SHACKELFORD SH 6 (0126-01-039)

Items: 93

County: SHACKELFORD
Length: N/A
Highway: SH 6
District: ABILENE
Control Number: 0126-01-039
DBE Goal: N/A
Project: STP 2020(029)
Guaranty: N/A
Time: 322 WORKING DAYS
Engineer's Estimate: $16,543,962.00
Date: 09/06/2019 (6 years ago)
Contract Number: N/A
Type: MILL, OVERLAY AND SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$16,543,962.00
$12,663,688.29
Over/Under Est: -23.45% -$3,880,273.71
$13,674,598.24
Over/Under Est: -17.34% -$2,869,363.76
Amt Left: 7.98% $1,010,909.95
Over/Under Est: -2.03% -$336,153.14
Amt Left: 27.99% $3,544,120.57
Delta: -18.52% -$2,533,210.62
Over/Under Est: -1.35% -$223,126.98
Amt Left: 28.88% $3,657,146.73
Delta: -0.70% -$113,026.16
$16,920,697.97
Over/Under Est: 2.28% $376,735.97
Amt Left: 33.62% $4,257,009.68
Delta: -3.68% -$599,862.95

Bid Items & Bid Tabulations

93 Total 0 of 93
SHACKELFORD  |  SH 6  |  ABILENE  |  0126-01-039  |  09/06/2019  |  $16,543,962.00  |  STP 2020(029)  |  MILL, OVERLAY AND SAFETY  |  322 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
DUININCK, INC.
J. H. STRAIN & SONS, INC.
ALLEN BUTLER CONSTRUCTION, INC.
GILVIN-TERRILL, LTD.
PREPARING ROW
STA 1,049.500 $700.000 $450.000 $190.000 $1,700.000 $174.450 $200.000
REMOVING STAB BASE AND ASPH PAV(8")
SY 4,175.000 $6.000 $6.000 $8.150 $8.750 $19.860 $10.000
EXCAVATION (ROADWAY)
CY 2,957.000 $20.000 $4.000 $21.000 $25.000 $10.430 $30.000
EXCAVATION (CHANNEL)
CY 50.000 $25.000 $25.000 $53.500 $100.000 $89.460 $30.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 7,256.000 $20.000 $18.000 $23.500 $20.000 $11.490 $30.000
BACKFILL (TY B)
STA 1,049.500 $200.000 $100.000 $79.500 $225.000 $116.940 $200.000
BLADING
HR 68.000 $200.000 $125.000 $265.000 $80.000 $249.910 $150.000
FURNISHING AND PLACING TOPSOIL (4")
SY 3,754.000 $6.000 $3.000 $10.500 $4.000 $3.660 $5.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 3,754.000 $1.500 $1.000 $0.570 $1.000 $1.430 $0.600
PROOF ROLLING
HR 10.000 $90.000 $85.000 $160.000 $125.000 $117.170 $240.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 1,183.000 $70.000 $70.000 $89.000 $60.000 $128.510 $65.000
PRIME COAT (AE-P)
GAL 47,422.000 $4.750 $2.000 $4.000 $4.750 $4.910 $4.500
ASPH (MULTI OPTION)
GAL 217,413.000 $4.250 $3.200 $2.950 $4.000 $3.460 $3.750
AGGR(TY-PB GR-4 SAC-B)
CY 4,111.000 $150.000 $110.000 $85.500 $130.000 $105.590 $125.000
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
TON 51,991.000 $125.000 $93.600 $99.750 $111.950 $123.700 $120.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 24,450.000 $38.000 $37.500 $33.000 $35.000 $39.540 $50.000
PLANE ASPH CONC PAV(0" TO 8")
SY 8,777.000 $10.000 $5.000 $9.000 $5.000 $6.380 $4.000
PLANE ASPH CONC PAV (2")
SY 472,637.000 $1.500 $1.360 $1.600 $1.100 $1.320 $1.500
CEM STABIL BKFL
CY 211.000 $170.000 $275.000 $295.000 $275.000 $232.600 $250.000
TEMPORARY SPL SHORING
SF 3,190.000 $40.000 $45.000 $27.000 $50.000 $34.320 $100.000
DRILL SHAFT (18 IN)
LF 214.000 $110.000 $72.000 $77.000 $72.000 $202.840 $150.000
DRILL SHAFT (36 IN)
LF 823.000 $300.000 $241.000 $260.000 $241.000 $311.280 $250.000
CL C CONC (ABUT)(HPC)
CY 60.800 $2,200.000 $1,600.000 $1,700.000 $1,600.000 $2,201.420 $2,500.000
CL C CONC (CAP)(HPC)
CY 42.600 $2,200.000 $1,625.000 $1,700.000 $1,625.000 $3,884.670 $2,000.000
CL C CONC (COLUMN)(HPC)
CY 24.100 $2,200.000 $1,500.000 $1,600.000 $1,500.000 $2,635.180 $2,000.000
REINF CONC SLAB (HPC)
