Show Job Controls
Bid Cobra

SMITH VARIOUS (0910-00-125)

Items: 77

County: SMITH
Length: 1.0000 MILES
Highway: VARIOUS
District: TYLER
Control Number: 0910-00-125
DBE Goal: 0.0%
Project: F 2026(333)
Guaranty: $68,000.00
Time: 55 WORKING DAYS
Engineer's Estimate: $3,424,377.50
Date: 02/04/2026 (4 months ago)
Contract Number: 2263021
Type: WIDEN ROAD - ADD LANES
Project ID: A00063484
Contract Type: Federal
Project Description: FY 2026 DISTRICT-WIDE THERMO PROGRAM #2
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
FRANCES MERECKA
ENRIQUE MANUEL GONZALEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,424,377.50
$2,466,733.32
Over/Under Est: -27.97% -$957,644.18
$2,746,485.61
Over/Under Est: -19.8% -$677,891.89
Amt Left: 11.34% $279,752.29
Over/Under Est: -19.56% -$669,846.64
Amt Left: 11.67% $287,797.54
Delta: -0.29% -$8,045.25
Subcontractor Percentage Amount
SURFACE PREPARATION TECHNOLOGIES, LLC 2.94% $72,521.96
Total: 2.94% $72,521.96

Bid Items & Bid Tabulations

77 Total 0 of 77
SMITH  |  VARIOUS  |  TYLER  |  0910-00-125  |  02/04/2026  |  $3,424,377.50  |  F 2026(333)  |  WIDEN ROAD - ADD LANES  |  55 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE-A-ZONE, LLC
STRIPE LINES, INC.
STRIPING TECHNOLOGY, L.P.
MOBILIZATION
LS 1.000 $312,000.000 $4,000.000 $28,000.000 $15,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $1,500.000 $500.000 $900.000 $1,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 6.000 $125.000 $100.000 $15.000 $325.000
TMA (STATIONARY)
DAY 128.000 $200.000 $1.000 $100.000 $200.000
TMA (MOBILE OPERATION)
DAY 146.000 $200.000 $1.000 $35.000 $200.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 268,020.000 $0.200 $0.170 $0.220 $0.180
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 158,960.000 $0.200 $0.170 $0.220 $0.200
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 14,170.000 $0.850 $0.500 $0.520 $1.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 12,710.000 $1.000 $0.900 $0.710 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 179,810.000 $0.850 $0.600 $0.710 $0.880
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 11,990.000 $6.000 $2.000 $3.300 $3.800
REFL PAV MRK TY I (W)18"(SLD)(100MIL)
LF 950.000 $6.500 $6.000 $4.250 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 44,080.000 $6.750 $4.750 $5.150 $4.550
REFL PAV MRK TY I (Y)6"(DOT)(100MIL)
LF 1,380.000 $0.850 $0.500 $0.520 $1.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 14,550.000 $0.750 $0.900 $0.460 $1.000
PAVEMENT SLER 6"
LF 200,757.000 $0.200 $0.100 $0.220 $0.200
PAVEMENT SLER 8"
LF 22,517.000 $0.300 $0.100 $0.270 $0.350
PAVEMENT SLER 12"
LF 1,505.000 $1.000 $1.000 $0.410 $2.200
PAVEMENT SLER 18"
LF 170.000 $2.000 $2.000 $5.320 $3.500
PAVEMENT SLER 24"
LF 3,910.000 $3.000 $2.000 $5.430 $3.500
PAVEMENT SLER (ARROW)
EA 101.000 $50.000 $40.000 $53.720 $65.000
PAVEMENT SLER (WORD)
EA 82.000 $50.000 $40.000 $54.550 $85.000
PAVEMENT SLER (YLD TRI)
EA 70.000 $10.000 $10.000 $50.040 $25.000
PAVEMENT SLER (NUMBER)
EA 4.000 $50.000 $50.000 $50.040 $250.000
REFL PAV MRK TY I (W)6"(BRK)(060MIL)
LF 43,410.000 $0.350 $0.330 $0.320 $0.380
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 214,140.000 $0.500 $0.420 $0.470 $0.460
REFL PAV MRK TY I (W)6"(SLD)(060MIL)
LF 131,280.000 $0.350 $0.320 $0.320 $0.350
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 1,041,450.000 $0.500 $0.400 $0.470 $0.370
REFL PAV MRK TY I (Y)6"(BRK)(060MIL)
LF 15,670.000 $0.350 $0.330 $0.320 $0.380
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 268,020.000 $0.500 $0.410 $0.470 $0.460
