RUSK FM 2658 (2653-01-016)

Items: 86

County: RUSK
Length: N/A
Highway: FM 2658
District: TYLER
Control Number: 2653-01-016
DBE Goal: N/A
Project: BR 2B23(067)
Guaranty: N/A
Time: 220 WORKING DAYS
Engineer's Estimate: $9,677,750.15
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$9,677,750.15
$9,612,238.35
Over/Under Est: -0.68% -$65,511.80
Over/Under Est: 6.38% $617,192.79
Amt Left: 7.1% $682,704.59
$12,405,854.35
Over/Under Est: 28.19% $2,728,104.20
Amt Left: 29.06% $2,793,616.00
Delta: -20.50% -$2,110,911.41
Subcontractor Percentage Amount
REYNOLDS & KAY, LTD. 5.81% $558,471.05
JE CASEY, LLC 2.94% $282,599.81
A. E. MOORE CONSTRUCTION, INC. 2.92% $280,677.36
STRIPING TECHNOLOGY, L.P. 1.64% $157,640.71
SCOTT DERR PAINTING CO, LLC 0.28% $26,914.27
FLEX SUPPLY, LLC 0.13% $12,495.91
TEX OP CONSTRUCTION, LP 0.13% $12,495.91
PENHALL COMPANY 0.04% $3,844.90
Total: 13.89% $1,335,139.92

