SMITH VARIOUS (0910-00-143)
Items: 12
County: SMITH
Length: 0.0000 MILES
Highway: VARIOUS
District: TYLER
Control Number: 0910-00-143
DBE Goal: 0.0%
Project: C 910-00-143
Guaranty: $70,000.00
Time: 291 WORKING DAYS
Engineer's Estimate: $3,487,920.00
Date: 04/03/2025 (1 year ago)
Contract Number: 4253014
Type: BRIDGE MAINTENANCE
Project ID: A00200688
Project Description: BRIDGE PREVENTATIVE MAINTENANCE (ROADWAYS LISTED IN PROJECT COMMENTS)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SMITH VARIOUS (0910-00-143)
Project Name: N/A
Project: C 910-00-143
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS LOCATIONS
Limits To: IN THE TYLER DISTRICT
Project Description: BRIDGE PREVENTATIVE MAINTENANCE (ROADWAYS LISTED IN PROJECT COMMENTS)
Informational
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,487,920.00 | |||
| $3,583,067.00 |
2.73%
$95,147.00
|
|||
| $3,925,830.00 |
12.56%
$437,910.00
|
9.57%
$342,763.00
|
||
| $3,991,654.56 |
14.44%
$503,734.56
|
11.4%
$408,587.56
|
-1.68%
-$65,824.56
|
|
| $4,544,831.25 |
30.3%
$1,056,911.25
|
26.84%
$961,764.25
|
-13.86%
-$553,176.69
|
|
| $4,656,858.47 |
33.51%
$1,168,938.47
|
29.97%
$1,073,791.47
|
-2.46%
-$112,027.22
|
|
| $4,682,800.00 |
34.26%
$1,194,880.00
|
30.69%
$1,099,733.00
|
-0.56%
-$25,941.53
|
|
| $4,796,323.75 |
37.51%
$1,308,403.75
|
33.86%
$1,213,256.75
|
-2.42%
-$113,523.75
|
E
Engineer's Estimate
$3,487,920.00
1
Awarded
$3,583,067.00
Over/Under Est:
2.73%
$95,147.00
$3,925,830.00
Over/Under Est:
12.56%
$437,910.00
Amt Left:
9.57%
$342,763.00
$3,991,654.56
Over/Under Est:
14.44%
$503,734.56
Amt Left:
11.4%
$408,587.56
Delta:
-1.68%
-$65,824.56
$4,544,831.25
Over/Under Est:
30.3%
$1,056,911.25
Amt Left:
26.84%
$961,764.25
Delta:
-13.86%
-$553,176.69
$4,656,858.47
Over/Under Est:
33.51%
$1,168,938.47
Amt Left:
29.97%
$1,073,791.47
Delta:
-2.46%
-$112,027.22
$4,682,800.00
Over/Under Est:
34.26%
$1,194,880.00
Amt Left:
30.69%
$1,099,733.00
Delta:
-0.56%
-$25,941.53
$4,796,323.75
Over/Under Est:
37.51%
$1,308,403.75
Amt Left:
33.86%
$1,213,256.75
Delta:
-2.42%
-$113,523.75
| Subcontractor | Percentage | Amount |
|---|---|---|
| TAYLOR CONTRACTING LLC | 8.29% | $297,036.25 |
| Total: | 8.29% | $297,036.25 |
Bid Items & Bid Tabulations
12
Total
0 of 12
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| Total: | $15,000.00 |