SAN PATRICIO US 181 (0101-03-127)
Items: 13
County: SAN PATRICIO
Length: 0.0000 MILES
Highway: US 181
District: CORPUS CHRISTI
Control Number: 0101-03-127
DBE Goal: 0.0%
Project: STP 2025(774)HES
Guaranty: $14,000.00
Time: 60 WORKING DAYS
Engineer's Estimate: $718,944.50
Date: 05/01/2025 (1 year ago)
Contract Number: 5253032
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00212188
Contract Type: Federal
Project Description: INSTALL MEDIAN CABLE BARRIER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
FIDENCIO LOPEZ
CHANDLER WILLIAMS
SAN PATRICIO US 181 (0101-03-127)
Project Name: N/A
Project: STP 2025(774)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: BEE CO. LINE
Limits To: FM 3089
Project Description: INSTALL MEDIAN CABLE BARRIER
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$718,944.50 | |||
| $584,654.00 |
-18.68%
-$134,290.50
|
|||
| $625,227.85 |
-13.04%
-$93,716.65
|
6.94%
$40,573.85
|
||
| $647,257.50 |
-9.97%
-$71,687.00
|
10.71%
$62,603.50
|
-3.52%
-$22,029.65
|
|
| $669,916.34 |
-6.82%
-$49,028.16
|
14.58%
$85,262.34
|
-3.50%
-$22,658.84
|
|
| $696,836.00 |
-3.08%
-$22,108.50
|
19.19%
$112,182.00
|
-4.02%
-$26,919.66
|
|
| $814,360.85 |
13.27%
$95,416.35
|
39.29%
$229,706.85
|
-16.87%
-$117,524.85
|
|
| $856,956.45 |
19.2%
$138,011.95
|
46.57%
$272,302.45
|
-5.23%
-$42,595.60
|
|
| $939,021.50 |
30.61%
$220,077.00
|
60.61%
$354,367.50
|
-9.58%
-$82,065.05
|
E
Engineer's Estimate
$718,944.50
1
Awarded
$584,654.00
Over/Under Est:
-18.68%
-$134,290.50
$625,227.85
Over/Under Est:
-13.04%
-$93,716.65
Amt Left:
6.94%
$40,573.85
$647,257.50
Over/Under Est:
-9.97%
-$71,687.00
Amt Left:
10.71%
$62,603.50
Delta:
-3.52%
-$22,029.65
$669,916.34
Over/Under Est:
-6.82%
-$49,028.16
Amt Left:
14.58%
$85,262.34
Delta:
-3.50%
-$22,658.84
$696,836.00
Over/Under Est:
-3.08%
-$22,108.50
Amt Left:
19.19%
$112,182.00
Delta:
-4.02%
-$26,919.66
$814,360.85
Over/Under Est:
13.27%
$95,416.35
Amt Left:
39.29%
$229,706.85
Delta:
-16.87%
-$117,524.85
$856,956.45
Over/Under Est:
19.2%
$138,011.95
Amt Left:
46.57%
$272,302.45
Delta:
-5.23%
-$42,595.60
$939,021.50
Over/Under Est:
30.61%
$220,077.00
Amt Left:
60.61%
$354,367.50
Delta:
-9.58%
-$82,065.05
| Subcontractor | Percentage | Amount |
|---|---|---|
| LONE STAR EROSION CONTROL | 2.29% | $13,388.58 |
| HIGHWAY BARRICADES AND SERVICES, LLC | 0.74% | $4,326.44 |
| Total: | 3.03% | $17,715.02 |
Bid Items & Bid Tabulations
13
Total
0 of 13
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| Total: | $6,000.00 |