Show Job Controls
Bid Cobra

SAN JACINTO SH 150 (0395-02-049)

Items: 37

County: SAN JACINTO
Length: 0.0000 MILES
Highway: SH 150
District: LUFKIN
Control Number: 0395-02-049
DBE Goal: 2.0%
Project: STP 2B24(468)TAPS
Guaranty: $28,000.00
Time: 80 WORKING DAYS
Engineer's Estimate: $1,712,447.00
Date: 08/08/2025 (10 months ago)
Contract Number: 8253213
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00207123
Contract Type: Federal
Project Description: THE PROJECT WILL CONSTRUCT A 6 FT WIDE SIDEWALK ALONG SH 150 FROM SH 156 TO THE COLDSPRING-OAKHURST HIGH SCHOOL CAMPUS. THE SIDEWALK WILL BE CONSTRUCTED ON THE EAST SIDE OF THE HIGHWAY AND WILL CONNECT TO AN EXISTING SIDEWALK EAST OF LIVE OAK STREET.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLINT JONES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (11)
E
Engineer's Estimate
$1,712,447.00
1
$1,350,735.01
Over/Under Est: -21.12% -$361,711.99
Over/Under Est: -13.38% -$229,127.00
Amt Left: 9.82% $132,584.99
$1,529,995.56
Over/Under Est: -10.65% -$182,451.44
Amt Left: 13.27% $179,260.55
Delta: -3.15% -$46,675.56
$1,557,578.00
Over/Under Est: -9.04% -$154,869.00
Amt Left: 15.31% $206,842.99
Delta: -1.80% -$27,582.44
Over/Under Est: -8.77% -$150,102.57
Amt Left: 15.67% $211,609.42
Delta: -0.31% -$4,766.43
Over/Under Est: -5.58% -$95,508.70
Amt Left: 19.71% $266,203.29
Delta: -3.49% -$54,593.87
$1,645,654.00
Over/Under Est: -3.9% -$66,793.00
Amt Left: 21.83% $294,918.99
Delta: -1.78% -$28,715.70
Over/Under Est: -2.34% -$40,110.00
Amt Left: 23.81% $321,601.99
Delta: -1.62% -$26,683.00
Over/Under Est: 1.79% $30,610.00
Amt Left: 29.05% $392,321.99
Delta: -4.23% -$70,720.00
$2,052,201.00
Over/Under Est: 19.84% $339,754.00
Amt Left: 51.93% $701,465.99
Delta: -17.74% -$309,144.00
Over/Under Est: 22.97% $393,295.14
Amt Left: 55.9% $755,007.13
Delta: -2.61% -$53,541.14
Subcontractor Percentage Amount
CAP RIVER LLC 3.27% $44,169.03
AWP SAFETY 0.84% $11,346.17
DIAMOND ELITE BARRICADES, LLC 0.72% $9,725.29
Total: 4.83% $65,240.49

