EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
|
CY
|
306.000
|
$33.000
|
$25.000
|
$20.000
|
|
|
BACKFILL (TY A)
|
STA
|
333.740
|
$300.000
|
$500.000
|
$150.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
1,380.000
|
$1.250
|
$5.000
|
$2.000
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
45,880.000
|
$0.800
|
$0.750
|
$0.770
|
|
|
BONDED FBR MTRX SEED (TEMP)(WARM)
|
SY
|
22,940.000
|
$1.250
|
$0.700
|
$0.720
|
|
|
BONDED FBR MTRX SEED (TEMP)(COOL)
|
SY
|
22,940.000
|
$1.250
|
$0.680
|
$0.700
|
|
|
VEGETATIVE WATERING
|
MG
|
1,009.000
|
$12.500
|
$10.000
|
$12.000
|
|
|
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
|
GAL
|
70,321.000
|
$3.250
|
$2.900
|
$3.120
|
|
|
AGGR (TY-PD GR-3 OR TY-PL GR-3)
|
CY
|
1,674.000
|
$120.000
|
$152.000
|
$95.000
|
|
|
PFC (ASPHALT) PG76-22
|
TON
|
705.000
|
$140.000
|
$130.000
|
$142.000
|
|
|
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
|
TON
|
11,050.000
|
$140.000
|
$130.000
|
$142.000
|
|
|
SUPERPAVE MIXTURES SP-C PG70-22
|
TON
|
16,263.000
|
$90.000
|
$110.000
|
$110.000
|
|
|
SUPERPAVE MIXTURES SP-D PG64-22(LEV-UP)
|
TON
|
10,024.000
|
$90.000
|
$99.500
|
$108.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
2,000.000
|
$50.000
|
$40.000
|
$50.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
1,050.000
|
$2.000
|
$4.250
|
$4.000
|
|
|
PLANE ASPH CONC PAV(0" TO 4")
|
SY
|
3,734.000
|
$2.750
|
$4.250
|
$4.000
|
|
|
PLANE ASPH CONC PAV (0" TO 1 1/2")
|
SY
|
1,822.000
|
$3.000
|
$2.000
|
$4.000
|
|
|
PLANE ASPH CONC PAV (4")
|
SY
|
74,354.000
|
$2.750
|
$3.500
|
$4.000
|
|
|
CONC STR REPR(REMOV AND REPL WINGWALL)
|
CY
|
1.400
|
$2,500.000
|
$2,900.000
|
$8,000.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
132.000
|
$150.000
|
$134.000
|
$200.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
110.000
|
$500.000
|
$490.000
|
$450.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL3)
|
LF
|
368.000
|
$35.000
|
$28.000
|
$38.000
|
|
|
RETROFIT RAIL (TY T223)
|
LF
|
440.800
|
$200.000
|
$129.000
|
$200.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
1.000
|
$1,600.000
|
$10,000.000
|
$2,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$555,000.000
|
$375,000.000
|
$400,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
9.000
|
$8,000.000
|
$2,000.000
|
$8,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
120.000
|
$30.000
|
$34.000
|
$38.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
120.000
|
$7.500
|
$10.000
|
$12.000
|
|
|
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
|
CY
|
50.000
|
$20.000
|
$15.000
|
$40.000
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
10.000
|
$80.000
|
$100.000
|
$125.000
|
|
|
CONSTRUCTION PERIMETER FENCE
|
LF
|
120.000
|
$5.000
|
$5.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,000.000
|
$2.500
|
$2.400
|
$2.700
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,000.000
|
$0.500
|
$1.100
|
$1.100
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
500.000
|
$75.000
|
$84.000
|
$90.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
500.000
|
$20.000
|
$6.250
|
$10.000
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
500.000
|
$15.000
|
$19.000
|
$15.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
3,139.000
|
$25.000
|
$35.000
|
$28.000
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
43.000
|
$95.000
|
$110.000
|
$135.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
67,968.000
|
$0.180
|
$0.180
|
$0.200
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
33,984.000
|
$0.200
|
$0.210
|
$0.200
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,100.000
|
$24.000
|
$20.000
|
$22.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,600.000
|
$1,400.000
|
$1,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
975.000
|
$3.500
|
$2.250
|
$3.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,400.000
|
$2,525.000
|
$2,800.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
8.000
|
$600.000
|
$200.000
|
$300.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$3,000.000
|
$2,000.000
|
$2,200.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,000.000
|
$800.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$12,000.000
|
$9,100.000
|
$10,000.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
36.000
|
$200.000
|
$315.000
|
$350.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
4.000
|
$250.000
|
$350.000
|
$400.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 2
|
EA
|
1.000
|
$300.000
|
$500.000
|
$500.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
39.000
|
$350.000
|
$375.000
|
$400.000
|
|
|
RELOCATE SM RD SN SUP&AM TY TWT
|
EA
|
9.000
|
$475.000
|
$400.000
|
$400.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
39.000
|
$90.000
|
$145.000
|
$150.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
8.000
|
$30.000
|
$20.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
24.000
|
$35.000
|
$25.000
|
$30.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
70,448.000
|
$0.160
|
$0.170
|
$0.190
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
70,028.000
|
$0.170
|
$0.170
|
$0.190
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
2,080.000
|
$1.250
|
$1.500
|
$2.000
|
|
|
WK ZN PAV MRK SHT TERM RMV (Y)(4")
|
LF
|
15,471.000
|
$0.900
|
$1.300
|
$1.500
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
239.000
|
$5.250
|
$6.000
|
$6.500
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
68,768.000
|
$0.350
|
$0.440
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
6,600.000
|
$0.350
|
$0.600
|
$0.650
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
35,104.000
|
$0.350
|
$0.440
|
$0.500
|
|
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
|
EA
|
9.000
|
$50.000
|
$75.000
|
$100.000
|
|
REFL PAV MRKR TY I-A
|
EA
|
34.000
|
$2.950
|
$4.000
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
595.000
|
$3.100
|
$4.000
|
$5.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$110.000
|
$14,000.000
|
$8,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
105.000
|
$200.000
|
$150.000
|
$300.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
28.000
|
$100.000
|
$50.000
|
$300.000
|
|
Totals: |
$6,188,566.380
|
$6,403,500.830
|
$6,632,252.760
|