SAN JACINTO US0059 (6327-67-001)

Items: 47

County: SAN JACINTO
Length: N/A
Highway: US0059
District: LUFKIN
Control Number: 6327-67-001
DBE Goal: N/A
Project: RMC - 632767001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $196,575.00
Date: 07/18/2018 (7 years ago)
Contract Number: N/A
Type: GUARD FENCE, ATTENUATOR & METAL RAIL RPR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$196,575.00
$176,695.00
Over/Under Est: -10.11% -$19,880.00
Over/Under Est: 12.05% $23,691.00
Amt Left: 24.66% $43,571.00

Bid Items & Bid Tabulations

47 Total 0 of 47
SAN JACINTO  |  US0059  |  LUFKIN  |  6327-67-001  |  07/18/2018  |  $196,575.00  |  RMC - 632767001  |  GUARD FENCE, ATTENUATOR & METAL RAIL...  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
P-VILLE, INCORPORATED
ISI CONTRACTING, INC.
REMOVING CONC (CURB)
LF 125.000 $8.000 $10.000 $15.000
RAIL (TY T631)
LF 75.000 $35.000 $20.000 $125.000
RAIL (TY T631LS)
LF 20.000 $55.000 $20.000 $140.000
MOBILIZATION (CALLOUT)
EA 12.000 $1,500.000 $1,800.000 $950.000
MTL W-BEAM GD FEN (TIM POST)
LF 800.000 $24.000 $22.000 $23.000
TERMINAL ANCHOR SECTION
EA 4.000 $150.000 $200.000 $350.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,400.000 $500.000 $2,650.000
MTL BEAM GD FEN TRANS (T101)
EA 8.000 $840.000 $100.000 $1,200.000
SHORT RADIUS
LF 50.000 $30.000 $35.000 $58.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $600.000 $10.000 $1,200.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,000.000 $950.000 $1,300.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 125.000 $22.000 $28.000 $25.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 75.000 $25.000 $20.000 $75.000
REMOVE METAL BEAM GUARD FENCE
LF 2,000.000 $2.500 $2.000 $1.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $250.000 $50.000 $95.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 40.000 $50.000 $100.000 $1.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $200.000 $50.000 $1.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,540.000 $3,450.000 $3,000.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 6.000 $460.000 $500.000 $500.000
CRASH CUSH ATTEN (INSTL)
EA 1.000 $15,000.000 $10,000.000 $23,000.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $700.000 $700.000 $750.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 10.000 $30.000 $5.000 $11.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 10.000 $45.000 $20.000 $22.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 1,200.000 $16.000 $15.000 $17.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 25.000 $20.000 $20.000 $30.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 75.000 $60.000 $50.000 $40.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 15.000 $55.000 $55.000 $50.000
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $280.000 $20.000 $200.000
REALIGN POSTS
EA 50.000 $20.000 $20.000 $8.000
INSTALL BLOCKOUT (TYPE SPECIFIED)
EA 15.000 $15.000 $15.000 $12.000
REMOVE & REPLACE BLOCKOUT
EA 50.000 $20.000 $15.000 $12.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 125.000 $45.000 $24.000 $30.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 15.000 $85.000 $50.000 $45.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 20.000 $12.000 $20.000 $44.000
REPLACE TERMINAL ANCHOR POSTS
EA 20.000 $52.000 $100.000 $150.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 6.000 $3,250.000 $3,450.000 $3,100.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 8.000 $850.000 $1,400.000 $1,200.000
REM & RESET SGT IMPACT HEAD
EA 30.000 $100.000 $75.000 $100.000
REPLACE SGT CABLE ASSEMBLY
EA 5.000 $60.000 $90.000 $110.000
REPLACE SGT CABLE ANCHOR
EA 5.000 $80.000 $75.000 $110.000
REPLACE SGT STRUT
EA 5.000 $80.000 $50.000 $75.000
REPLACE SGT OBJECT MARKER
EA 5.000 $40.000 $20.000 $31.000
REPAIR RAIL ELEMENT(W - BEAM FURNISHED)
LF 50.000 $22.000 $4.000 $7.000
REPAIR (WIDE QUAD)
EA 2.000 $1,800.000 $500.000 $2,500.000
REPAIR (TY T101RC)
LF 25.000 $45.000 $20.000 $125.000
REPAIR (STL POST W/DOUBLED W-BEAMS-T6)
EA 50.000 $50.000 $50.000 $50.000
TMA (STATIONARY)
EA 1.000 $3,000.000 $100.000 $230.000
Totals: $196,575.000 $176,695.000 $220,266.000