Show Job Controls
Bid Cobra

SMITH VARIOUS (0910-00-147)

Items: 55

County: SMITH
Length: 0.0000 MILES
Highway: VARIOUS
District: TYLER
Control Number: 0910-00-147
DBE Goal: 4.0%
Project: BR 2025(709)
Guaranty: $60,000.00
Time: 183 WORKING DAYS
Engineer's Estimate: $3,032,844.12
Date: 05/02/2025 (1 year ago)
Contract Number: 5253212
Type: REHABILITATE BRIDGE
Project ID: A00205877
Contract Type: Federal
Project Description: BMIP BRIDGE REHABILITATION AT THE VARIOUS LOCATIONS IN TYLER DISTRICT.ROADWAYS:US 79 EBUS 79 WBUS 175 (SL 7)SH 322SS 147 EBSH 19FM 2966FM 349US 84
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
PAUL SCHNEIDER
JOSH FULTON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$3,032,844.12
Over/Under Est: -7.8% -$236,511.72
Over/Under Est: -4.76% -$144,267.11
Amt Left: 3.3% $92,244.61
Over/Under Est: 4.16% $126,209.98
Amt Left: 12.97% $362,721.70
Delta: -9.36% -$270,477.09
Over/Under Est: 29.58% $897,055.78
Amt Left: 40.54% $1,133,567.50
Delta: -24.40% -$770,845.80
Over/Under Est: 56.4% $1,710,451.33
Amt Left: 69.63% $1,946,963.05
Delta: -20.70% -$813,395.55
Subcontractor Percentage Amount
S & S BRIDGE PAINTING, INC. 14.34% $402,123.34
TEXCO SERVICES, LLC 5.87% $164,606.97
HYDRO TECHNOLOGIES, INC. 1.98% $55,523.31
TRAFFIC HIGHWAY MAINTENANCE, LLC 1.91% $53,560.36
FC TRAFFIC CONTROL, INC. 1.15% $32,248.39
TEXOP CONSTRUCTION 0.64% $17,946.93
EMERY SAPP & SON'S INC. 0.34% $9,534.31
Total: 26.23% $735,543.61

