RUSK US 84 (0123-04-023)

Items: 65

County: RUSK
Length: N/A
Highway: US 84
District: TYLER
Control Number: 0123-04-023
DBE Goal: N/A
Project: F 2023(370)
Guaranty: N/A
Time: 97 WORKING DAYS
Engineer's Estimate: $3,073,701.30
Date: 01/05/2023 (3 years ago)
Contract Number: N/A
Type: WIDEN ROAD - ADD LANES
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$3,073,701.30
$2,429,718.64
Over/Under Est: -20.95% -$643,982.66
Over/Under Est: -7.47% -$229,622.83
Amt Left: 17.05% $414,359.83
$2,861,553.15
Over/Under Est: -6.9% -$212,148.15
Amt Left: 17.77% $431,834.51
Delta: -0.61% -$17,474.68
Over/Under Est: -2.66% -$81,607.35
Amt Left: 23.15% $562,375.31
Delta: -4.56% -$130,540.80
Over/Under Est: 19.44% $597,401.52
Amt Left: 51.09% $1,241,384.18
Delta: -22.69% -$679,008.87
Subcontractor Percentage Amount
R & G CONSTRUCTION, LLC 15.27% $563,756.82
DREWERY CONSTRUCTION COMPANY, INCORPORATED 5.63% $207,855.33
REYNOLDS & KAY, LTD. 3.76% $138,816.35
STRIPING TECHNOLOGY, L.P. 1.16% $42,826.32
CAP RIVER LLC 1.11% $40,980.36
SOUTHWEST ENVIRONMENT SERVICES LLC 0.78% $28,797.01
ISAACS CONSTRUCTION SERVICES LLC 0.66% $24,366.70
PANOLA SIGN & BARRICADE, INC. 0.32% $11,814.16
WEST TEXAS ROCK RESOURCES, LLC 0.17% $6,276.27
Total: 28.86% $1,065,489.32

