SCURRY US 180 (0296-01-039)

Items: 21

County: SCURRY
Length: N/A
Highway: US 180
District: ABILENE
Control Number: 0296-01-039
DBE Goal: 0.0%
Project: F 2024(705)
Guaranty: N/A
Time: 53 WORKING DAYS
Engineer's Estimate: $3,166,079.20
Date: 01/05/2024 (2 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
STEWART CHAPMAN
MAXIE ALLEN
JOSE CABRERA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,166,079.20
$3,120,194.70
Over/Under Est: -1.45% -$45,884.50
$3,279,733.53
Over/Under Est: 3.59% $113,654.33
Amt Left: 5.11% $159,538.83
$3,285,967.75
Over/Under Est: 3.79% $119,888.55
Amt Left: 5.31% $165,773.05
Delta: -0.19% -$6,234.22
$3,592,219.42
Over/Under Est: 13.46% $426,140.22
Amt Left: 15.13% $472,024.72
Delta: -9.32% -$306,251.67
Subcontractor Percentage Amount
FLAT LINE, INC. 1.33% $41,498.59
HJC FARMS, INC. 0.99% $30,889.93
PROFESSIONAL TRAFFIC CONTROL LLC 0.40% $12,480.78
CONTRACTORS SERVICE, LTD. 0.29% $9,048.56
WEST TEXAS ROCK RESOURCES, LLC 0.24% $7,488.47
Total: 3.25% $101,406.33

Bid Items & Bid Tabulations

21 Total 0 of 21
SCURRY  |  US 180  |  ABILENE  |  0296-01-039  |  01/05/2024  |  $3,166,079.20  |  F 2024(705)  |  PREVENT MAINT  |  53 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
RK HALL, LLC
CK NEWBERRY, LLC
GILVIN-TERRILL, LTD.
BACKFILL (TY B)
STA 223.570 $150.000 $375.000 $250.000 $600.000 $370.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 11,555.000 $50.000 $50.000 $50.000 $60.000 $74.000
PLANE ASPH CONC PAV (1")
SY 73,281.000 $5.000 $2.500 $2.740 $2.000 $1.500
CLEAN EXIST CULVERTS
EA 1.000 $2,500.000 $10,000.000 $35,000.000 $3,400.000 $15,000.000
MOBILIZATION
LS 1.000 $300,000.000 $200,000.000 $161,937.560 $300,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $10,000.000 $30,000.000 $25,000.000 $25,000.000 $25,000.000
RUMBLE STRIPS (SHOULDER)
LF 44,314.000 $0.250 $0.250 $0.120 $0.250 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 22,357.000 $0.250 $0.250 $0.120 $0.250 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 309.000 $50.000 $34.000 $31.080 $32.000 $28.250
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 66.000 $85.000 $100.000 $91.300 $95.000 $83.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $4,050.000 $3,712.500 $3,500.000 $3,375.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 7.000 $50.000 $42.000 $38.500 $40.000 $35.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,459.000 $1.500 $3.750 $3.400 $2.250 $1.500
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 44,314.000 $0.900 $0.650 $0.590 $0.750 $0.540
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 3,812.000 $0.900 $0.650 $0.590 $0.750 $0.540
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 24,567.000 $0.900 $0.650 $0.590 $0.750 $0.540
REFL PAV MRKR TY II-A-A
EA 503.000 $3.250 $7.000 $5.500 $6.000 $5.000
SP MIXES SP-C SAC-B PG70-22
TON 11,076.000 $150.000 $160.000 $180.000 $158.000 $175.000
TACK COAT
GAL 10,069.000 $6.000 $7.000 $6.380 $5.500 $5.000
TMA (STATIONARY)
DAY 25.000 $250.000 $500.000 $431.540 $500.000 $800.000
TMA (MOBILE OPERATION)
DAY 10.000 $500.000 $1,000.000 $1,188.930 $550.000 $800.000
Totals: $3,166,079.200 $3,120,194.700 $3,279,733.530 $3,285,967.750 $3,592,219.420