Bid Items & Bid Tabulations

86 Total 0 of 86
RUSK  |  FM 2658  |  TYLER  |  2653-01-016  |  08/02/2023  |  $9,677,750.15  |  BR 2B23(067)  |  BRIDGE REPL  |  220 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 57.020 $3,500.000 $10,000.000 $10,000.000 $10,000.000
REMOVING CONC (RIPRAP)
SY 346.000 $80.000 $25.000 $50.000 $30.000
REMOVING CONC (CTB)
LF 1,762.000 $30.000 $30.000 $55.000 $25.000
REMOVING CONC (MISC)
SY 45.200 $50.000 $100.000 $150.000 $50.000
REMOVING CONCRETE(MOW STRIP)
LF 2,181.000 $10.000 $10.000 $22.000 $15.000
REMOVING STAB BASE AND ASPH PAV(8")
SY 4,532.000 $10.000 $15.000 $12.000 $12.000
EXCAVATION (ROADWAY)
CY 4,832.000 $25.000 $25.000 $20.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 5,173.000 $25.000 $30.000 $25.000 $25.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 25.000 $60.000 $50.000 $100.000 $200.000
BLADING
STA 206.080 $300.000 $350.000 $320.000 $400.000
FURNISHING AND PLACING TOPSOIL (4")
SY 3,260.000 $6.000 $4.000 $5.000 $3.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 24,384.000 $0.200 $0.660 $0.140 $0.250
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 48,768.000 $0.800 $0.750 $0.650 $0.650
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 24,384.000 $1.000 $0.250 $0.610 $0.600
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 24,384.000 $1.000 $0.250 $0.610 $0.600
VEGETATIVE WATERING
MG 1,341.000 $20.000 $10.000 $42.000 $15.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 4,532.000 $30.000 $55.000 $39.000 $55.000
REWORK BS MTL (TY B) (8") (ORD COMP)
SY 104,178.000 $9.000 $5.000 $6.000 $20.000
REWORK BS MTL (TY B) (12")(ORD COMP)
SY 6,964.000 $10.000 $3.500 $9.000 $30.000
CEMENT
TON 4,034.000 $285.000 $235.000 $340.000 $350.000
CEMENT TREAT (NEW BASE) (8")
SY 4,532.000 $5.750 $4.250 $6.000 $5.000
CEMENT TREAT(EXIST MATL)(8")
SY 111,491.000 $5.750 $4.750 $5.000 $5.000
CEMENT TREAT (SUBGRADE)(10")
SY 108,086.000 $6.000 $4.750 $5.500 $5.000
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 2,688.000 $8.000 $6.000 $6.900 $10.000
ASPH (RC-250)
GAL 21,211.000 $6.500 $6.500 $5.750 $10.000
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 874.000 $190.000 $220.000 $240.000 $165.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 85,406.000 $5.500 $5.500 $6.000 $6.000
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 922.000 $190.000 $180.000 $245.000 $175.000
AGGR (TY-PD GR-5 OR TY-PL GR-5)
CY 816.000 $250.000 $250.000 $225.000 $165.000
CEM STABIL BKFL
CY 120.000 $300.000 $280.000 $300.000 $400.000
FLOWABLE BACKFILL
CY 1.000 $1,000.000 $1,000.000 $3,000.000 $6,000.000
DRILL SHAFT (36 IN)
LF 300.000 $300.000 $280.000 $475.000 $425.000
CL C CONC (ABUT)
CY 51.400 $1,350.000 $1,500.000 $1,200.000 $1,500.000
REINF CONC SLAB
SF 3,780.000 $25.000 $35.000 $38.000 $40.000
APPROACH SLAB
CY 64.200 $800.000 $750.000 $1,100.000 $900.000
PRESTR CONC GIRDER (TX40)
LF 447.500 $225.000 $280.000 $350.000 $300.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 2,792.000 $25.000 $12.000 $20.000 $15.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 5.000 $1,200.000 $1,000.000 $6,000.000 $5,000.000
RIPRAP (CONC)(4 IN)
CY 70.100 $900.000 $750.000 $650.000 $1,000.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 3,010.000 $180.000 $170.000 $200.000 $300.000
RIPRAP (MOW STRIP)(4 IN)
CY 173.000 $900.000 $550.000 $675.000 $700.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 440.000 $100.000 $75.000 $87.000 $55.000
RAIL (TY T551)
LF 220.000 $150.000 $180.000 $165.000 $165.000
RETROFIT RAIL (TY T631)
LF 506.000 $130.000 $110.000 $150.000 $125.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 82.000 $185.000 $75.000 $275.000 $250.000
REMOV STR (BOX CULVERT)
EA 1.000 $120,000.000 $15,000.000 $100,000.000 $100,000.000
MOBILIZATION
LS 1.000 $880,000.000 $1,500,000.000 $1,000,000.000 $1,200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $5,000.000 $10,000.000 $10,000.000 $30,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 1,230.000 $30.000 $45.000 $40.000 $35.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $40.000 $100.000 $40.000 $45.000
ROCK FILTER DAMS (REMOVE)
LF 1,290.000 $10.000 $10.000 $20.000 $12.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 200.000 $40.000 $100.000 $50.000 $30.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 45.000 $125.000 $100.000 $150.000 $125.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 25,720.000 $4.000 $4.000 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 25,720.000 $1.000 $1.000 $1.500 $0.650
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 30.000 $150.000 $200.000 $175.000 $200.000
MTL W-BEAM GD FEN (STEEL POST)
LF 8,100.000 $32.000 $29.000 $35.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $2,000.000 $2,800.000 $2,300.000
REMOVE METAL BEAM GUARD FENCE
LF 6,550.000 $5.000 $4.000 $3.000 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,400.000 $3,250.000 $3,600.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $300.000 $350.000 $275.000 $230.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,500.000 $1,500.000 $1,050.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $800.000 $1,000.000 $1,000.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 4.000 $130.000 $100.000 $420.000 $200.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $25.000 $45.000 $27.000 $40.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 106.000 $30.000 $31.000 $33.000 $30.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 51,961.000 $1.500 $0.420 $0.600 $0.550
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 1,520.000 $1.500 $0.470 $1.300 $1.100
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 44,757.000 $1.500 $0.420 $0.600 $0.550
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,218.000 $2.000 $1.000 $2.000 $2.000
PAVEMENT SEALER 6"
LF 2,507.000 $1.000 $1.000 $0.600 $0.550
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 3,583.000 $1.200 $1.150 $1.300 $1.100
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 90.000 $1.200 $3.000 $5.500 $6.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 3,300.000 $1.200 $1.150 $1.300 $1.100
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 48,378.000 $1.500 $1.150 $1.300 $1.100
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 1,430.000 $1.500 $3.000 $2.200 $3.000
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 41,457.000 $1.500 $1.150 $1.300 $1.100
REFL PAV MRKR TY II-A-A
EA 636.000 $4.500 $6.000 $4.400 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 1,987.000 $1.200 $4.000 $1.300 $1.100
PAV SURF PREP FOR MRK (6")
LF 2,507.000 $0.600 $1.000 $0.600 $0.300
SP MIXES SP-C PG70-22
TON 3,064.000 $200.000 $180.000 $185.000 $190.000
TACK COAT
GAL 1,393.000 $10.000 $6.000 $6.950 $8.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 910.000 $110.000 $200.000 $150.000 $200.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 145.000 $15.000 $20.000 $25.000 $12.000
TMA (STATIONARY)
DAY 20.000 $300.000 $1,000.000 $200.000 $1,000.000
TMA (MOBILE OPERATION)
DAY 4.000 $300.000 $1,000.000 $475.000 $1,000.000
Totals: $9,677,750.150 $9,612,238.350 $10,294,942.940 $12,405,854.350