SF 11,040.000 $34.000 $27.750 $29.500 $27.750 $51.340 $30.000
APPROACH SLAB (HPC)
CY 105.000 $900.000 $500.000 $535.000 $500.000 $820.780 $1,000.000
PRESTR CONC GIRDER (TX46)
LF 1,431.310 $160.000 $196.000 $210.000 $196.000 $196.610 $175.000
SILICONE RESIN PAINT FINISH
SF 690.000 $12.000 $15.000 $16.000 $15.000 $9.760 $10.000
RIPRAP (CONC)(5 IN)
CY 23.400 $625.000 $550.000 $535.000 $600.000 $631.100 $1,000.000
RIPRAP (CONC)(6 IN)
CY 30.000 $875.000 $710.000 $645.000 $600.000 $631.100 $800.000
RIPRAP (STONE PROTECTION)(15 IN)
CY 620.000 $150.000 $105.000 $170.000 $185.000 $172.050 $250.000
RAIL (TY T551)(HPC)
LF 548.000 $60.000 $125.000 $135.000 $125.000 $141.300 $115.000
RETROFIT RAIL (TY T631)
LF 278.500 $110.000 $85.000 $93.500 $90.000 $109.590 $90.000
HEADER TYPE EXPANSION JOINT
CF 13.000 $550.000 $720.000 $745.000 $800.000 $858.290 $500.000
JOINT SEALANT
LF 91.000 $14.000 $25.000 $25.500 $27.000 $25.240 $30.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 94.000 $90.000 $125.000 $135.000 $125.000 $255.310 $110.000
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 135.000 $1,200.000 $850.000 $910.000 $1,000.000 $1,131.120 $1,000.000
SET (TY I)(S= 8 FT)(HW= 7 FT)(3:1) (C)
EA 10.000 $12,000.000 $5,000.000 $8,600.000 $6,500.000 $7,573.190 $9,000.000
CLEAN EXIST CULVERTS
EA 5.000 $2,000.000 $1,750.000 $1,600.000 $2,000.000 $2,145.770 $2,500.000
REMOV STR (SET)
EA 10.000 $1,600.000 $250.000 $535.000 $750.000 $631.100 $2,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $45,000.000 $90,000.000 $96,500.000 $100,000.000 $196,060.710 $500,000.000
MOBILIZATION
LS 1.000 $1,504,000.000 $1,100,000.000 $1,300,000.000 $1,620,000.000 $1,502,137.210 $1,650,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $12,500.000 $10,000.000 $17,000.000 $8,000.000 $14,683.180 $30,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 50.000 $55.000 $75.000 $85.500 $75.000 $174.950 $70.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $23.000 $8.000 $21.500 $20.000 $42.730 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,600.000 $4.250 $3.500 $2.700 $7.500 $5.670 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,600.000 $2.000 $1.200 $1.050 $1.500 $2.510 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 620.000 $8.000 $4.900 $3.850 $7.500 $6.890 $4.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 620.000 $2.500 $1.500 $1.050 $1.500 $2.710 $1.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 12.000 $7,000.000 $4,000.000 $6,200.000 $5,250.000 $4,417.690 $4,600.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 1,050.000 $30.000 $12.000 $23.000 $22.000 $35.130 $10.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,050.000 $25.000 $12.000 $11.000 $17.500 $7.160 $5.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 1,050.000 $30.000 $12.000 $21.500 $17.500 $30.020 $10.000
RUMBLE STRIPS (SHOULDER)
LF 206,867.000 $0.200 $0.120 $0.160 $0.180 $0.290 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 102,346.000 $0.200 $0.120 $0.160 $0.260 $0.330 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 6,655.000 $25.000 $22.000 $21.000 $22.650 $29.110 $20.000
TERMINAL ANCHOR SECTION
EA 1.000 $1,850.000 $700.000 $1,200.000 $850.000 $820.430 $1,100.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 28.000 $1,650.000 $1,700.000 $1,400.000 $1,830.000 $2,019.520 $1,350.000
MTL BEAM GD FEN TRANS (T6)
EA 23.000 $800.000 $1,100.000 $805.000 $855.000 $1,262.200 $750.000
SHORT RADIUS
