Bid Cobra

RUSK US 79 (0246-01-034)

Items: 45

County: RUSK
Length: N/A
Highway: US 79
District: TYLER
Control Number: 0246-01-034
DBE Goal: N/A
Project: STP 2019(435)
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $5,687,717.03
Date: 01/08/2019 (7 years ago)
Contract Number: N/A
Type: PLAN,CAM,HARST,SUPERPV,OCST,PFC SURF,SIGNS,PM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$5,687,717.03
$5,843,498.19
Over/Under Est: 2.74% $155,781.16
Over/Under Est: 13.16% $748,327.79
Amt Left: 10.14% $592,546.63
Over/Under Est: 18.91% $1,075,348.85
Amt Left: 15.74% $919,567.69
Delta: -5.08% -$327,021.06
Over/Under Est: 21.95% $1,248,673.45
Amt Left: 18.7% $1,092,892.29
Delta: -2.56% -$173,324.60

Bid Items & Bid Tabulations

45 Total 0 of 45
RUSK  |  US 79  |  TYLER  |  0246-01-034  |  01/08/2019  |  $5,687,717.03  |  STP 2019(435)  |  PLAN,CAM,HARST,SUPERPV,OCST,PFC SURF...  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
BACKFILL (TY A)
STA 294.000 $225.000 $400.000 $415.000 $375.000 $300.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 65,400.000 $0.750 $0.770 $0.850 $0.850 $0.850
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 32,700.000 $0.750 $0.250 $0.700 $0.750 $0.730
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 32,700.000 $0.750 $0.250 $0.700 $0.700 $0.700
VEGETATIVE WATERING
MG 1,439.000 $7.500 $10.000 $10.000 $8.000 $3.000
ASPH (A-R TYPE II)
GAL 15,953.000 $12.000 $16.500 $17.000 $15.000 $18.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 58,908.000 $3.250 $2.750 $2.000 $4.000 $3.700
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 1,693.000 $120.000 $161.950 $100.000 $165.000 $146.000
PFC (ASPHALT) PG76-22
TON 614.000 $120.000 $130.000 $1.000 $150.000 $150.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 9,621.000 $120.000 $130.000 $150.000 $150.000 $150.000
SUPERPAVE MIXTURES SP-C PG64-22
TON 16,732.000 $90.000 $101.500 $115.000 $110.000 $110.000
SUPERPAVE MIXTURES SP-D PG64-22(LEV-UP)
TON 5,442.000 $85.000 $100.000 $110.000 $115.000 $110.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 2,000.000 $50.000 $50.000 $60.000 $60.000 $68.000
PLANE ASPH CONC PAV (2")
SY 69,996.000 $2.500 $1.000 $2.000 $2.000 $1.400
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 1,911.000 $3.000 $1.500 $5.000 $2.000 $3.400
PLANE ASPH CONC PAV (4")
SY 49,474.000 $3.000 $2.000 $3.000 $3.250 $2.850
MOBILIZATION
LS 1.000 $500,000.000 $308,000.000 $300,000.000 $350,000.000 $550,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $2,500.000 $2,500.000 $6,000.000 $5,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,000.000 $2.500 $2.450 $2.000 $3.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,000.000 $0.750 $0.900 $1.000 $1.000 $1.100
DRIVEWAYS (ACP)
SY 5,885.000 $25.000 $23.500 $22.000 $30.000 $27.000
DRIVEWAYS (CONC) (HES)
SY 143.000 $110.000 $100.000 $125.000 $80.000 $100.000
RUMBLE STRIPS (SHOULDER)
LF 57,780.000 $0.250 $0.160 $0.150 $0.200 $0.180
RUMBLE STRIPS (CENTERLINE)
LF 28,890.000 $0.250 $0.160 $0.270 $0.250 $0.180
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 70.000 $250.000 $259.750 $275.000 $190.000 $285.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 7.000 $350.000 $310.240 $325.000 $230.000 $340.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 2.000 $400.000 $415.810 $435.000 $345.000 $460.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 2.000 $875.000 $909.610 $1,000.000 $800.000 $1,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 24.000 $350.000 $377.380 $400.000 $300.000 $415.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 5.000 $475.000 $312.900 $330.000 $275.000 $345.000
REMOVE SM RD SN SUP&AM
EA 26.000 $125.000 $105.190 $110.000 $100.000 $115.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 95,966.000 $0.160 $0.170 $0.130 $0.140 $0.190
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 95,966.000 $0.170 $0.170 $0.130 $0.140 $0.190
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,620.000 $1.250 $0.250 $1.000 $2.000 $1.200
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 43,200.000 $0.900 $0.010 $1.000 $1.350 $1.200
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 303.000 $5.250 $15.500 $5.800 $6.000 $17.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 58,860.000 $0.350 $0.320 $0.460 $0.500 $0.350
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 5,640.000 $0.350 $0.320 $0.580 $0.600 $0.360
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 26,646.000 $0.350 $0.320 $0.460 $0.500 $0.350
REFL PAV MRKR TY II-A-A
EA 474.000 $3.100 $6.400 $4.000 $4.100 $7.000
CAM (ASPHALT) PG(70-22)
TON 239.000 $125.000 $145.000 $1.000 $165.000 $200.000
CAM (AGGREGATE)
TON 2,951.000 $125.000 $145.000 $190.000 $165.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $10,200.000 $8,500.000 $22,000.000 $18,000.000
TMA (STATIONARY)
DAY 70.000 $200.000 $210.000 $500.000 $200.000 $125.000
TMA (MOBILE OPERATION)
DAY 30.000 $100.000 $0.010 $105.000 $200.000 $100.000
Totals: $5,687,717.030 $5,843,498.190 $6,436,044.820 $6,763,065.880 $6,936,390.480