Show Job Controls
Bid Cobra

SHELBY FM 2261 (1409-03-020)

Items: 65

County: SHELBY
Length: N/A
Highway: FM 2261
District: LUFKIN
Control Number: 1409-03-020
DBE Goal: N/A
Project: BR 2021(582)
Guaranty: N/A
Time: 191 WORKING DAYS
Engineer's Estimate: $1,222,602.65
Date: 06/03/2021 (5 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$1,222,602.65
$1,320,204.74
Over/Under Est: 7.98% $97,602.09
Over/Under Est: 17.53% $214,277.66
Amt Left: 8.84% $116,675.57
Over/Under Est: 21.36% $261,177.11
Amt Left: 12.39% $163,575.02
Delta: -3.26% -$46,899.45
Over/Under Est: 52.02% $635,941.85
Amt Left: 40.78% $538,339.76
Delta: -25.26% -$374,764.74

Bid Items & Bid Tabulations

65 Total 0 of 65
SHELBY  |  FM 2261  |  LUFKIN  |  1409-03-020  |  06/03/2021  |  $1,222,602.65  |  BR 2021(582)  |  BRIDGE REPL  |  191 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONGVIEW BRIDGE AND ROAD, LTD.
STATELINE CONSTRUCTION, LLC
DREWERY CONSTRUCTION COMPANY, INCORPORATED
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 16.000 $2,800.000 $2,600.000 $800.000 $5,600.000 $3,500.000
REMOVING STAB BASE AND ASPH PAV (6")
CY 1,302.000 $10.000 $2.000 $6.250 $15.000 $25.000
EXCAVATION (ROADWAY)
CY 4,860.000 $10.000 $8.700 $11.000 $9.000 $25.000
SUBGRADE WIDENING (ORD COMP)
STA 6.000 $500.000 $595.000 $2,000.000 $150.000 $1,000.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 11,347.000 $8.000 $11.800 $15.500 $15.000 $25.000
FURNISHING AND PLACING TOPSOIL (4")
SY 16,101.000 $1.500 $1.700 $3.500 $2.250 $0.500
BROADCAST SEED (TEMP) (WARM)
SY 8,051.000 $0.150 $0.120 $0.250 $0.120 $0.500
BROADCAST SEED (TEMP) (COOL)
SY 8,051.000 $0.150 $0.120 $0.250 $0.120 $0.500
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 16,101.000 $0.350 $0.350 $0.480 $0.320 $0.500
VEGETATIVE WATERING
MG 645.000 $12.500 $1.000 $14.000 $25.000 $1.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 645.000 $1.000 $2.200 $4.250 $2.050 $2.000
FL BS (RDWY DEL) (TY A GR 1-2)
TON 2,677.000 $45.000 $45.000 $52.500 $48.000 $55.000
CEMENT
TON 93.000 $180.000 $220.000 $200.000 $185.000 $225.000
CEMENT TREAT(MX EXST MTL & NW BS)(12")
SY 804.000 $3.750 $2.500 $13.250 $5.000 $15.000
CEMENT TREAT (NEW BASE)(12")
SY 4,353.000 $4.000 $2.500 $12.750 $3.500 $15.000
PRIME COAT (RC-250)
GAL 1,290.000 $4.000 $0.010 $22.500 $0.010 $10.000
ASPH (RC-250)
TON 6.000 $900.000 $1,800.000 $625.000 $1,400.000 $2,500.000
AGGR (TY-PE, E, L OR PL GR 3)
CY 45.000 $120.000 $246.000 $575.000 $335.000 $500.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 42.000 $115.000 $254.000 $575.000 $375.000 $500.000
AGGR (TY E OR L GR 5)
CY 39.000 $115.000 $214.000 $575.000 $365.000 $275.000
ASPH (AC-15P, AC-10-2TR, OR CRS-2P)
TON 20.000 $900.000 $970.000 $3,500.000 $935.000 $2,500.000
CEM STABIL BKFL
CY 101.500 $200.000 $210.000 $225.000 $185.000 $225.000
DRILL SHAFT (36 IN)
LF 449.000 $270.000 $247.500 $235.000 $215.000 $185.000
CL C CONC (ABUT)
CY 37.800 $1,000.000 $1,000.000 $800.000 $900.000 $1,200.000
CL C CONC (CAP)
CY 30.000 $1,000.000 $1,000.000 $850.000 $930.000 $1,200.000
CL C CONC (COLUMN)
CY 8.400 $1,000.000 $1,000.000 $1,600.000 $980.000 $1,200.000
REINF CONC SLAB
SF 5,100.000 $20.000 $25.000 $16.000 $17.500 $24.000
APPROACH SLAB
