Show Job Controls
Bid Cobra

SAN AUGUSTINE US0096 (6309-68-001)

Items: 45

County: SAN AUGUSTINE
Length: N/A
Highway: US0096
District: LUFKIN
Control Number: 6309-68-001
DBE Goal: N/A
Project: RMC - 630968001
Guaranty: N/A
Time: 200 W
Engineer's Estimate: $192,850.00
Date: 11/17/2016 (9 years ago)
Contract Number: N/A
Type: GUARD FENCE, ATTENUATOR & METAL RAIL REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$192,850.00
$146,806.00
Over/Under Est: -23.88% -$46,044.00
Over/Under Est: -22.93% -$44,230.00
Amt Left: 1.24% $1,814.00

Bid Items & Bid Tabulations

45 Total 0 of 45
SAN AUGUSTINE  |  US0096  |  LUFKIN  |  6309-68-001  |  11/17/2016  |  $192,850.00  |  RMC - 630968001  |  GUARD FENCE, ATTENUATOR & METAL RAIL...  |  200 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACE CONTRACTORS, INC.
T & L CLEANING SERVICES
REMOVING CONC (CURB)
LF 125.000 $10.000 $5.000 $10.000
RAIL (TY T631)
LF 75.000 $110.000 $40.000 $30.000
RAIL (TY T631LS)
LF 20.000 $65.000 $40.000 $50.000
MTL W-BEAM GD FEN (TIM POST)
LF 800.000 $25.000 $26.500 $24.000
TERMINAL ANCHOR SECTION
EA 4.000 $1,015.000 $100.000 $200.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,700.000 $1,250.000 $1,200.000
MTL BEAM GD FEN TRANS (T101)
EA 8.000 $1,600.000 $1,000.000 $600.000
SHORT RADIUS
LF 50.000 $50.000 $30.000 $25.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $1,000.000 $250.000 $500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,100.000 $500.000 $1,000.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 125.000 $40.000 $25.000 $20.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 75.000 $70.000 $25.000 $20.000
REMOVE METAL BEAM GUARD FENCE
LF 2,000.000 $2.500 $2.000 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $175.000 $100.000 $100.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 40.000 $160.000 $5.000 $10.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $175.000 $100.000 $100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,300.000 $3,000.000 $2,700.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 6.000 $1,800.000 $1.000 $100.000
CRASH CUSH ATTEN (INSTL)
EA 1.000 $13,000.000 $5,000.000 $15,000.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,200.000 $500.000 $1,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 10.000 $36.000 $25.000 $25.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 10.000 $62.000 $25.000 $30.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 1,200.000 $17.000 $16.500 $16.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 25.000 $7.000 $25.000 $10.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 75.000 $34.500 $35.000 $40.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 15.000 $46.000 $45.000 $40.000
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $115.000 $50.000 $1.000
REALIGN POSTS
EA 30.000 $17.250 $20.000 $10.000
INSTALL BLOCKOUT (TYPE SPECIFIED)
EA 15.000 $33.000 $20.000 $10.000
REMOVE & REPLACE BLOCKOUT
EA 5.000 $17.000 $20.000 $10.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 125.000 $46.000 $50.000 $30.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 15.000 $115.000 $100.000 $70.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 20.000 $5.750 $1.000 $1.000
REPLACE TERMINAL ANCHOR POSTS
EA 20.000 $17.250 $1.000 $100.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 6.000 $2,900.000 $3,000.000 $2,700.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 8.000 $400.000 $850.000 $800.000
REM & RESET SGT IMPACT HEAD
EA 8.000 $115.000 $100.000 $50.000
REPLACE SGT CABLE ASSEMBLY
EA 5.000 $50.000 $100.000 $1.000
REPLACE SGT CABLE ANCHOR
EA 5.000 $1.000 $1.000 $1.000
REPLACE SGT STRUT
EA 5.000 $1.000 $1.000 $1.000
REPLACE SGT OBJECT MARKER
EA 5.000 $100.000 $50.000 $25.000
REPAIR RAIL ELEMENT(W - BEAM FURNISHED)
LF 50.000 $12.500 $15.000 $11.000
REPAIR (WIDE QUAD)
EA 2.000 $10.000 $2,000.000 $500.000
REPAIR (TY T101RC)
LF 25.000 $20.000 $30.000 $30.000
REPAIR (STL POST W/DOUBLED W-BEAMS-T6)
EA 50.000 $10.000 $20.000 $50.000
Totals: $192,850.000 $146,806.000 $148,620.000