Bid Items & Bid Tabulations

37 Total 0 of 37
SAN JACINTO  |  SH 150  |  LUFKIN  |  0395-02-049  |  08/08/2025  |  $1,712,447.00  |  STP 2B24(468)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
GARRET SHIELDS INFRASTRUCTURE
TI-ZACK CONCRETE, LLC
MBN ENTERPRISES LLC
SCOUT 5 CONSTRUCTION LLC
HIGHWAY 19 CONSTRUCTION LLC
ICOS MANAGEMENT, LLC
CROSS PLUS CONSTRUCTION, LLC
GREY SKY CONSTRUCTION LLC
ENCINO LANDSCAPE, INC.
TEXAS STEEL INDUSTRIAL PLACING, LLC
PREPARING ROW
STA 46.500 $1,000.000 $75.000 $800.000 $1,080.000 $1,700.000 $198.000 $2,500.000 $2,500.000 $1,200.000 $3,800.000 $1,000.000 $2,000.000
REMOV CONC (RIPRAP)
SY 19.000 $25.000 $35.000 $50.000 $24.000 $45.000 $372.000 $25.000 $40.000 $45.000 $100.000 $100.000 $150.000
REMOV CONC (DRIVEWAYS)
SY 198.000 $25.000 $73.640 $40.000 $17.270 $35.000 $297.600 $25.000 $40.000 $45.000 $20.000 $40.000 $50.000
RMV (6"-10") TRT/UNTRT BASE & ASPH PAV
SY 1,965.000 $20.000 $12.500 $20.000 $16.240 $29.000 $26.400 $15.000 $13.000 $45.000 $20.000 $50.000 $50.000
EXCAV (ROADWAY)
CY 1,277.000 $40.000 $40.000 $40.000 $17.850 $15.000 $40.800 $25.000 $17.500 $45.000 $20.000 $30.000 $35.000
EMBANK (FNL)(OC)(TY B)
CY 1,451.000 $50.000 $35.000 $40.000 $3.140 $15.000 $8.400 $35.000 $25.000 $45.000 $50.000 $40.000 $100.000
BLOCK SODDING
SY 6,743.000 $10.000 $7.210 $10.000 $7.200 $11.000 $13.690 $7.500 $8.500 $12.000 $10.000 $8.000 $8.000
BROADCAST SEED (TEMP_COOL)
SY 3,372.000 $1.000 $0.010 $2.000 $3.600 $1.000 $0.010 $0.150 $0.500 $3.000 $1.000 $1.000 $2.000
VEGETATIVE WATERING
TGL 190.000 $30.000 $0.010 $50.000 $1.200 $85.000 $14.400 $100.000 $18.000 $123.000 $50.000 $30.000 $40.000
SP MIXES SP-D PG64-22
TON 5.000 $180.000 $350.000 $300.000 $330.000 $300.000 $270.000 $500.000 $200.000 $250.000 $5,000.000 $300.000 $1,000.000
CUT & RESTORE ASPH PAVING
SY 31.000 $250.000 $275.000 $200.000 $126.000 $150.000 $198.000 $350.000 $155.000 $200.000 $200.000 $200.000 $500.000
CEM STABIL BKFL
CY 598.000 $400.000 $264.000 $200.000 $195.750 $88.000 $276.000 $350.000 $325.000 $250.000 $350.000 $400.000 $305.000
RIPRAP (CONC)(5 IN)
CY 222.000 $800.000 $596.610 $600.000 $959.670 $680.000 $676.800 $750.000 $900.000 $599.000 $650.000 $800.000 $850.000
RC PIPE (CL III)(18 IN)
LF 1,134.000 $100.000 $63.560 $90.000 $95.350 $110.000 $127.200 $100.000 $80.000 $89.000 $85.000 $200.000 $120.000
RC PIPE (CL III)(24 IN)
LF 342.000 $150.000 $82.680 $100.000 $135.830 $120.000 $148.800 $110.000 $150.000 $129.000 $150.000 $250.000 $150.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 41.000 $1,200.000 $1,093.300 $1,200.000 $1,666.580 $1,770.000 $1,340.400 $1,000.000 $1,250.000 $1,900.000 $1,850.000 $1,500.000 $1,250.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 12.000 $2,000.000 $1,522.330 $2,000.000 $2,463.130 $2,300.000 $2,012.400 $1,600.000 $2,000.000 $2,500.000 $2,200.000 $2,500.000 $2,000.000
REMOV STR (PIPE)
EA 29.000 $500.000 $1,220.330 $400.000 $1,599.060 $1,300.000 $532.800 $500.000 $1,250.000 $26.000 $50.000 $200.000 $100.000
MOBILIZATION
LS 1.000 $150,000.000 $124,882.650 $120,000.000 $132,233.250 $150,000.000 $70,235.150 $200,000.000 $164,000.000 $100,000.000 $170,000.000 $200,000.000 $212,089.140
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $3,500.000 $3,500.000 $5,000.000 $1,800.000 $5,000.000 $0.010 $5,000.000 $5,000.000 $12,000.000 $15,000.000 $5,000.000 $3,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 1.000 $20,000.000 $15,500.000 $1,000.000 $1.200 $18,000.000 $25,000.000 $17,000.000 $14,500.000 $500.000 $15,000.000 $10,000.000 $18,000.000
TMA (STATIONARY)
DAY 90.000 $350.000 $0.010 $300.000 $1.200 $250.000 $0.010 $500.000 $350.000 $750.000 $250.000 $300.000 $350.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 175.000 $45.000 $55.000 $30.000 $0.120 $60.000 $38.400 $75.000 $35.000 $12.000 $30.000 $10.000 $60.000
ROCK FILTER DAMS (REMOVE)
LF 175.000 $15.000 $17.600 $10.000 $0.120 $25.000 $0.010 $15.000 $10.000 $12.000 $15.000 $5.000 $20.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 156.000 $40.000 $0.010 $10.000 $0.120 $60.000 $0.010 $15.000 $10.000 $12.000 $40.000 $50.000 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $15.000 $0.010 $1.000 $0.120 $25.000 $0.010 $10.000 $15.000 $12.000 $20.000 $10.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 600.000 $5.000 $5.170 $5.000 $0.120 $6.000 $12.500 $5.000 $5.000 $1.000 $4.000 $5.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 600.000 $1.500 $1.430 $1.000 $0.120 $2.000 $2.000 $1.000 $1.000 $1.000 $2.000 $1.000 $2.000
DRIVEWAYS (CONC)
SY 187.000 $120.000 $428.350 $120.000 $141.360 $125.000 $100.000 $115.000 $185.000 $125.000 $85.000 $160.000 $140.000
DRIVEWAYS (ACP)
SY 1,547.000 $80.000 $79.030 $120.000 $96.000 $87.000 $100.000 $75.000 $70.000 $100.000 $55.000 $80.000 $130.000
CONC SIDEWALKS (5")
SY 2,886.000 $110.000 $87.170 $100.000 $130.120 $110.000 $125.000 $75.000 $100.000 $90.000 $75.000 $150.000 $140.000
CURB RAMPS (TY 10)
EA 5.000 $3,200.000 $1,850.000 $3,000.000 $2,908.100 $2,700.000 $2,995.200 $1,500.000 $2,500.000 $1,200.000 $3,850.000 $2,000.000 $4,500.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $600.000 $605.000 $500.000 $540.000 $750.000 $354.000 $350.000 $625.000 $1,200.000 $1,100.000 $1,000.000 $500.000
MAILBOX INSTALL-MP (TIM-POST) TY 5
EA 5.000 $400.000 $500.000 $500.000 $660.000 $750.000 $360.000 $450.000 $425.000 $1,200.000 $1,100.000 $800.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 7.000 $750.000 $516.450 $800.000 $540.000 $800.000 $83.000 $850.000 $750.000 $1,200.000 $1,500.000 $1,000.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $850.000 $680.310 $1,000.000 $540.000 $900.000 $144.120 $850.000 $900.000 $1,200.000 $1,500.000 $1,000.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,200.000 $927.590 $1,000.000 $540.000 $1,200.000 $377.360 $1,000.000 $1,200.000 $1,900.000 $1,500.000 $1,000.000 $1,500.000
Totals: $1,712,447.000 $1,350,735.010 $1,483,320.000 $1,529,995.560 $1,557,578.000 $1,562,344.430 $1,616,938.300 $1,645,654.000 $1,672,337.000 $1,743,057.000 $2,052,201.000 $2,105,742.140
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
Total: $3,000.00