SAN JACINTO US0059 (6327-80-001)

Items: 26

County: SAN JACINTO
Length: N/A
Highway: US0059
District: LUFKIN
Control Number: 6327-80-001
DBE Goal: N/A
Project: RMC - 632780001
Guaranty: N/A
Time: 40 W
Engineer's Estimate: $272,699.00
Date: 09/12/2018 (7 years ago)
Contract Number: N/A
Type: FHWA
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$272,699.00
$259,685.00
Over/Under Est: -4.77% -$13,014.00
Over/Under Est: 2.87% $7,835.00
Amt Left: 8.03% $20,849.00
Over/Under Est: 36.7% $100,091.00
Amt Left: 43.55% $113,105.00
Delta: -32.89% -$92,256.00

Bid Items & Bid Tabulations

26 Total 0 of 26
SAN JACINTO  |  US0059  |  LUFKIN  |  6327-80-001  |  09/12/2018  |  $272,699.00  |  RMC - 632780001  |  FHWA  |  40 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
L.C. JORDAN & SON
BECK-REIT & SONS, LTD.
TEXCON GENERAL CONTRACTORS
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 434.000 $28.000 $15.000 $25.000 $45.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 29.000 $140.000 $75.000 $133.000 $130.000
FURNISHING AND PLACING TOPSOIL (4")
SY 400.000 $4.000 $5.000 $3.000 $15.000
COMPOST MANUF TOPSOIL (4")
SY 250.000 $3.000 $7.000 $10.000 $20.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 400.000 $1.000 $1.000 $1.000 $2.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 250.000 $1.000 $1.000 $1.000 $2.000
VEGETATIVE WATERING
MG 14.000 $150.000 $150.000 $50.000 $160.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 650.000 $10.000 $4.000 $3.000 $8.000
D-GR HMA(SQ) TY-D PG64-22 NON-MOW STRIP
SY 808.000 $62.000 $60.000 $80.000 $110.000
FLOWABLE BACKFILL
CY 50.000 $240.000 $210.000 $220.000 $230.000
CONC STR REPR(REMOV AND REPL WINGWALL)
CY 30.000 $320.000 $900.000 $1,000.000 $1,200.000
RIPRAP (CONC)(5 IN)
CY 28.000 $600.000 $450.000 $475.000 $690.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 75.000 $350.000 $210.000 $155.000 $240.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 90.000 $250.000 $210.000 $155.000 $280.000
CONC BOX CULV (9 FT X 8 FT)
LF 8.000 $1,000.000 $950.000 $1,000.000 $2,400.000
MOBILIZATION
LS 1.000 $24,791.000 $25,000.000 $25,000.000 $25,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,000.000 $100.000 $4,000.000 $4,200.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 575.000 $5.000 $3.000 $2.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 575.000 $2.000 $1.000 $1.500 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 875.000 $24.000 $24.000 $25.000 $24.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $2,500.000 $1,800.000 $1,777.000 $2,400.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 225.000 $25.000 $82.000 $60.000 $100.000
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $5.000 $3.000 $8.000 $2.000
GUARDRAIL END TREATMENT (INSTALL)
EA 9.000 $2,500.000 $2,500.000 $2,300.000 $2,100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 28.000 $25.000 $65.000 $75.000 $100.000
TMA (STATIONARY)
DAY 20.000 $400.000 $350.000 $233.000 $120.000
Totals: $272,699.000 $259,685.000 $280,534.000 $372,790.000