LF 25.000 $40.000 $32.000 $73.000 $27.200 $37.870 $70.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 73.000 $100.000 $58.000 $98.500 $65.000 $69.420 $100.000
REMOVE METAL BEAM GUARD FENCE
LF 11,135.000 $2.800 $3.200 $2.150 $2.000 $3.790 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 64.000 $270.000 $220.000 $320.000 $200.000 $252.440 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 69.000 $2,600.000 $2,800.000 $2,800.000 $3,000.000 $3,344.820 $2,650.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $225.000 $220.000 $320.000 $200.000 $252.440 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,200.000 $1,000.000 $2,900.000 $2,000.000 $1,262.200 $2,750.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,100.000 $1,000.000 $1,900.000 $1,000.000 $946.650 $1,750.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $11,000.000 $10,000.000 $9,600.000 $8,500.000 $9,782.040 $9,000.000
WIRE FENCE (TY C)
LF 870.000 $20.000 $9.000 $10.500 $25.000 $31.550 $25.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 149.000 $500.000 $390.000 $395.000 $435.000 $467.010 $370.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 33.000 $925.000 $460.000 $465.000 $500.000 $549.060 $435.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $1,000.000 $650.000 $665.000 $715.000 $782.560 $620.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 20.000 $700.000 $670.000 $685.000 $740.000 $807.810 $640.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $1,800.000 $650.000 $660.000 $710.000 $776.250 $615.000
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
EA 1.000 $1,800.000 $1,300.000 $1,300.000 $1,400.000 $1,527.260 $1,210.000
REMOVE SM RD SN SUP&AM
EA 236.000 $125.000 $48.000 $48.000 $50.000 $56.800 $45.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 31.000 $45.000 $23.000 $25.500 $25.000 $18.930 $22.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 78.000 $85.000 $56.000 $57.000 $61.000 $75.730 $53.000
INSTL OM ASSM (OM-3R)(FLX)SRF
EA 64.000 $220.000 $200.000 $210.000 $225.000 $82.040 $195.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 120.000 $40.000 $28.000 $31.000 $30.000 $37.870 $26.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 206,867.000 $0.350 $0.130 $0.130 $0.170 $0.210 $0.200
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 15,600.000 $0.350 $0.150 $0.150 $0.320 $0.210 $0.250
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 113,136.000 $0.350 $0.140 $0.140 $0.320 $0.210 $0.200
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 206,867.000 $0.500 $0.400 $0.410 $0.340 $0.540 $0.440
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 15,600.000 $0.500 $0.400 $0.410 $0.340 $0.540 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 113,136.000 $0.500 $0.400 $0.410 $0.340 $0.540 $0.440
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 140.000 $14.500 $55.000 $53.500 $17.000 $31.550 $16.000
REFL PAV MRKR TY II-A-A
EA 2,277.000 $5.000 $5.000 $5.000 $4.000 $4.100 $4.250
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $20,000.000 $10,000.000 $27,000.000 $15,000.000 $24,593.930 $16,500.000
TMA (STATIONARY)
DAY 540.000 $250.000 $100.000 $255.000 $250.000 $303.630 $250.000
TMA (MOBILE OPERATION)
DAY 216.000 $250.000 $10.000 $965.000 $250.000 $1,429.230 $1,250.000
TEMP SPEED MONITOR SYS
EA 2.000 $14,000.000 $10,000.000 $17,000.000 $15,000.000 $18,932.970 $5,000.000
Totals: $16,543,962.000 $12,663,688.290 $13,674,598.240 $16,207,808.860 $16,320,835.055 $16,920,697.970