SMITH SH 64 (0245-06-089)

Items: 21

County: SMITH
Length: N/A
Highway: SH 64
District: TYLER
Control Number: 0245-06-089
DBE Goal: 0.0%
Project: STP 2024(856)HES
Guaranty: N/A
Time: 70 WORKING DAYS
Engineer's Estimate: $526,765.50
Date: 04/05/2024 (2 years ago)
Contract Number: N/A
Type: INSTALL ILLUMINATION
Mail/Deliver Bids To: N/A
JUANITA DANIELSWEST
STEVEN SWINDELL
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$526,765.50
$497,607.50
Over/Under Est: -5.54% -$29,158.00
$556,665.78
Over/Under Est: 5.68% $29,900.28
Amt Left: 11.87% $59,058.28
Over/Under Est: 10.53% $55,488.50
Amt Left: 17.01% $84,646.50
Delta: -4.60% -$25,588.22
Over/Under Est: 11.17% $58,832.00
Amt Left: 17.68% $87,990.00
Delta: -0.57% -$3,343.50
Over/Under Est: 12.08% $63,607.00
Amt Left: 18.64% $92,765.00
Delta: -0.82% -$4,775.00
Subcontractor Percentage Amount
KDT ELECTRIC, LLC 20.21% $100,566.48
SCHUSTER MULCH & CONSTRUCTION, LLC 6.03% $30,005.73
B B UNDERGROUND, LLC 3.22% $16,022.96
AWP SAFETY 1.06% $5,274.64
Total: 30.52% $151,869.81

Bid Items & Bid Tabulations

21 Total 0 of 21
SMITH  |  SH 64  |  TYLER  |  0245-06-089  |  04/05/2024  |  $526,765.50  |  STP 2024(856)HES  |  INSTL ILLUM  |  70 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MARCOM'S MOWING SERVICE, LLC
YUNEX LLC
FNH CONSTRUCTION, LLC
STRIPING TECHNOLOGY, L.P.
RISE UP CONSTRUCTION LLC
PREPARING ROW
STA 37.000 $1,600.000 $2,850.000 $412.700 $1,400.000 $6,000.000 $3,900.000
DRILL SHAFT (30 IN)
LF 40.000 $325.000 $480.000 $1,029.800 $450.000 $250.000 $500.000
RIPRAP (CONC)(CL B)
CY 1.400 $2,500.000 $850.000 $1,948.200 $1,500.000 $450.000 $1,000.000
MOBILIZATION
LS 1.000 $53,500.000 $50,000.000 $63,390.700 $60,000.000 $30,000.000 $52,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,500.000 $4,000.000 $13,963.700 $10,000.000 $6,500.000 $12,000.000
IN RD IL (TY SA) 40T-12 (250W EQ) LED
EA 4.000 $8,500.000 $8,250.000 $5,518.900 $12,500.000 $6,700.000 $6,500.000
CONDT (PVC) (SCH 40) (2")
LF 685.000 $16.750 $20.000 $23.700 $20.000 $12.000 $20.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,146.000 $36.000 $30.000 $31.800 $50.000 $35.000 $42.000
ELEC CONDR (NO.8) BARE
LF 2,391.000 $3.250 $2.500 $2.400 $3.000 $3.000 $3.000
ELEC CONDR (NO.8) INSULATED
LF 6,187.000 $3.000 $3.000 $2.500 $3.000 $3.500 $2.500
GROUND BOX TY A (122311)W/APRON
EA 16.000 $1,200.000 $1,560.000 $3,431.300 $1,500.000 $1,000.000 $1,500.000
ELC SRV TY T 120/240 000(NS)GS(L)SP(O)
EA 3.000 $7,000.000 $6,950.000 $9,679.500 $9,500.000 $5,200.000 $4,500.000
ALUMINUM SIGNS (TY A)
SF 294.000 $36.000 $28.500 $37.600 $30.000 $25.000 $60.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $750.000 $850.000 $1,179.500 $1,500.000 $1,000.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 14.000 $225.000 $110.000 $187.000 $500.000 $250.000 $250.000
REMOVING TRAFFIC SIGNALS
EA 2.000 $1,000.000 $8,500.000 $5,918.900 $6,500.000 $4,800.000 $1,000.000
VEH SIG SEC (12")LED(YEL)
EA 16.000 $315.000 $315.000 $384.600 $350.000 $285.000 $700.000
VEH SIG SEC (12")LED(RED)
EA 12.000 $315.000 $315.000 $384.600 $350.000 $5,500.000 $500.000
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 6.000 $12,000.000 $6,200.000 $9,138.700 $9,500.000 $8,500.000 $7,740.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 8.000 $15,000.000 $8,400.000 $11,637.200 $12,500.000 $300.000 $7,740.000
TMA (STATIONARY)
DAY 50.000 $325.000 $250.000 $235.300 $250.000 $300.000 $500.000
Totals: $526,765.500 $497,607.500 $556,665.780 $582,254.000 $585,597.500 $590,372.500