Show Job Controls
Bid Cobra

SAN PATRICIO CR (0916-28-077)

Items: 46

County: SAN PATRICIO
Length: N/A
Highway: CR
District: CORPUS CHRISTI
Control Number: 0916-28-077
DBE Goal: N/A
Project: BR 2021(895)
Guaranty: N/A
Time: 96 WORKING DAYS
Engineer's Estimate: $654,387.29
Date: 01/06/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$654,387.29
Over/Under Est: 21.67% $141,818.06
Over/Under Est: 31.95% $209,084.92
Amt Left: 8.45% $67,266.86
$999,046.10
Over/Under Est: 52.67% $344,658.81
Amt Left: 25.48% $202,840.75
Delta: -15.70% -$135,573.89
Over/Under Est: 58.09% $380,159.91
Amt Left: 29.93% $238,341.85
Delta: -3.55% -$35,501.10
Subcontractor Percentage Amount
HB FARMER FOUNDATION, LLC 20.31% $161,709.31
AVILES CONSTRUCTION SERVICE, INC 7.12% $56,689.82
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 4.12% $32,803.66
TORO BRAVO CONSTRUCTION, LLC 3.02% $24,045.40
TEX-MIX PAVING, LLC 2.87% $22,851.09
SOIL TECH ADVANCE INC. 2.51% $19,984.75
SAPO ENGINEERING CONSULTANTS, LLC 2.51% $19,984.75
HOLES-SOUTH TEXAS LLC 2.12% $16,879.55
H & S CONSTRUCTORS, INC. 1.36% $10,828.39
HIGHWAY BARRICADES AND SERVICES, LLC 0.72% $5,732.68
HERMANOS STEEL, LLC 0.64% $5,095.71
HOUSTON SAWING & DRILLING 0.44% $3,503.30
Total: 47.74% $380,108.41

Bid Items & Bid Tabulations

46 Total 0 of 46
SAN PATRICIO  |  CR  |  CORPUS CHRISTI  |  0916-28-077  |  01/06/2022  |  $654,387.29  |  BR 2021(895)  |  BRIDGE REPL  |  96 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
TEXAS STEEL INDUSTRIAL PLACING, LLC
CK NEWBERRY, LLC
LUCANIA CONSTRUCTION LLC
PREPARING ROW
STA 5.000 $2,000.000 $1,525.000 $2,730.000 $2,500.000 $900.000
EXCAVATION (ROADWAY)
CY 103.000 $20.000 $45.000 $30.000 $70.000 $18.000
EXCAVATION (SPECIAL)
CY 44.000 $20.000 $18.000 $30.000 $150.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 243.000 $15.000 $28.000 $74.000 $50.000 $50.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 1,179.000 $0.300 $0.800 $1.450 $1.000 $1.400
BROADCAST SEED (TEMP) (WARM)
SY 295.000 $0.500 $0.800 $5.000 $1.000 $3.250
BROADCAST SEED (TEMP) (COOL)
SY 295.000 $0.500 $0.800 $5.000 $1.000 $3.250
VEGETATIVE WATERING
MG 22.000 $20.000 $78.000 $150.000 $20.000 $100.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 173.000 $10.000 $6.500 $12.500 $10.000 $11.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 180.000 $70.000 $138.000 $78.000 $175.000 $115.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 16.000 $177.000 $182.000 $225.000 $250.000 $270.000
LIME TRT (SUBGRADE)(8")
SY 712.000 $3.000 $2.500 $20.750 $15.000 $7.000
PRIME COAT (MC-30)
GAL 130.000 $4.500 $6.700 $29.500 $10.000 $10.000
ASPH (MULTI OPTION)
GAL 461.000 $3.000 $2.800 $9.500 $13.000 $10.000
AGGR (MULTI OPTION)
CY 13.000 $65.000 $32.000 $239.000 $750.000 $120.000
CEM STABIL BKFL
CY 75.000 $100.000 $154.000 $150.000 $250.000 $200.000
DRILL SHAFT (18 IN)
LF 156.000 $100.000 $145.000 $195.000 $200.000 $115.000
DRILL SHAFT (36 IN)
LF 462.000 $180.000 $301.000 $328.000 $425.000 $375.000
CL C CONC (ABUT)(HPC)
CY 51.200 $900.000 $1,070.000 $1,025.000 $1,500.000 $1,300.000
CL C CONC (CAP)(HPC)
CY 18.600 $980.000 $2,375.000 $1,150.000 $2,500.000 $1,600.000
CL C CONC (COLUMN)(HPC)
CY 6.300 $880.000 $1,975.000 $1,950.000 $3,500.000 $1,800.000
REINF CONC SLAB
SF 3,120.000 $25.000 $18.000 $22.000 $30.000 $35.000
APPROACH SLAB
CY 68.800 $500.000 $330.000 $575.000 $500.000 $850.000
PRESTR CONC GIRDER (TX28)
LF 474.520 $167.000 $180.000 $193.000 $205.000 $255.000
RIPRAP (CONC)(5 IN)
CY 61.000 $450.000 $336.000 $725.000 $550.000 $550.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 72.000 $125.000 $152.000 $190.000 $250.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $465.000 $490.000 $725.000 $550.000 $575.000
RAIL (TY T223)(HPC)
LF 292.000 $130.000 $170.000 $115.000 $150.000 $180.000
ARMOR JOINT (SEALED)
LF 84.000 $115.000 $141.000 $85.000 $100.000 $205.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $35,000.000 $40,000.000 $10,000.000 $50,000.000
MOBILIZATION
LS 1.000 $59,489.750 $75,000.000 $56,000.000 $85,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $4,000.000 $2,640.000 $1,425.000 $1,000.000 $2,250.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $30.000 $40.000 $50.000 $30.000 $67.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $10.000 $3.150 $20.000 $20.000 $26.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 67.000 $23.000 $7.000 $40.000 $20.000 $23.000
CONSTRUCTION EXITS (REMOVE)
SY 67.000 $8.000 $5.000 $20.000 $5.000 $6.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 830.000 $2.600 $3.000 $4.000 $4.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 830.000 $0.800 $1.000 $1.750 $1.000 $1.750
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 80.000 $6.000 $8.000 $12.500 $8.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 80.000 $1.950 $2.000 $5.000 $2.000 $9.000
MTL W-BEAM GD FEN (TIM POST)
LF 275.000 $22.000 $43.000 $36.000 $30.000 $55.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $3,378.000 $2,430.000 $2,500.000 $2,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,600.000 $2,317.000 $3,990.000 $4,000.000 $3,950.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $28.000 $32.000 $50.000 $30.000 $75.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $34.000 $36.000 $65.000 $30.000 $100.000
ANTI - GRAFFITI COATNG(PERMNENT-TY III)
SF 3,115.000 $1.000 $3.050 $3.320 $1.500 $2.000
Totals: $654,387.290 $796,205.350 $863,472.210 $999,046.100 $1,034,547.200