Show Job Controls
Bid Cobra

SHELBY COUNTY ROAD 3689 (0911-39-074)

Items: 53

County: SHELBY
Length: 0.0000 MILES
Highway: COUNTY ROAD 3689
District: LUFKIN
Control Number: 0911-39-074
DBE Goal: 4.0%
Project: BR 2B23(242)
Guaranty: $44,000.00
Time: 260 WORKING DAYS
Engineer's Estimate: $2,163,444.15
Date: 08/07/2025 (10 months ago)
Contract Number: 8253016
Type: BRIDGE REPLACEMENT
Project ID: A00185701
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RANDAL COOPER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$2,163,444.15
Over/Under Est: -24.65% -$533,346.15
$1,695,870.85
Over/Under Est: -21.61% -$467,573.30
Amt Left: 4.03% $65,772.85
$1,854,462.38
Over/Under Est: -14.28% -$308,981.77
Amt Left: 13.76% $224,364.38
Delta: -9.35% -$158,591.53
Over/Under Est: -9.15% -$197,925.45
Amt Left: 20.58% $335,420.70
Delta: -5.99% -$111,056.32
Over/Under Est: -8.52% -$184,369.65
Amt Left: 21.41% $348,976.50
Delta: -0.69% -$13,555.80
Over/Under Est: -7.66% -$165,745.20
Amt Left: 22.55% $367,600.95
Delta: -0.94% -$18,624.45
$2,052,166.32
Over/Under Est: -5.14% -$111,277.83
Amt Left: 25.89% $422,068.32
Delta: -2.73% -$54,467.37
$2,087,399.25
Over/Under Est: -3.51% -$76,044.90
Amt Left: 28.05% $457,301.25
Delta: -1.72% -$35,232.93
Subcontractor Percentage Amount
MORRIS COUNTY CONTRACTORS, L.L.C. 3.33% $54,282.26
PANOLA SIGN & BARRICADE, INC. 1.08% $17,605.06
TORO BRAVO CONSTRUCTION, LLC 0.90% $14,670.88
CAP RIVER LLC 0.67% $10,921.66
HOUSTON SAWING & DRILLING 0.55% $8,965.54
Total: 6.53% $106,445.40