CY 51.400 $450.000 $660.000 $500.000 $515.000 $600.000
PRESTR CONC GIRDER (TX28)
LF 594.000 $150.000 $150.000 $155.000 $160.000 $200.000
RIPRAP (CONC)(5 IN)
CY 71.000 $400.000 $425.000 $335.000 $412.000 $550.000
RAIL (TY T223)
LF 332.000 $90.000 $100.000 $110.000 $93.000 $120.000
ARMOR JOINT (SEALED)
LF 60.000 $75.000 $110.000 $105.000 $100.000 $80.000
RC PIPE (CL III)(18 IN)
LF 90.000 $50.000 $71.500 $55.000 $72.000 $75.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $700.000 $825.000 $900.000 $720.000 $2,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $15,000.000 $20,000.000 $19,999.000 $15,500.000 $25,000.000
REMOV STR (PIPE)
EA 1.000 $500.000 $540.000 $2,000.000 $412.000 $500.000
MOBILIZATION
LS 1.000 $110,000.000 $110,000.000 $50,000.000 $210,000.000 $170,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $2,500.000 $1,600.000 $1,100.000 $1,900.000 $2,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $35.000 $41.250 $32.500 $39.000 $1.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $10.000 $8.800 $10.000 $8.250 $1.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $15.000 $20.000 $25.000 $33.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $5.000 $12.000 $8.250 $1.000
CONSTRUCTION PERIMETER FENCE
LF 400.000 $6.000 $4.400 $12.750 $4.100 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,474.000 $3.000 $3.150 $3.250 $3.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,474.000 $1.000 $0.850 $2.000 $0.800 $1.000
DRIVEWAYS (SURF TREAT)
SY 133.000 $30.000 $78.000 $52.500 $40.000 $60.000
MTL W-BEAM GD FEN (TIM POST)
LF 575.000 $23.000 $25.300 $27.250 $24.000 $24.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,625.000 $1,843.750 $2,500.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 950.000 $3.000 $2.750 $2.000 $2.600 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,600.000 $2,695.000 $3,250.000 $2,500.000 $2,800.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $275.000 $200.000 $200.000 $500.000
WIRE FENCE (TY A)
LF 567.000 $15.000 $14.850 $13.500 $14.000 $20.000
GATE (TY 1)
EA 2.000 $2,000.000 $935.000 $1,000.000 $900.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 4.000 $400.000 $430.000 $575.000 $400.000 $800.000
REMOVE SM RD SN SUP&AM
EA 6.000 $100.000 $82.000 $200.000 $100.000 $500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $20.000 $16.500 $18.750 $16.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $30.000 $30.000 $31.250 $28.000 $30.000
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 3,320.000 $0.750 $3.300 $1.510 $2.050 $4.000
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 3,320.000 $0.750 $3.300 $1.510 $2.050 $4.000
REFL PAV MRKR TY II-A-A
EA 82.000 $3.000 $27.500 $7.540 $10.300 $25.000
PAV SURF PREP FOR MRK (4")
LF 190.000 $0.200 $3.300 $1.510 $4.100 $5.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 30.000 $120.000 $225.000 $250.000 $345.000 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $15,000.000 $7,000.000 $10,300.000 $20,000.000
TMA (STATIONARY)
DAY 20.000 $250.000 $150.000 $175.000 $250.000 $200.000
TMA (MOBILE OPERATION)
DAY 20.000 $45.000 $150.000 $350.000 $100.000 $200.000
Totals: $1,222,602.650 $1,320,204.740 $1,436,880.310 $1,483,779.760 $1,858,544.500