 $100.000 $225.000 $217.500 $180.000 $150.000 $290.000 $165.000 $248.000 $180.000 $265.000
CONC BOX CULV (9 FT X 9 FT)
LF 129.000 $900.000 $700.000 $907.750 $850.000 $1,100.000 $1,050.000 $1,050.000 $1,100.000 $1,500.000 $975.000
WINGWALL (PW - 1) (HW=12 FT)
EA 2.000 $55,000.000 $40,000.000 $43,870.000 $52,777.000 $32,500.000 $57,500.000 $32,000.000 $35,000.000 $45,000.000 $85,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $30,000.000 $5,000.000 $7,837.500 $10,000.000 $17,500.000 $32,800.000 $10,000.000 $27,000.000 $20,000.000 $89,000.000
MOBILIZATION
LS 1.000 $112,187.190 $100,000.000 $117,150.000 $150,000.000 $125,000.000 $95,000.000 $130,000.000 $250,000.000 $145,000.000 $390,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $2,500.000 $2,000.000 $1,338.000 $1,600.000 $2,900.000 $2,500.000 $3,000.000 $1,800.000 $4,000.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 96.000 $30.000 $40.000 $36.000 $35.000 $33.000 $41.000 $33.000 $31.500 $1.000 $60.000
ROCK FILTER DAMS (REMOVE)
LF 96.000 $10.000 $10.000 $9.600 $10.000 $9.000 $10.250 $9.000 $8.400 $1.000 $10.000
EXCAV (EROSN & SEDMT CONT, IN VEH)
CY 25.000 $34.000 $50.000 $25.000 $30.000 $75.000 $10.000 $50.000 $24.000 $1.000 $75.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 30.000 $65.000 $100.000 $75.000 $10.000 $75.000 $95.000 $75.000 $160.000 $1.000 $125.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,740.000 $2.600 $5.000 $2.950 $3.000 $3.100 $3.100 $3.200 $2.950 $1.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,740.000 $0.800 $2.000 $0.550 $1.000 $0.740 $1.050 $0.750 $0.700 $1.000 $1.000
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 30.000 $90.000 $150.000 $120.000 $50.000 $75.000 $125.000 $100.000 $195.000 $1.000 $125.000
CONC CURB & GUTTER (TY II)
LF 120.000 $30.000 $100.000 $91.000 $75.000 $25.000 $30.000 $35.000 $50.000 $40.000 $75.000
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $21.000 $27.300 $23.000 $25.000 $23.500 $29.000 $29.000 $27.000 $28.000 $29.000
MTL BEAM GD FEN TRANS (TL2)
EA 6.000 $1,500.000 $1,233.750 $803.000 $1,100.000 $825.000 $1,486.250 $1,300.000 $1,250.000 $1,500.000 $100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,600.000 $3,097.500 $2,890.000 $3,000.000 $2,925.000 $3,075.000 $3,300.000 $3,100.000 $3,000.000 $3,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $8,700.000 $11,550.000 $7,010.000 $9,500.000 $7,110.000 $9,500.000 $12,500.000 $11,550.000 $15,000.000 $950.000
WIRE FENCE (TY C)
LF 224.000 $14.000 $40.000 $10.700 $17.000 $20.000 $20.000 $28.000 $16.000 $20.000 $15.000
WIRE FENCE (TY D)
LF 98.000 $10.000 $40.000 $21.400 $21.000 $20.000 $20.000 $55.000 $21.000 $25.000 $15.000
REMOVE SM RD SN SUP&AM
EA 7.000 $100.000 $250.000 $53.500 $100.000 $100.000 $50.000 $50.000 $95.000 $900.000 $150.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 12.000 $25.000 $15.750 $19.260 $24.000 $25.000 $40.000 $20.000 $16.000 $40.000 $50.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 8.000 $20.000 $21.000 $53.500 $50.000 $1.000 $20.000 $30.000 $25.000 $10.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $30.000 $26.250 $26.750 $35.000 $30.000 $51.250 $30.000 $26.000 $40.000 $50.000
D-GR HMA TY-C PG64-22
TON 161.000 $130.000 $202.000 $192.600 $161.000 $170.000 $184.500 $175.000 $185.000 $200.000 $150.000
D-GR HMA TY-D PG64-22
TON 682.000 $160.000 $205.000 $171.200 $161.000 $165.000 $164.000 $150.000 $145.000 $200.000 $150.000
STEEL FENCE (REMOVE)
LF 86.000 $10.000 $10.000 $10.700 $10.000 $10.000 $20.000 $15.000 $10.000 $10.000 $15.000
STEEL FENCE (INSTALL)
LF 92.000 $45.000 $100.000 $107.000 $25.000 $100.000 $50.000 $125.000 $45.000 $60.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 42.000 $110.000 $150.000 $98.500 $100.000 $85.000 $65.000 $150.000 $150.000 $125.000 $135.000
Totals: $1,258,233.400 $1,258,293.700 $1,289,878.180 $1,313,336.400 $1,365,597.050 $1,366,251.490 $1,385,627.850 $1,574,309.100 $1,619,586.700 $1,910,115.950