SMITH VARIOUS (0910-00-144)
Items: 28
County: SMITH
Length: 0.0000 MILES
Highway: VARIOUS
District: TYLER
Control Number: 0910-00-144
DBE Goal: 0.0%
Project: F 2026(534)
Guaranty: $60,000.00
Time: 199 WORKING DAYS
Engineer's Estimate: $3,297,936.88
Date: 04/07/2026 (2 months ago)
Contract Number: 4263010
Type: BRIDGE MAINTENANCE
Project ID: A00200689
Contract Type: Federal
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SMITH VARIOUS (0910-00-144)
Project Name: N/A
Project: F 2026(534)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS LOCATIONS
Limits To: IN THE TYLER DISTRICT
Project Description: BRIDGE PREVENTATIVE MAINTENANCE
SMITH VARIOUS (0910-00-164)
Project Name: 2026BPM - FC 6
Project: C 910-00-164
Length: 0.0000 MILES
Project Type: BRIDGE MAINTENANCE
Limits From: VARIOUS FC 6 LOCATIONS
Limits To: IN THE TYLER DISTRICT
Project Description: BRIDGE PREVENTATIVE MAINTENANCE FUNCTIONAL CLASS 6 ROADWAYS
Bidders (11)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,297,936.88 | |||
| $1,987,427.29 |
-39.74%
-$1,310,509.59
|
|||
| $2,554,629.00 |
-22.54%
-$743,307.88
|
28.54%
$567,201.71
|
||
| $2,678,002.40 |
-18.8%
-$619,934.48
|
34.75%
$690,575.11
|
-4.83%
-$123,373.40
|
|
| $2,897,721.00 |
-12.14%
-$400,215.88
|
45.8%
$910,293.71
|
-8.20%
-$219,718.60
|
|
| $3,167,161.00 |
-3.97%
-$130,775.88
|
59.36%
$1,179,733.71
|
-9.30%
-$269,440.00
|
|
| $3,247,520.00 |
-1.53%
-$50,416.88
|
63.4%
$1,260,092.71
|
-2.54%
-$80,359.00
|
|
| $3,607,130.40 |
9.38%
$309,193.52
|
81.5%
$1,619,703.11
|
-11.07%
-$359,610.40
|
|
| $3,910,453.52 |
18.57%
$612,516.64
|
96.76%
$1,923,026.23
|
-8.41%
-$303,323.12
|
|
| $3,999,237.00 |
21.26%
$701,300.12
|
101.23%
$2,011,809.71
|
-2.27%
-$88,783.48
|
|
| $4,582,556.00 |
38.95%
$1,284,619.12
|
130.58%
$2,595,128.71
|
-14.59%
-$583,319.00
|
|
| $6,642,746.00 |
101.42%
$3,344,809.12
|
234.24%
$4,655,318.71
|
-44.96%
-$2,060,190.00
|
E
Engineer's Estimate
$3,297,936.88
1
Awarded
$1,987,427.29
Over/Under Est:
-39.74%
-$1,310,509.59
$2,554,629.00
Over/Under Est:
-22.54%
-$743,307.88
Amt Left:
28.54%
$567,201.71
$2,678,002.40
Over/Under Est:
-18.8%
-$619,934.48
Amt Left:
34.75%
$690,575.11
Delta:
-4.83%
-$123,373.40
$2,897,721.00
Over/Under Est:
-12.14%
-$400,215.88
Amt Left:
45.8%
$910,293.71
Delta:
-8.20%
-$219,718.60
$3,167,161.00
Over/Under Est:
-3.97%
-$130,775.88
Amt Left:
59.36%
$1,179,733.71
Delta:
-9.30%
-$269,440.00
$3,247,520.00
Over/Under Est:
-1.53%
-$50,416.88
Amt Left:
63.4%
$1,260,092.71
Delta:
-2.54%
-$80,359.00
$3,607,130.40
Over/Under Est:
9.38%
$309,193.52
Amt Left:
81.5%
$1,619,703.11
Delta:
-11.07%
-$359,610.40
$3,910,453.52
Over/Under Est:
18.57%
$612,516.64
Amt Left:
96.76%
$1,923,026.23
Delta:
-8.41%
-$303,323.12
$3,999,237.00
Over/Under Est:
21.26%
$701,300.12
Amt Left:
101.23%
$2,011,809.71
Delta:
-2.27%
-$88,783.48
$4,582,556.00
Over/Under Est:
38.95%
$1,284,619.12
Amt Left:
130.58%
$2,595,128.71
Delta:
-14.59%
-$583,319.00
$6,642,746.00
Over/Under Est:
101.42%
$3,344,809.12
Amt Left:
234.24%
$4,655,318.71
Delta:
-44.96%
-$2,060,190.00
Bid Items & Bid Tabulations
28
Total
0 of 28
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $20,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $20,000.00 |
| Total: | $60,000.00 |