Bid Items & Bid Tabulations

55 Total 0 of 55
SMITH  |  VARIOUS  |  TYLER  |  0910-00-147  |  05/02/2025  |  $3,032,844.12  |  BR 2025(709)  |  REHAB BRIDGE  |  183 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
STRUCTURAL INTEGRITY GROUP LLC
GIBSON & ASSOCIATES, INC.
EAST TEXAS BRIDGE, INC.
HIGHWAY 19 CONSTRUCTION LLC
REMOV CONC (RIPRAP)
CY 1,310.000 $58.000 $10.000 $50.000 $10.000 $50.000 $35.000
REMOV CONC (MEDIANS)
CY 9.300 $81.000 $20.000 $55.000 $250.000 $400.000 $180.000
EMBANK (FNL)(OC)(TY C)
CY 20.000 $47.500 $125.000 $185.000 $100.000 $200.000 $100.000
PLANE ASPH CONC PAV(2" TO 4")
SY 1,219.000 $10.000 $25.000 $22.500 $10.980 $30.000 $25.000
FLOWABLE BACKFILL
CY 17.000 $350.000 $400.000 $705.000 $900.000 $500.000 $350.000
CL B CONC (FLUME)
CY 40.000 $574.000 $700.000 $855.000 $1,150.000 $1,000.000 $750.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 19,073.000 $12.500 $17.000 $11.250 $14.500 $15.000 $25.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 138.000 $250.000 $325.000 $135.000 $195.000 $350.000 $35.000
CONC STR REPAIR (EPOXY MORTAR)
SF 4.000 $200.000 $325.000 $1,000.000 $1,050.000 $650.000 $1,500.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 20.000 $260.560 $325.000 $200.000 $300.000 $300.000 $350.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 72.000 $176.000 $325.000 $190.000 $300.000 $350.000 $550.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 36.000 $450.000 $325.000 $240.000 $300.000 $400.000 $350.000
CONC STR REPAIR (STANDARD)
SF 28.000 $100.000 $300.000 $220.000 $300.000 $400.000 $180.000
RIPRAP (CONC) (CL B) (4 IN)
CY 348.000 $1,239.000 $700.000 $540.000 $530.200 $900.000 $900.000
RIPRAP (MOW STRIP)(4 IN)
CY 104.300 $670.000 $750.000 $610.000 $671.000 $775.000 $550.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 280.000 $220.000 $250.000 $310.000 $255.200 $250.000 $200.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 202.000 $59.250 $60.000 $53.000 $27.500 $65.000 $75.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 1,874.000 $80.000 $60.000 $67.000 $44.000 $75.000 $75.000
RESIZING AND SEALING JOINTS
LF 160.000 $105.000 $55.000 $56.000 $132.000 $75.000 $55.000
CONCRETE OVERLAY (3 IN)
SY 1,219.000 $67.000 $130.000 $100.000 $170.000 $85.000 $150.000
MULTI-LAYER POLYMER OVERLAY
SY 9,238.000 $50.000 $50.000 $43.000 $38.500 $45.000 $155.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 1,247.000 $171.950 $110.000 $185.000 $135.000 $200.000 $245.000
HYDRO-DEMOLITION (1 IN)
SY 1,219.000 $75.000 $85.000 $70.000 $165.000 $90.000 $85.000
SHOT BLASTING
SY 10,485.000 $15.000 $4.000 $4.000 $6.500 $10.000 $15.000
RAISING EXIST STRUCT
EA 1.000 $50,000.000 $75,000.000 $18,200.000 $78,000.000 $60,000.000 $60,000.000
MOBILIZATION
LS 1.000 $275,713.100 $155,000.000 $325,000.000 $388,000.000 $385,000.000 $303,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $10,012.240 $5,000.000 $14,000.000 $16,000.000 $25,000.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $2,500.000 $15,000.000 $18,000.000 $25,000.000 $15,000.000
TMA (STATIONARY)
DAY 216.000 $210.000 $50.000 $10.000 $360.000 $250.000 $500.000
TMA (MOBILE OPERATION)
HR 264.000 $86.330 $50.000 $10.000 $40.000 $50.000 $100.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 352.000 $57.420 $5.000 $35.000 $50.000 $150.000 $275.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,775.000 $42.500 $36.000 $33.350 $29.430 $36.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $2,500.000 $3,200.000 $2,575.000 $1,925.000 $3,000.000 $3,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,500.000 $2,000.000 $1,865.000 $1,375.000 $1,800.000 $2,850.000
REMOVE METAL BEAM GUARD FENCE
LF 1,800.000 $2.670 $5.000 $4.000 $4.680 $4.000 $5.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 4.000 $418.600 $400.000 $280.000 $357.500 $250.000 $350.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,625.000 $4,000.000 $3,415.000 $3,465.000 $3,600.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $850.000 $500.000 $364.000 $550.000 $300.000 $250.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 1,280.000 $1.500 $6.000 $5.600 $5.500 $6.000 $5.000
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 1,280.000 $1.500 $6.000 $5.600 $5.500 $6.000 $5.000
PAVEMENT SLER 6"
LF 16,031.000 $0.500 $0.750 $0.560 $0.550 $0.600 $1.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 1,560.000 $1.300 $4.000 $3.400 $3.300 $3.500 $3.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 5,787.000 $0.500 $2.000 $3.400 $3.300 $3.500 $1.500
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 6,624.000 $0.500 $2.000 $3.400 $3.300 $3.500 $1.500
REFL PAV MRKR TY I-C
EA 78.000 $5.720 $15.000 $6.750 $6.600 $7.000 $10.000
REFL PAV MRKR TY II-A-A
EA 65.000 $5.500 $15.000 $6.750 $6.600 $7.000 $10.000
PAV SURF PREP FOR MRK (6")
LF 16,031.000 $0.030 $0.650 $0.300 $0.280 $0.300 $0.450
REPAIR (STEEL RAIL)
LF 6.000 $170.000 $500.000 $840.000 $500.000 $2,000.000 $250.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 6.000 $852.670 $500.000 $625.000 $500.000 $1,500.000 $350.000
REP STL BRIDGE MEMBER (BEAM)
EA 16.000 $4,688.000 $9,000.000 $8,100.000 $5,000.000 $25,000.000 $10,000.000
REP STL BRIDGE MEMBER (DIAPHRAGM)
EA 1.000 $2,750.000 $2,500.000 $3,500.000 $3,000.000 $30,000.000 $10,000.000
REP STL BRIDGE MEMBER (BEARINGS)
EA 4.000 $154.000 $7,500.000 $11,600.000 $10,100.000 $2,500.000 $25,000.000
STEEL BRIDGE ZONE PAINTING
SF 1,957.000 $25.000 $90.000 $92.600 $82.500 $90.000 $35.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 1.000 $579.000 $300.000 $150.000 $550.000 $1,000.000 $1,500.000
BENT CAP/ABUTMENT CAP CLEANING
EA 5.000 $1,400.000 $500.000 $800.000 $2,800.000 $4,000.000 $5,000.000
Totals: $3,032,844.120 $2,796,332.400 $2,888,577.010 $3,159,054.100 $3,929,899.900 $4,743,295.450
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $137,856.55
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,000.00
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $156,960.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $275,713.10
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) $137,856.55
Total: $711,386.20