Show Job Controls
Bid Cobra

RUSK US 84 (0123-04-021)

Items: 12

County: RUSK
Length: N/A
Highway: US 84
District: TYLER
Control Number: 0123-04-021
DBE Goal: N/A
Project: STP 2020(483)HES
Guaranty: N/A
Time: 125 WORKING DAYS
Engineer's Estimate: $1,267,011.50
Date: 01/09/2020 (6 years ago)
Contract Number: N/A
Type: INSTALL PROFILE EDGELINE & CENTERLINE MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,267,011.50
$1,024,466.95
Over/Under Est: -19.14% -$242,544.55
Over/Under Est: -15.62% -$197,865.30
Amt Left: 4.36% $44,679.25
Over/Under Est: -8.57% -$108,580.00
Amt Left: 13.08% $133,964.55
Delta: -8.35% -$89,285.30
Over/Under Est: 25.09% $317,894.30
Amt Left: 54.71% $560,438.85
Delta: -36.81% -$426,474.30

Bid Items & Bid Tabulations

12 Total 0 of 12
RUSK  |  US 84  |  TYLER  |  0123-04-021  |  01/09/2020  |  $1,267,011.50  |  STP 2020(483)HES  |  INSTL PROFILE EDGELINE & CENTERLINE...  |  125 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE-A-ZONE, INC.
TOTAL HIGHWAY MAINTENANCE, LLC
STRIPING TECHNOLOGY, L.P.
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $25,000.000 $27,500.000 $25,000.000 $1,000.000 $125,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $220.000 $2,500.000 $5,000.000 $3,500.000
PAVEMENT SEALER 4"
LF 7,590.000 $0.500 $0.200 $0.110 $0.250 $0.100
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 18,300.000 $0.300 $0.360 $0.340 $0.380 $0.320
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 1,076,150.000 $0.540 $0.480 $0.490 $0.520 $0.650
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 40,590.000 $0.550 $0.550 $0.540 $0.650 $0.750
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 776,260.000 $0.600 $0.495 $0.490 $0.520 $0.650
REFL PAV MRKR TY II-A-A
EA 11,734.000 $2.500 $3.000 $2.950 $3.200 $3.450
ELIM EXT PAV MRK & MRKS (4")
LF 7,590.000 $1.000 $0.650 $0.550 $0.550 $0.550
PREFORMED CENTERLINE RUMBLE STRIP
LF 4,820.000 $5.000 $4.900 $3.750 $8.500 $6.250
TMA (STATIONARY)
DAY 100.000 $200.000 $0.010 $125.000 $250.000 $500.000
TMA (MOBILE OPERATION)
DAY 125.000 $300.000 $0.010 $125.000 $50.000 $500.000
Totals: $1,267,011.500 $1,024,466.950 $1,069,146.200 $1,158,431.500 $1,584,905.800