SMITH FM 1253 (0203-08-016)

Items: 16

County: SMITH
Length: N/A
Highway: FM 1253
District: TYLER
Control Number: 0203-08-016
DBE Goal: N/A
Project: STP 2019(619)HES
Guaranty: N/A
Time: 84 WORKING DAYS
Engineer's Estimate: $1,178,935.60
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: CENTERLINE & EDGELINE PROFILE PAV MRK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,178,935.60
$706,776.90
Over/Under Est: -40.05% -$472,158.70
$769,486.35
Over/Under Est: -34.73% -$409,449.25
Amt Left: 8.87% $62,709.45
Over/Under Est: -22.16% -$261,288.90
Amt Left: 29.84% $210,869.80
Delta: -19.25% -$148,160.35
Over/Under Est: -16.92% -$199,502.40
Amt Left: 38.58% $272,656.30
Delta: -6.73% -$61,786.50
Over/Under Est: 7.75% $91,344.80
Amt Left: 79.73% $563,503.50
Delta: -29.70% -$290,847.20

Bid Items & Bid Tabulations

16 Total 0 of 16
SMITH  |  FM 1253  |  TYLER  |  0203-08-016  |  03/06/2019  |  $1,178,935.60  |  STP 2019(619)HES  |  CENTERLINE & EDGELINE PROFILE PAV MR...  |  84 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CENTERLINE TECHNOLOGIES, LLC
STRIPE-A-ZONE, INC.
STRIPING TECHNOLOGY, L.P.
TOTAL HIGHWAY MAINTENANCE, LLC
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $10.000 $1.000 $26,250.000 $75,000.000 $55,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $1.000 $9,150.000 $5,000.000 $4,500.000 $21,500.000
PAVEMENT SEALER 4"
LF 600.000 $0.200 $1.000 $1.000 $0.500 $1.000 $5.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 5,700.000 $0.300 $0.270 $0.400 $0.500 $0.470 $0.370
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 12,100.000 $0.300 $0.270 $0.310 $0.450 $0.410 $0.320
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 12,040.000 $0.300 $0.270 $0.400 $0.500 $0.470 $0.370
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 182,790.000 $0.300 $0.250 $0.310 $0.450 $0.410 $0.320
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 715,990.000 $0.850 $0.540 $0.515 $0.580 $0.650 $0.740
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 16,920.000 $1.250 $0.550 $0.550 $1.000 $0.750 $0.950
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 390,820.000 $1.000 $0.550 $0.515 $0.580 $0.650 $0.740
REFL PAV MRKR TY II-A-A
EA 8,643.000 $2.700 $3.000 $2.550 $3.400 $4.000 $3.800
REFL PAV MRKR TY II-C-R
EA 553.000 $3.000 $3.000 $2.550 $3.400 $4.000 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 600.000 $0.450 $10.000 $1.000 $1.000 $1.000 $17.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 1,570.000 $3.000 $5.000 $7.950 $12.000 $7.000 $9.000
TMA (STATIONARY)
EA 2.000 $8,000.000 $1.000 $300.000 $1,000.000 $2,500.000 $2,500.000
TMA (MOBILE OPERATION)
DAY 84.000 $220.000 $1.000 $45.000 $50.000 $275.000 $825.000
Totals: $1,178,935.600 $706,776.900 $769,486.350 $917,646.700 $979,433.200 $1,270,280.400