SHELBY COUNTY ROAD 3012 (0911-39-070)

Items: 50

County: SHELBY
Length: 0.0000 MILES
Highway: COUNTY ROAD 3012
District: LUFKIN
Control Number: 0911-39-070
DBE Goal: 3.5%
Project: BR 2B23(044)
Guaranty: $43,000.00
Time: 346 WORKING DAYS
Engineer's Estimate: $2,145,295.50
Date: 10/01/2024 (1 year ago)
Contract Number: 10243020
Type: BRIDGE REPLACEMENT
Project ID: A00140931
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
RANDAL COOPER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$2,145,295.50
$2,037,058.97
Over/Under Est: -5.05% -$108,236.53
$2,373,650.82
Over/Under Est: 10.64% $228,355.32
Amt Left: 16.52% $336,591.85
Over/Under Est: 13.25% $284,151.95
Amt Left: 19.26% $392,388.48
Delta: -2.35% -$55,796.63
Over/Under Est: 41.93% $899,487.50
Amt Left: 49.47% $1,007,724.03
Delta: -25.33% -$615,335.55
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 12.35% $251,978.40
TEXCO SERVICES, LLC 4.55% $92,834.15
J. H. ODEN CONTRACTING COMPANY 2.14% $43,662.65
DIAMOND ELITE BARRICADES, LLC 1.57% $32,032.88
DUSTROL, INC. 0.41% $8,365.27
CAP RIVER LLC 0.31% $6,324.96
TORO BRAVO CONSTRUCTION, LLC 0.23% $4,692.72
Total: 21.56% $439,891.03

Bid Items & Bid Tabulations

50 Total 0 of 50
SHELBY  |  COUNTY ROAD 3012  |  LUFKIN  |  0911-39-070  |  10/01/2024  |  $2,145,295.50  |  BR 2B23(044)  |  BRIDGE REPL  |  346 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
SKYLINE BRIDGE LLC
EAST TEXAS BRIDGE, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 16.400 $3,000.000 $2,000.000 $2,275.000 $5,000.000 $6,800.000
EXCAV (ROADWAY)
CY 719.000 $20.000 $20.000 $20.000 $30.000 $30.000
EMBANK (FNL)(OC)(TY B)
CY 1,323.000 $30.000 $20.000 $37.000 $35.000 $40.000
FURN & PLACE TOPSOIL (4")
SY 5,047.000 $5.500 $4.000 $4.000 $4.000 $5.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 5,047.000 $2.000 $3.240 $2.500 $2.350 $2.000
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 2,345.000 $2.000 $0.010 $2.250 $2.250 $1.000
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 2,345.000 $2.000 $0.010 $2.250 $2.250 $1.000
VEGETATIVE WATERING
TGL 195.000 $20.000 $10.000 $1.000 $10.000 $1.000
SOIL RET BLKT(SL_MOD_SAND_SHORT)
SY 248.000 $10.000 $5.400 $3.250 $3.750 $6.000
FL BS (CMP IN PLC)(TY D GR 1-2) (4")
SY 882.000 $40.000 $40.000 $42.000 $35.000 $50.000
FL BS (CMP IN PLC)(TY D GR 1-2) (6")
SY 2,811.000 $45.000 $40.000 $48.000 $40.000 $60.000
ASPH (RC-250)
TON 0.830 $1,500.000 $28,080.000 $18,554.000 $7,500.000 $20,000.000
AGGR (TY E OR L, GR-5)
CY 6.000 $360.000 $1,500.000 $1,867.000 $750.000 $4,000.000
SP MIXES SP-C SAC-B PG64-22
TON 84.000 $180.000 $350.000 $550.000 $450.000 $600.000
CEM STABIL BKFL
CY 220.000 $350.000 $350.000 $345.000 $325.000 $300.000
DRILL SHAFT (24 IN)
LF 420.000 $280.000 $317.320 $325.000 $330.000 $225.000
DRILL SHAFT (36 IN)
LF 420.000 $320.000 $382.120 $415.000 $415.000 $360.000
CL C CONC (ABUT)
CY 97.800 $1,400.000 $1,100.000 $1,025.000 $1,500.000 $2,500.000
REINF CONC SLAB
SF 6,040.000 $25.000 $31.000 $27.500 $35.000 $45.000
SHEAR KEY
CY 9.000 $650.000 $800.000 $1,400.000 $1,000.000 $800.000
PRESTR CONC GIRDER (TX28)
LF 278.000 $250.000 $452.000 $413.000 $345.000 $440.000
PRESTR CONC SLAB BEAM (4SB15)
LF 134.000 $250.000 $300.000 $584.000 $345.000 $460.000
PRESTR CONC SLAB BEAM (5SB15)
LF 384.000 $275.000 $322.000 $327.000 $345.000 $460.000
PRESTR CONC BOX BEAM (4B20)
LF 258.000 $270.000 $324.000 $546.000 $345.000 $475.000
PRESTR CONC BOX BEAM (5B20)
LF 129.000 $280.000 $324.000 $400.000 $345.000 $475.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 758.000 $225.000 $190.000 $211.000 $285.000 $250.000
RAIL (TY T631LS)
LF 588.000 $80.000 $67.500 $82.000 $80.000 $75.000
TYPE A JOINT
LF 210.000 $75.000 $20.000 $120.000 $50.000 $150.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 4.000 $20,000.000 $5,000.000 $12,775.000 $20,000.000 $50,000.000
MOBILIZATION
LS 1.000 $200,000.000 $200,000.000 $175,000.000 $235,000.000 $275,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 31.000 $2,000.000 $1,033.190 $1,840.000 $3,500.000 $3,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 214.000 $50.000 $54.000 $40.000 $40.000 $1.000
ROCK FILTER DAMS (REMOVE)
LF 214.000 $15.000 $16.200 $11.000 $15.000 $1.000
CONSTRUCTION PERIMETER FENCE
LF 25.000 $10.000 $10.800 $18.000 $15.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,993.000 $4.000 $4.760 $4.000 $4.500 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,993.000 $1.000 $1.080 $1.000 $1.000 $1.000
CONSTRUCTING DETOURS
SY 435.000 $100.000 $50.000 $150.000 $70.000 $220.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 20.000 $4,500.000 $2,868.480 $4,316.000 $2,500.000 $5,000.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 150.000 $300.000 $80.000 $117.000 $85.000 $120.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 40.000 $300.000 $80.000 $205.000 $85.000 $120.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 150.000 $100.000 $20.000 $61.000 $20.000 $120.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 40.000 $100.000 $20.000 $165.000 $20.000 $120.000
MTL W-BEAM GD FEN (TIM POST)
LF 337.000 $35.000 $27.540 $35.000 $30.000 $26.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,500.000 $1,431.000 $1,656.000 $1,500.000 $1,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,105.000 $3,594.000 $3,200.000 $3,000.000
WIRE FENCE (TY D)
LF 91.000 $25.000 $27.000 $47.000 $35.000 $25.000
REMOVE SM RD SN SUP&AM
EA 6.000 $250.000 $250.000 $281.000 $100.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 25.000 $40.000 $27.000 $31.000 $30.000 $30.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 8.000 $25.000 $486.000 $150.000 $300.000 $500.000
BONDING COURSE
GAL 38.000 $6.000 $40.000 $250.000 $50.000 $20.000
Totals: $2,145,295.500 $2,037,058.970 $2,373,650.820 $2,429,447.450 $3,044,783.000