Bid Items & Bid Tabulations

53 Total 0 of 53
SHELBY  |  COUNTY ROAD 3689  |  LUFKIN  |  0911-39-074  |  08/07/2025  |  $2,163,444.15  |  BR 2B23(242)  |  BRIDGE REPL  |  260 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
THK CONSTRUCTION LLC
TALBERT COMPANIES LLC
TRUE ROADS CONSTRUCTION, LLC
BLACKSMITH VENTURES LLC
TEXAS STEEL INDUSTRIAL PLACING, LLC
LAKEY, INC.
SKYLINE BRIDGE LLC
PREPARING ROW
STA 12.750 $2,000.000 $3,000.000 $2,000.000 $3,000.000 $3,000.000 $4,705.000 $2,000.000 $3,504.000 $3,800.000
EXCAV (ROADWAY)
CY 977.000 $20.000 $20.000 $18.000 $26.000 $20.000 $5.000 $25.000 $22.840 $18.000
EMBANK (FNL)(OC)(TY B)
CY 746.000 $30.000 $20.000 $18.000 $31.000 $32.000 $25.000 $30.000 $43.750 $45.000
FURN & PLACE TOPSOIL (4")
SY 2,743.000 $4.000 $3.000 $3.500 $9.000 $5.000 $5.000 $3.000 $3.840 $5.000
BLOCK SODDING
SY 624.000 $10.000 $8.000 $9.630 $9.000 $12.000 $15.000 $8.000 $9.450 $8.500
BROADCAST SEED (TEMP_WARM)
SY 1,645.000 $2.000 $0.500 $1.070 $1.000 $1.200 $0.500 $1.000 $0.960 $1.250
BROADCAST SEED (TEMP_COOL)
SY 1,645.000 $2.000 $0.500 $1.070 $1.000 $1.200 $0.500 $1.000 $0.960 $1.250
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 3,289.000 $2.500 $1.500 $1.560 $1.450 $1.750 $0.500 $1.250 $0.540 $1.250
VEGETATIVE WATERING
TGL 132.000 $10.000 $1.000 $10.000 $50.000 $22.000 $10.000 $10.000 $33.120 $1.000
SOIL RET BLKT(SL_MOD_SAND_SHORT_ROLL)
SY 140.000 $6.000 $4.000 $7.490 $7.000 $8.400 $10.000 $10.000 $4.800 $10.000
FL BS (CMP IN PLC)(TY D GR 1-2) (4")
SY 1,372.000 $40.000 $35.000 $40.000 $31.500 $25.000 $40.000 $25.000 $38.400 $65.000
FL BS (CMP IN PLC)(TY D GR 1-2) (6")
SY 1,288.000 $50.000 $40.000 $40.000 $31.500 $32.000 $40.000 $30.000 $38.400 $75.000
ASPH (RC-250)
TON 1.420 $20,000.000 $5,000.000 $3,521.000 $7,010.050 $4,000.000 $2,450.000 $2,000.000 $1,728.000 $3,800.000
AGGR (TY E OR L, GR-5)
CY 10.000 $1,500.000 $1,500.000 $500.000 $874.500 $850.000 $500.000 $1,000.000 $1,440.000 $2,500.000
SP MIXES SP-C SAC-B PG64-22
TON 148.000 $450.000 $200.000 $300.000 $180.000 $280.000 $200.000 $250.000 $336.000 $400.000
CEM STABIL BKFL
CY 151.000 $350.000 $300.000 $350.000 $213.000 $350.000 $250.000 $250.000 $336.000 $325.000
DRILL SHAFT (18 IN)
LF 168.000 $300.000 $140.000 $206.110 $145.000 $375.000 $325.000 $400.000 $186.720 $175.000
DRILL SHAFT (30 IN)
LF 417.000 $325.000 $230.000 $266.630 $230.000 $495.000 $425.000 $500.000 $336.000 $300.000
DRILL SHAFT (36 IN)
LF 252.000 $390.000 $230.000 $301.470 $250.000 $460.000 $390.000 $550.000 $366.000 $400.000
CL C CONC (ABUT)
CY 97.600 $1,200.000 $1,400.000 $1,050.000 $1,350.000 $1,400.000 $2,500.000 $1,250.000 $1,308.000 $1,400.000
REINF CONC SLAB
SF 1,950.000 $30.000 $30.000 $30.000 $29.000 $40.000 $22.000 $28.000 $29.760 $31.500
REINF CONC SLAB (BOX BEAM)
SF 3,402.000 $30.000 $25.000 $21.000 $28.000 $25.000 $22.000 $25.000 $29.760 $28.000
SHEAR KEY
CY 17.200 $900.000 $600.000 $800.000 $750.000 $565.000 $1,000.000 $650.000 $768.000 $800.000
PRESTR CONC GIRDER (TX28)
LF 297.690 $425.000 $300.000 $322.520 $207.220 $305.000 $275.000 $330.000 $433.920 $350.000
PRESTR CONC BOX BEAM (4B20)
LF 516.000 $350.000 $310.000 $305.210 $244.950 $295.000 $300.000 $310.000 $311.040 $325.000
PRESTR CONC BOX BEAM (5B20)
LF 258.000 $350.000 $310.000 $366.060 $244.950 $295.000 $300.000 $395.000 $311.040 $350.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 703.000 $290.000 $225.000 $200.000 $216.000 $200.000 $225.000 $200.000 $225.600 $225.000
