Show Job Controls
Bid Cobra

SABINE FM 1 (0064-05-063)

Items: 41

County: SABINE
Length: N/A
Highway: FM 1
District: LUFKIN
Control Number: 0064-05-063
DBE Goal: N/A
Project: STP 2019(495)HES
Guaranty: N/A
Time: 148 WORKING DAYS
Engineer's Estimate: $610,907.10
Date: 06/04/2020 (6 years ago)
Contract Number: N/A
Type: CONSTRUCTION OF SAFETY WORK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$610,907.10
Over/Under Est: 25.13% $153,530.14
$888,894.70
Over/Under Est: 45.5% $277,987.60
Amt Left: 16.28% $124,457.46
Over/Under Est: 49.19% $300,522.70
Amt Left: 19.23% $146,992.56
Delta: -2.54% -$22,535.10
Over/Under Est: 51.21% $312,837.90
Amt Left: 20.84% $159,307.76
Delta: -1.35% -$12,315.20
Over/Under Est: 57.82% $353,212.64
Amt Left: 26.12% $199,682.50
Delta: -4.37% -$40,374.74
$1,076,903.00
Over/Under Est: 76.28% $465,995.90
Amt Left: 40.88% $312,465.76
Delta: -11.70% -$112,783.26

Bid Items & Bid Tabulations

41 Total 0 of 41
SABINE  |  FM 1  |  LUFKIN  |  0064-05-063  |  06/04/2020  |  $610,907.10  |  STP 2019(495)HES  |  CONSTRUCTION OF SAFETY WORK  |  148 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A R BROTHERS CONSTRUCTION SERVICES, INC.
DBI SERVICES, LLC
EAST TEXAS BRIDGE, INC.
SJ&J CONSTRUCTION, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 32.000 $500.000 $450.000 $1,900.000 $1,800.000 $1,000.000 $2,000.000 $2,031.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 3,674.000 $10.000 $25.000 $23.000 $18.000 $30.000 $18.000 $30.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 32.000 $100.000 $110.000 $140.000 $125.000 $100.000 $130.000 $150.000
BLOCK SODDING
SY 372.000 $5.000 $7.000 $7.000 $7.000 $4.500 $5.500 $5.000
BROADCAST SEED (TEMP) (WARM)
SY 7,056.000 $0.300 $0.150 $0.150 $0.150 $0.500 $0.150 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 7,056.000 $0.300 $0.150 $0.150 $0.150 $0.500 $0.150 $1.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 14,112.000 $0.500 $0.500 $0.450 $0.500 $1.500 $0.320 $1.000
VEGETATIVE WATERING
MG 572.100 $20.000 $10.000 $65.000 $10.000 $10.000 $5.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 3,728.000 $2.000 $1.230 $1.250 $1.250 $4.500 $0.950 $6.500
D-GR HMA(SQ) TY-D PG64-22 NON-MOW STRIP
SY 2,017.000 $40.000 $65.000 $80.000 $55.000 $50.000 $100.000 $40.000
FLOWABLE BACKFILL
CY 20.000 $220.000 $192.000 $150.000 $300.000 $220.000 $272.000 $350.000
TEMPORARY SPL SHORING
SF 1,200.000 $20.000 $35.000 $23.000 $45.000 $35.000 $33.000 $55.000
CL C CONC (WINGWALLS)
CY 16.200 $1,000.000 $2,000.000 $1,550.000 $1,200.000 $2,500.000 $1,475.000 $1,500.000
CL C CONC (RAIL FOUNDATION)
CY 2.000 $800.000 $900.000 $525.000 $2,500.000 $3,000.000 $915.000 $1,500.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 11.000 $200.000 $175.000 $240.000 $250.000 $250.000 $250.000 $185.000
RETROFIT RAIL (TY T131RC)
LF 220.000 $150.000 $195.000 $150.000 $185.000 $220.000 $240.000 $150.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 20.000 $400.000 $375.000 $1,780.000 $1,000.000 $700.000 $600.000 $1,000.000
RC PIPE (CL III)(18 IN)
LF 118.000 $45.000 $50.000 $180.000 $70.000 $80.000 $55.000 $85.000
WINGWALL (PW - 2) (HW=7 FT)
EA 1.000 $18,000.000 $26,000.000 $29,000.000 $32,000.000 $12,000.000 $31,000.000 $35,000.000
WINGWALL (PW - 2) (HW=8 FT)
EA 1.000 $20,000.000 $31,900.000 $33,600.000 $35,000.000 $25,000.000 $32,000.000 $40,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $450.000 $750.000 $2,200.000 $1,200.000 $1,500.000 $940.000 $1,850.000
CLEAN EXIST CULVERTS
EA 1.000 $600.000 $1,500.000 $7,000.000 $3,000.000 $1,000.000 $3,310.000 $1,500.000
REMOV STR (PIPE)
EA 1.000 $500.000 $175.000 $1,800.000 $500.000 $1,000.000 $662.000 $500.000
MOBILIZATION
LS 1.000 $53,000.000 $70,000.000 $80,000.000 $86,000.000 $100,000.000 $90,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $1,750.000 $1,750.000 $3,300.000 $6,000.000 $4,000.000 $2,500.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,200.000 $2.500 $3.000 $2.000 $3.500 $4.000 $3.200 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,200.000 $1.000 $2.000 $0.200 $1.000 $2.000 $1.000 $2.000
MTL W-BEAM GD FEN (TIM POST)
LF 3,200.000 $22.000 $20.500 $21.000 $23.000 $29.000 $25.000 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $1,800.000 $1,562.000 $1,375.000 $1,500.000 $1,500.000 $1,850.000 $1,850.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 100.000 $25.000 $40.500 $17.500 $27.000 $70.000 $32.000 $50.000
REMOVE METAL BEAM GUARD FENCE
LF 3,375.000 $2.500 $2.400 $1.000 $3.000 $4.000 $4.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 12.000 $250.000 $354.000 $100.000 $250.000 $500.000 $400.000 $850.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 16.000 $300.000 $354.000 $100.000 $200.000 $1,200.000 $400.000 $850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 20.000 $2,500.000 $2,976.000 $2,180.000 $2,750.000 $2,900.000 $3,000.000 $2,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $285.000 $354.000 $100.000 $250.000 $750.000 $400.000 $1,500.000
WIRE FENCE (TY C)
LF 250.000 $11.000 $7.000 $10.000 $25.000 $27.000 $18.000 $20.000
INSTL OM ASSM (OM-2Z)(FLX)SRF
EA 14.000 $60.000 $72.000 $65.000 $75.000 $40.000 $85.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 58.000 $40.000 $34.500 $20.000 $35.000 $90.000 $30.000 $100.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 24.000 $23.000 $28.500 $65.000 $25.000 $90.000 $30.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $4,780.000 $7,500.000 $20,000.000 $5,000.000 $15,000.000 $12,500.000
TMA (STATIONARY)
DAY 48.000 $300.000 $90.000 $250.000 $325.000 $150.000 $200.000 $550.000
Totals: $610,907.100 $764,437.240 $888,894.700 $911,429.800 $923,745.000 $964,119.740 $1,076,903.000