Show Job Controls
Bid Cobra

SAN JACINTO SH0150 (6467-73-001)

Items: 4

County: SAN JACINTO
Length: N/A
Highway: SH0150
District: LUFKIN
Control Number: 6467-73-001
DBE Goal: 0.0%
Project: MMC - 646773001
Guaranty: N/A
Time: 180 CALENDAR DAYS
Engineer's Estimate: $130,882.52
Date: 05/30/2024 (2 years ago)
Contract Number: N/A
Type: HYDRAULIC CEMENT/BULK&BAG/SAN JACINTO (POLK&TRIN)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$130,882.52
$123,344.00
Over/Under Est: -5.76% -$7,538.52
$124,105.60
Over/Under Est: -5.18% -$6,776.92
Amt Left: 0.62% $761.60

Bid Items & Bid Tabulations

4 Total 0 of 4
SAN JACINTO  |  SH0150  |  LUFKIN  |  6467-73-001  |  05/30/2024  |  $130,882.52  |  MMC - 646773001  |  HYDRAULIC CEMENT/BULK&BAG/SAN JACINT...  |  180 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TOUCHSTONE RESOURCES, LLC
AKA-MATERIALS
HYDRAULIC CEMENT(TY I)(DEL)(SITE 2)
TON 300.000 $235.810 $220.000 $220.000
HYDRAULIC CEMENT(TY I)(DEL)(47LBS)(ST1)
BAG 896.000 $8.390 $8.000 $8.200
HYDRAULIC CEMENT(TY I)(DEL)(47LBS)(ST3)
BAG 1,792.000 $8.390 $8.000 $8.200
HYDRAULIC CEMENT(TY I)(DEL)(47LBS)(ST4)
BAG 4,480.000 $8.390 $8.000 $8.050
Totals: $130,882.520 $123,344.000 $124,105.600