Bid Items & Bid Tabulations

65 Total 0 of 65
RUSK  |  US 84  |  TYLER  |  0123-04-023  |  01/05/2023  |  $3,073,701.30  |  F 2023(370)  |  WIDEN ROAD - ADD LANES  |  97 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
L. S. EQUIPMENT CO., INC.
REYNOLDS & KAY, LTD.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
EAST TEXAS BRIDGE, INC.
PREPARING ROW
STA 110.000 $3,500.000 $1,800.000 $1,500.000 $1,000.000 $2,500.000 $5,000.000
SUBGRADE WIDENING (ORD COMP)
STA 110.000 $400.000 $250.000 $950.000 $750.000 $630.000 $500.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 2,290.000 $38.000 $27.000 $25.000 $20.000 $28.000 $20.000
BACKFILL (TY A)
STA 110.000 $500.000 $482.000 $250.000 $1,300.000 $220.000 $800.000
BLADING
STA 110.000 $350.000 $196.000 $500.000 $120.000 $195.000 $350.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 34,222.000 $1.100 $0.650 $0.650 $0.700 $0.650 $0.720
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 17,111.000 $1.100 $0.570 $0.650 $0.650 $0.600 $0.600
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 17,111.000 $1.100 $0.540 $0.590 $0.550 $0.550 $0.580
VEGETATIVE WATERING
MG 753.000 $11.000 $18.000 $0.010 $10.000 $33.000 $10.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 14,373.000 $6.500 $4.750 $5.500 $4.750 $4.000 $5.000
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 342.000 $140.000 $179.000 $150.000 $179.000 $188.000 $225.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,000.000 $85.000 $50.000 $76.000 $68.000 $75.000 $75.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,244.000 $2.500 $13.500 $7.000 $10.000 $8.000 $7.000
PLANE ASPH CONC PAV(2" TO 4")
SY 1,911.000 $3.000 $0.010 $7.500 $11.000 $10.000 $7.000
TEMPORARY SPL SHORING
SF 90.000 $30.000 $97.000 $75.000 $130.000 $105.000 $150.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 100.000 $140.000 $182.000 $110.000 $225.000 $160.000 $225.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 8.000 $500.000 $927.000 $650.000 $1,500.000 $735.000 $2,000.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 16.000 $600.000 $1,130.000 $900.000 $1,650.000 $945.000 $2,000.000
RC PIPE (CL III)(18 IN)
LF 504.000 $60.000 $48.000 $70.000 $65.000 $65.000 $65.000
WINGWALL (FW - 0) (HW=3 FT)
EA 3.000 $6,500.000 $8,210.000 $7,500.000 $15,000.000 $10,000.000 $15,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 38.000 $850.000 $925.000 $850.000 $950.000 $1,050.000 $900.000
CLEAN EXIST CULVERTS
EA 8.000 $2,000.000 $1,000.000 $500.000 $2,100.000 $2,100.000 $5,000.000
REMOV STR (WINGWALL)
EA 3.000 $2,500.000 $1,200.000 $2,500.000 $1,500.000 $2,100.000 $3,000.000
REMOV STR (PIPE)
EA 19.000 $450.000 $350.000 $500.000 $500.000 $1,600.000 $1,000.000
MOBILIZATION
LS 1.000 $230,000.000 $179,100.000 $280,000.000 $307,000.000 $355,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $7,500.000 $2,000.000 $3,000.000 $7,000.000 $3,500.000 $10,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 500.000 $35.000 $32.000 $38.000 $33.000 $34.000 $36.000
ROCK FILTER DAMS (REMOVE)
LF 500.000 $8.500 $9.000 $10.000 $10.000 $9.500 $10.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 150.000 $25.000 $45.000 $45.000 $20.000 $31.000 $30.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 50.000 $100.000 $95.000 $75.000 $60.000 $230.000 $125.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $2.800 $3.050 $7.000 $3.350 $3.200 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $1.000 $0.700 $4.000 $0.750 $0.750 $1.000
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 60.000 $85.000 $165.000 $125.000 $100.000 $245.000 $150.000
INTERSECTIONS (ACP)
SY 1,911.000 $80.000 $48.650 $65.000 $58.000 $47.000 $50.000
DRIVEWAYS (ACP)
SY 2,293.000 $65.000 $47.890 $52.000 $55.000 $41.000 $45.000
TURNOUTS (ACP)
SY 108.000 $84.000 $102.650 $71.000 $98.000 $42.000 $50.000
RUMBLE STRIPS (SHOULDER)
LF 22,000.000 $0.200 $0.500 $0.300 $0.700 $0.300 $0.500
RUMBLE STRIPS (CENTERLINE)
LF 11,000.000 $0.200 $0.500 $0.300 $0.760 $0.300 $0.500
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 9.000 $250.000 $322.000 $350.000 $375.000 $340.000 $370.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 1.000 $550.000 $614.000 $700.000 $715.000 $645.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $650.000 $855.000 $350.000 $995.000 $900.000 $950.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $730.000 $915.000 $1,000.000 $1,050.000 $960.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $725.000 $919.000 $1,000.000 $1,075.000 $965.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $825.000 $1,052.000 $1,200.000 $1,225.000 $1,100.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,300.000 $1,015.000 $1,200.000 $1,200.000 $1,050.000 $1,200.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 24.000 $400.000 $426.000 $600.000 $500.000 $450.000 $500.000
REMOVE SM RD SN SUP&AM
EA 37.000 $75.000 $94.000 $250.000 $110.000 $140.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 16.000 $35.000 $100.000 $100.000 $100.000 $37.000 $100.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 22,000.000 $0.250 $0.250 $0.280 $0.290 $0.250 $0.280
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 200.000 $3.000 $3.000 $3.500 $3.500 $3.150 $3.300
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 22,000.000 $0.250 $0.250 $0.280 $0.290 $0.250 $0.280
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 4,224.000 $0.600 $1.600 $2.000 $1.450 $1.300 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,060.000 $1.500 $1.150 $2.000 $1.150 $1.500 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 200.000 $6.000 $6.000 $7.000 $7.000 $6.300 $7.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 22,000.000 $0.300 $0.600 $0.270 $0.700 $0.650 $0.700
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 23,280.000 $0.400 $0.600 $0.650 $0.700 $0.650 $0.700
REFL PAV MRKR TY I-A
EA 198.000 $3.500 $4.000 $6.000 $4.500 $4.200 $4.500
REFL PAV MRKR TY II-A-A
EA 556.000 $3.500 $4.000 $5.000 $4.500 $4.200 $4.500
SP MIXES SP-B PG64-22
TON 3,392.000 $145.000 $135.000 $150.000 $147.000 $150.000 $200.000
SP MIXES SP-D SAC-A PG70-22
TON 3,764.000 $160.000 $140.000 $150.000 $147.000 $165.000 $185.000
TACK COAT
GAL 680.000 $4.000 $4.000 $8.000 $3.400 $4.500 $8.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $80.000 $100.000 $125.000 $115.000 $220.000 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $10,000.000 $12,000.000 $4,500.000 $13,000.000 $22,000.000
TMA (STATIONARY)
DAY 30.000 $150.000 $150.000 $400.000 $140.000 $235.000 $300.000
TMA (MOBILE OPERATION)
DAY 75.000 $150.000 $0.010 $550.000 $150.000 $105.000 $300.000
Totals: $3,073,701.300 $2,429,718.640 $2,844,078.470 $2,861,553.150 $2,992,093.950 $3,671,102.820