RAIL (TY T223)
LF 530.000 $200.000 $150.000 $180.000 $165.000 $140.000 $175.000 $150.000 $144.000 $175.000
ARMOR JOINT (SEALED)
LF 139.000 $155.000 $190.000 $150.000 $165.000 $140.000 $75.000 $150.000 $192.000 $125.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $20,000.000 $5,000.000 $5,000.000 $15,000.000 $13,500.000 $20,000.000 $28,000.000 $25,152.000 $15,000.000
MOBILIZATION
LS 1.000 $200,000.000 $140,000.000 $160,000.000 $343,200.000 $200,000.000 $225,000.000 $200,000.000 $200,000.000 $190,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $2,000.000 $1,800.000 $1,008.060 $2,800.000 $2,000.000 $263.000 $1,250.000 $5,000.000 $3,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 112.000 $50.000 $1.000 $42.800 $40.000 $48.000 $50.000 $40.000 $52.120 $45.000
ROCK FILTER DAMS (REMOVE)
LF 112.000 $15.000 $1.000 $14.980 $14.000 $17.000 $1.000 $10.000 $16.340 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 305.000 $30.000 $1.000 $42.800 $40.000 $48.000 $1.000 $40.000 $32.640 $10.000
CONSTRUCTION EXITS (REMOVE)
SY 305.000 $10.000 $1.000 $13.910 $13.000 $16.000 $1.000 $10.000 $12.140 $1.000
CONSTRUCTION PERIMETER FENCE
LF 281.000 $12.000 $2.000 $6.420 $6.000 $7.000 $15.000 $6.000 $10.360 $8.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,469.000 $4.000 $1.000 $4.280 $4.000 $5.000 $4.000 $5.000 $4.560 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,469.000 $1.100 $1.000 $1.070 $1.000 $1.500 $1.000 $2.000 $1.250 $1.500
DRIVEWAYS (ACP)
SY 20.000 $100.000 $105.000 $300.000 $77.000 $120.000 $200.000 $200.000 $87.500 $200.000
DRIVEWAYS (BASE)
SY 30.000 $60.000 $60.000 $40.000 $35.000 $95.000 $75.000 $80.000 $86.400 $200.000
MTL W-BEAM GD FEN (TIM POST)
LF 512.500 $35.000 $25.000 $25.920 $23.000 $28.000 $29.000 $26.000 $27.490 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,600.000 $1,658.500 $1,575.000 $1,900.000 $2,379.000 $2,000.000 $2,275.200 $1,850.000
MTL BEAM GD FEN TRANS (TL2)
EA 8.000 $1,900.000 $1,200.000 $1,257.250 $1,175.000 $1,500.000 $1,755.000 $1,600.000 $1,344.000 $1,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,500.000 $1,300.000 $1,364.250 $1,300.000 $1,500.000 $1,500.000 $1,725.000 $1,440.000 $1,650.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,500.000 $3,000.000 $3,210.000 $2,900.000 $3,600.000 $3,000.000 $3,250.000 $3,198.270 $3,500.000
WIRE FENCE (TY C)
LF 775.000 $50.000 $20.000 $30.000 $25.000 $18.000 $10.000 $30.000 $28.800 $25.000
GATE (TY 1)
EA 2.000 $2,500.000 $1,000.000 $500.000 $2,535.830 $1,800.000 $250.000 $1,000.000 $3,078.240 $3,000.000
WIRE FENCE (WATER GAP)
LF 100.000 $200.000 $60.000 $10.000 $64.000 $36.000 $25.000 $50.000 $48.000 $100.000
REMOVE SM RD SN SUP&AM
EA 6.000 $250.000 $50.000 $250.000 $152.380 $120.000 $1.000 $200.000 $240.000 $200.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 10.000 $30.000 $15.000 $16.050 $25.000 $18.000 $50.000 $30.000 $24.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $30.000 $30.000 $26.750 $31.000 $30.000 $50.000 $50.000 $33.600 $50.000
BONDING COURSE
GAL 66.000 $15.000 $8.000 $20.000 $25.000 $15.000 $45.000 $40.000 $7.680 $40.000
Totals: $2,163,444.150 $1,630,098.000 $1,695,870.849 $1,854,462.383 $1,965,518.700 $1,979,074.500 $1,997,698.950 $2,052,166.320 $2,087,399.250
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
Total: $3,000.00