Bid Cobra

RUSK US 259 (0138-04-046)

Items: 50

County: RUSK
Length: N/A
Highway: US 259
District: TYLER
Control Number: 0138-04-046
DBE Goal: N/A
Project: C 138-4-46
Guaranty: N/A
Time: 71 WORKING DAYS
Engineer's Estimate: $5,848,094.69
Date: 05/02/2018 (8 years ago)
Contract Number: N/A
Type: PLNG, ACP OVERLAY, SEAL COAT, PFC, PV MK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$5,848,094.69
$5,220,900.06
Over/Under Est: -10.72% -$627,194.63
Over/Under Est: -3.82% -$223,135.09
Amt Left: 7.74% $404,059.54
Over/Under Est: -3.31% -$193,344.20
Amt Left: 8.31% $433,850.43
Delta: -0.53% -$29,790.89
Over/Under Est: -0.32% -$18,566.38
Amt Left: 11.66% $608,628.25
Delta: -3.09% -$174,777.82

Bid Items & Bid Tabulations

50 Total 0 of 50
RUSK  |  US 259  |  TYLER  |  0138-04-046  |  05/02/2018  |  $5,848,094.69  |  C 138-4-46  |  PLNG, ACP OVERLAY, SEAL COAT, PFC, P...  |  71 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
EAST TEXAS BRIDGE, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
LONGVIEW BRIDGE AND ROAD, LTD.
BACKFILL (TY C)
STA 8.000 $300.000 $500.000 $400.000 $300.000 $575.000
VEGETATIVE WATERING
MG 5.000 $16.000 $10.000 $50.000 $100.000 $100.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 87,903.000 $2.500 $2.650 $3.200 $2.900 $3.250
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 2,093.000 $125.000 $140.000 $130.000 $100.000 $130.000
PFC (ASPHALT) PG76-22
TON 733.000 $130.000 $125.250 $130.000 $0.010 $130.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 11,482.000 $130.000 $125.250 $130.000 $140.000 $130.000
SUPERPAVE MIXTURES SP-C PG70-22
TON 18,798.000 $97.000 $98.500 $105.000 $115.000 $103.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 11,733.000 $65.000 $40.500 $50.000 $55.000 $53.500
PLANE ASPH CONC PAV (3")
SY 2,826.000 $2.500 $2.100 $3.000 $5.000 $2.750
PLANE ASPH CONC PAV (2 1/2")
SY 133,628.000 $2.500 $2.100 $2.250 $2.500 $2.350
RIPRAP (MOW STRIP)(4 IN)
CY 16.000 $450.000 $460.000 $450.000 $500.000 $545.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 224.000 $14.000 $30.000 $35.000 $32.500 $38.750
RETROFIT RAIL (TY T223)
LF 346.000 $250.000 $74.750 $85.000 $100.000 $82.000
HEADER TYPE EXPANSION JOINT
LF 224.000 $113.000 $155.000 $200.000 $100.000 $225.000
JOINT SEALANT
LF 224.000 $15.000 $30.000 $20.000 $6.000 $24.000
MOBILIZATION
LS 1.000 $500,000.000 $286,000.000 $280,000.000 $150,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $6,500.000 $2,000.000 $7,000.000 $2,000.000 $3,300.000
RUMBLE STRIPS (SHOULDER)
LF 77,167.000 $0.200 $0.130 $0.200 $0.200 $0.120
MTL W-BEAM GD FEN (TIM POST)
LF 775.000 $20.000 $18.000 $22.000 $19.000 $19.800
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,551.500 $1,525.000 $1,800.000 $1,400.000 $1,675.000
REMOVE METAL BEAM GUARD FENCE
LF 775.000 $5.000 $4.000 $3.000 $2.000 $4.400
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $250.000 $300.000 $250.000 $210.000 $330.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,255.000 $2,475.000 $2,500.000 $2,400.000 $2,725.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $250.000 $250.000 $210.000 $275.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 10.000 $30.000 $24.000 $30.000 $21.000 $26.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 12.000 $30.000 $29.000 $30.000 $21.000 $32.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 5,370.000 $0.150 $0.500 $0.550 $0.550 $0.550
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 960.000 $0.150 $1.000 $1.100 $1.050 $1.100
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 80.000 $2.200 $3.000 $3.300 $3.150 $3.300
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 885.000 $0.150 $1.000 $1.100 $1.050 $1.100
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 930.000 $0.150 $1.000 $1.100 $1.050 $1.100
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 80.000 $5.850 $7.000 $8.000 $8.000 $4.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,205.000 $1.250 $1.250 $2.000 $1.000 $1.200
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 908.000 $1.250 $1.250 $2.000 $1.000 $1.200
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 6,330.000 $1.250 $1.400 $2.000 $1.000 $1.400
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 1,815.000 $1.250 $1.400 $2.000 $1.000 $1.400
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,265.000 $0.800 $0.820 $0.900 $0.900 $0.900
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 260.000 $5.000 $5.300 $6.000 $5.600 $5.850
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 427.000 $5.000 $5.300 $6.000 $5.600 $5.850
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 10,735.000 $0.420 $0.460 $0.500 $0.500 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 42,331.000 $0.380 $0.400 $0.450 $0.420 $0.440
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 415.000 $0.420 $1.000 $1.100 $1.050 $1.100
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 42,927.000 $0.380 $0.400 $0.450 $0.420 $0.440
PREFAB PAV MRK TY C (W) (ARROW)
EA 70.000 $200.000 $170.000 $200.000 $200.000 $190.000
PREFAB PAV MRK TY C (W) (WORD)
EA 26.000 $300.000 $220.000 $250.000 $231.000 $245.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 7.000 $56.000 $55.000 $60.000 $58.000 $60.000
REFL PAV MRKR TY I-C
EA 1,074.000 $3.750 $3.300 $4.000 $3.500 $3.650
REFL PAV MRKR TY II-A-A
EA 177.000 $4.000 $3.300 $4.000 $3.500 $3.650
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $125.000 $115.000 $200.000 $350.000 $100.000
TMA (STATIONARY)
DAY 142.000 $300.000 $210.000 $200.000 $300.000 $165.000
Totals: $5,848,094.690 $5,220,900.060 $5,624,959.600 $5,654,750.490 $5,829,528.310