Show Job Controls
Bid Cobra

RUNNELS US 67 (0158-01-083)

Items: 22

County: RUNNELS
Length: N/A
Highway: US 67
District: SAN ANGELO
Control Number: 0158-01-083
DBE Goal: N/A
Project: STP 1902(010)HES
Guaranty: N/A
Time: 202 WORKING DAYS
Engineer's Estimate: $4,143,679.00
Date: 06/05/2019 (7 years ago)
Contract Number: N/A
Type: INSTALL CABLE BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$4,143,679.00
$3,312,755.35
Over/Under Est: -20.05% -$830,923.65
Over/Under Est: -14.79% -$612,712.95
Amt Left: 6.59% $218,210.70
$3,826,709.50
Over/Under Est: -7.65% -$316,969.50
Amt Left: 15.51% $513,954.15
Delta: -8.38% -$295,743.45
$4,203,118.50
Over/Under Est: 1.43% $59,439.50
Amt Left: 26.88% $890,363.15
Delta: -9.84% -$376,409.00
$4,411,767.00
Over/Under Est: 6.47% $268,088.00
Amt Left: 33.18% $1,099,011.65
Delta: -4.96% -$208,648.50
$4,840,849.50
Over/Under Est: 16.82% $697,170.50
Amt Left: 46.13% $1,528,094.15
Delta: -9.73% -$429,082.50
Over/Under Est: 31.87% $1,320,580.34
Amt Left: 64.95% $2,151,503.99
Delta: -12.88% -$623,409.84

Bid Items & Bid Tabulations

22 Total 0 of 22
RUNNELS  |  US 67  |  SAN ANGELO  |  0158-01-083  |  06/05/2019  |  $4,143,679.00  |  STP 1902(010)HES  |  INSTL CABLE BARRIER  |  202 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GRATIOT CONSTRUCTION, LTD.
SCR CIVIL CONSTRUCTION, LLC
DBI SERVICES, LLC
DCI CONTRACTING, INC.
HJC FARMS, INC.
VANN/ELLI, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
PREP ROW (TREE) (2" TO 12" DIA)
EA 3.000 $200.000 $470.590 $635.000 $560.000 $1,022.000 $300.000 $500.000 $2,093.960
OBLITERATING ABANDONED ROAD
SY 260.000 $7.300 $100.000 $93.000 $67.000 $19.000 $10.000 $12.000 $53.940
BLADING
HR 300.000 $168.000 $111.760 $270.000 $45.000 $146.000 $200.000 $250.000 $231.990
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 71.000 $560.000 $662.350 $630.000 $810.000 $370.000 $700.000 $620.000 $895.090
DRILL SEEDING (TEMP) (WARM)
AC 24.000 $430.000 $524.710 $500.000 $540.000 $423.000 $600.000 $500.000 $710.400
DRILL SEEDING (TEMP) (COOL)
AC 18.000 $460.000 $524.710 $450.000 $540.000 $483.000 $600.000 $500.000 $727.200
WILDFLOWER SEEDING
AC 23.000 $1,000.000 $1,423.530 $1,355.000 $1,350.000 $724.000 $1,100.000 $2,000.000 $1,152.590
RIPRAP (CONC)(CL B)
CY 4,444.000 $375.000 $364.250 $385.000 $360.000 $470.000 $525.000 $550.000 $442.130
REMOV STR (SET)
EA 2.000 $450.000 $588.240 $1,100.000 $360.000 $1,180.000 $500.000 $600.000 $594.100
REMOV STR (PIPE)
EA 1.000 $500.000 $588.240 $6,500.000 $720.000 $4,720.000 $600.000 $800.000 $1,782.290
MOBILIZATION
LS 1.000 $367,000.000 $320,000.000 $140,000.000 $482,000.000 $431,000.000 $100,000.000 $440,000.000 $896,347.030
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $9,000.000 $1,570.590 $3,800.000 $3,700.000 $4,345.000 $5,000.000 $5,000.000 $6,169.080
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,528.000 $9.000 $7.240 $6.900 $8.000 $7.000 $6.000 $9.000 $10.340
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,528.000 $2.500 $1.670 $1.600 $2.000 $1.250 $1.000 $1.500 $2.600
CABLE BARRIER SYSTEM (TL-4)
LF 102,880.000 $12.000 $7.850 $8.750 $9.500 $8.550 $10.000 $10.250 $15.220
CABLE BARRIER SYSTEM (TL-4) (10'-0")
LF 12,217.000 $12.000 $9.680 $10.650 $13.500 $10.500 $13.000 $11.500 $19.030
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 106.000 $2,400.000 $1,977.650 $2,200.000 $1,650.000 $2,500.000 $3,500.000 $2,700.000 $2,876.980
REMOVE SM RD SN SUP&AM
EA 7.000 $120.000 $176.470 $325.000 $360.000 $295.000 $100.000 $150.000 $159.100
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 1.000 $45.000 $176.470 $400.000 $360.000 $295.000 $50.000 $100.000 $206.210
POST AND CABLE FENCE (NEW INSTALLATION)
LF 2,900.000 $25.000 $10.590 $16.000 $8.000 $29.000 $25.000 $10.000 $21.770
POST AND CABLE FENCE (NEW CONC ANCHOR)
EA 30.000 $1,300.000 $235.290 $300.000 $360.000 $1,000.000 $1,000.000 $500.000 $960.020
TMA (STATIONARY)
DAY 404.000 $250.000 $5.880 $218.000 $460.000 $269.000 $200.000 $400.000 $246.720
Totals: $4,143,679.000 $3,312,755.350 $3,530,966.050 $3,826,709.500 $4,203,118.500 $4,411,767.000 $4,840,849.500 $5,464,259.340