SAN PATRICIO CS (0916-28-068)
Items: 14
County: SAN PATRICIO
Length: N/A
Highway: CS
District: CORPUS CHRISTI
Control Number: 0916-28-068
DBE Goal: N/A
Project: STP 1702(430)TAPS
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $132,782.00
Date: 08/08/2017 (8 years ago)
Contract Number: N/A
Type: CONSTRUCT SIDEWALK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$132,782.00 | |||
| $119,588.00 |
-9.94%
-$13,194.00
|
|||
| $123,079.00 |
-7.31%
-$9,703.00
|
2.92%
$3,491.00
|
||
| $138,606.00 |
4.39%
$5,824.00
|
15.9%
$19,018.00
|
-12.62%
-$15,527.00
|
|
| $185,459.00 |
39.67%
$52,677.00
|
55.08%
$65,871.00
|
-33.80%
-$46,853.00
|
|
| $190,442.00 |
43.42%
$57,660.00
|
59.25%
$70,854.00
|
-2.69%
-$4,983.00
|
|
| $196,105.00 |
47.69%
$63,323.00
|
63.98%
$76,517.00
|
-2.97%
-$5,663.00
|
|
| $197,590.00 |
48.81%
$64,808.00
|
65.23%
$78,002.00
|
-0.76%
-$1,485.00
|
|
| $220,601.40 |
66.14%
$87,819.40
|
84.47%
$101,013.40
|
-11.65%
-$23,011.40
|
E
Engineer's Estimate
$132,782.00
1
Awarded
$119,588.00
Over/Under Est:
-9.94%
-$13,194.00
$123,079.00
Over/Under Est:
-7.31%
-$9,703.00
Amt Left:
2.92%
$3,491.00
$138,606.00
Over/Under Est:
4.39%
$5,824.00
Amt Left:
15.9%
$19,018.00
Delta:
-12.62%
-$15,527.00
$185,459.00
Over/Under Est:
39.67%
$52,677.00
Amt Left:
55.08%
$65,871.00
Delta:
-33.80%
-$46,853.00
$190,442.00
Over/Under Est:
43.42%
$57,660.00
Amt Left:
59.25%
$70,854.00
Delta:
-2.69%
-$4,983.00
$196,105.00
Over/Under Est:
47.69%
$63,323.00
Amt Left:
63.98%
$76,517.00
Delta:
-2.97%
-$5,663.00
$197,590.00
Over/Under Est:
48.81%
$64,808.00
Amt Left:
65.23%
$78,002.00
Delta:
-0.76%
-$1,485.00
$220,601.40
Over/Under Est:
66.14%
$87,819.40
Amt Left:
84.47%
$101,013.40
Delta:
-11.65%
-$23,011.40
Bid Items & Bid Tabulations
14
Total
0 of 14