REFL PAV MRK TY I (Y)6"(SLD)(060MIL)
LF 166,170.000 $0.350 $0.320 $0.320 $0.350
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 1,070,050.000 $0.500 $0.400 $0.470 $0.370
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 1,140.000 $6.000 $2.750 $2.730 $5.000
PREFAB PM TY C (W)(ARROW)
EA 961.000 $190.000 $175.000 $151.910 $185.500
PREFAB PM TY C (W)(DBL ARROW)
EA 12.000 $285.000 $275.000 $215.050 $235.500
PREFAB PM TY C (W)(TPL ARROW)
EA 1.000 $350.000 $325.000 $288.560 $330.500
PREFAB PM TY C (W)(UTURN ARROW)
EA 3.000 $310.000 $275.000 $222.680 $300.500
PREFAB PM TY C (W)(LN REDUCT ARROW)
EA 40.000 $350.000 $375.000 $275.070 $275.500
PREFAB PM TY C (W)(NUMBER)
EA 25.000 $350.000 $300.000 $105.380 $275.500
PREFAB PM TY C (W)(WORD)
EA 610.000 $210.000 $215.000 $192.150 $205.500
PREFAB PM TY C (W)(RR XING)
EA 18.000 $500.000 $450.000 $289.260 $555.500
PREFAB PM TY C (W)(18")(YLD TRI)
EA 129.000 $25.000 $30.000 $66.630 $28.500
PREFAB PM TY C (W)(36")(YLD TRI)
EA 492.000 $50.000 $40.000 $70.970 $33.750
PREFAB PM TY C (W)(BIKE ARROW)
EA 6.000 $200.000 $200.000 $91.690 $200.000
PREFAB PM TY C (W)(BIKE SYMBOL)
EA 6.000 $200.000 $225.000 $132.470 $200.000
REFL PAV MRKR TY I-A
EA 1,924.000 $4.000 $4.000 $3.130 $4.000
REFL PAV MRKR TY I-C
EA 9,365.000 $4.000 $3.950 $3.130 $4.000
REFL PAV MRKR TY II-A-A
EA 17,759.000 $4.000 $3.950 $3.130 $4.000
REFL PAV MRKR TY II-C-R
EA 11,695.000 $4.000 $3.950 $3.130 $4.200
TRAFFIC BUTTON TY W
EA 4,206.000 $4.000 $3.750 $2.830 $3.650
TRAFFIC BUTTON TY B
EA 4,271.000 $4.000 $3.750 $2.830 $3.650
ELIM EXT PM & MRKS (6")
LF 303,527.000 $0.500 $0.310 $0.430 $0.630
ELIM EXT PM & MRKS (8")
LF 23,925.000 $0.600 $0.500 $0.550 $0.750
ELIM EXT PM & MRKS (12")
LF 21,935.000 $2.000 $2.500 $0.710 $2.100
ELIM EXT PM & MRKS (18")
LF 170.000 $2.500 $2.000 $2.420 $2.650
ELIM EXT PM & MRKS (24")
LF 3,990.000 $3.500 $3.000 $2.440 $3.150
ELIM EXT PM & MRKS (ARROW)
EA 146.000 $75.000 $80.000 $60.940 $70.500
ELIM EXT PM & MRKS (DBL ARROW)
EA 5.000 $145.000 $80.000 $81.000 $100.500
ELIM EXT PM & MRKS (NUMBER)
EA 5.000 $150.000 $80.000 $43.240 $150.500
ELIM EXT PM & MRKS (WORD)
EA 90.000 $135.000 $80.000 $60.940 $90.500
ELIM EXT PM & MRKS (RR XING)
EA 18.000 $215.000 $150.000 $102.240 $275.500
ELIM EXT PM & MRKS (18")(YLD TRI)
EA 15.000 $10.000 $20.000 $7.840 $22.500
ELIM EXT PM & MRKS (36")(YLD TRI)
EA 93.000 $15.000 $20.000 $13.740 $25.500
PAV SURF PREP FOR MRK (6")
LF 13,840.000 $0.050 $0.010 $0.040 $0.100
PAV SURF PREP FOR MRK (8")
LF 1,940.000 $0.100 $0.010 $0.040 $0.200
PAV SURF PREP FOR MRK (12")
LF 1,505.000 $0.500 $0.010 $0.510 $0.500
PAV SURF PREP FOR MRK (24")
LF 350.000 $1.000 $0.010 $0.940 $1.500
PAV SURF PREP FOR MRK (ARROW)
EA 18.000 $15.000 $10.000 $46.970 $55.500
PAV SURF PREP FOR MRK (NUMBER)
EA 4.000 $25.000 $10.000 $46.970 $55.500
PAV SURF PREP FOR MRK (WORD)
EA 13.000 $15.000 $10.000 $46.970 $75.500
MLTPLY PV MK W/WTY (W) (6") (SLD)
LF 41,770.000 $0.650 $0.500 $0.820 $0.680
MLTPLY PV MK W/WTY (W) (6") (BRK)
LF 9,490.000 $0.800 $0.620 $0.820 $0.720
MLTPLY PV MK W/WTY (W) (6") (DOT)
LF 410.000 $1.250 $0.700 $0.820 $2.200
MLTPLY PV MK W/WTY (Y) (6") (SLD)
LF 44,960.000 $0.650 $0.500 $0.820 $0.680
MLTPLY PV MK W/WTY (Y) (6") (BRK)
LF 6,430.000 $0.800 $0.620 $0.820 $0.720
MLTPLY PV MK W/WTY (W) (8") (SLD)
LF 1,070.000 $1.500 $0.800 $1.240 $1.100
MLTPLY PV MK W/WTY (W) (8") (DOT)
LF 120.000 $1.800 $1.000 $1.240 $2.200
Totals: $3,424,377.500 $2,466,733.320 $2,746,485.610 $2,754,530.860
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $3,000.00