PREPARING ROW
|
STA
|
127.660
|
$1,800.000
|
$1,575.000
|
$2,500.000
|
$1,500.000
|
$2,234.070
|
|
|
PREPARING ROW (TREE) (36" TO 48" DIA)
|
EA
|
1.000
|
$2,500.000
|
$3,000.000
|
$1,250.000
|
$3,500.000
|
$1,200.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
3,115.580
|
$11.000
|
$11.550
|
$16.000
|
$20.000
|
$23.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (3")
|
SY
|
16,011.110
|
$4.250
|
$3.000
|
$2.250
|
$2.500
|
$5.800
|
|
|
REMOVE TREATD BASE & ASPH PAV(13"-19")
|
SY
|
12,356.890
|
$8.500
|
$9.450
|
$8.300
|
$7.000
|
$10.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
127.660
|
$350.000
|
$315.000
|
$310.000
|
$290.000
|
$375.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
6,251.080
|
$10.000
|
$12.600
|
$22.000
|
$11.000
|
$12.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
127.660
|
$175.000
|
$175.000
|
$200.000
|
$300.000
|
$750.000
|
|
|
ROAD GRADER WORK (ORD COMP)
|
STA
|
127.660
|
$200.000
|
$750.000
|
$0.010
|
$250.000
|
$400.000
|
|
|
DRILL SEEDING (PERM) (URBAN) (CLAY)
|
SY
|
66,667.000
|
$0.100
|
$0.100
|
$0.110
|
$0.120
|
$0.070
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
20,002.000
|
$0.100
|
$0.100
|
$0.090
|
$0.120
|
$0.065
|
|
|
VEGETATIVE WATERING
|
MG
|
12,002.000
|
$6.500
|
$0.500
|
$0.010
|
$1.000
|
$0.010
|
|
|
FL BS (RDWY DEL) (TY D GR 1-2)
|
TON
|
2,268.260
|
$25.000
|
$27.500
|
$20.000
|
$36.000
|
$23.500
|
|
|
FL BS (CMP IN PLACE)(TY D GR 1-2)(11")
|
SY
|
24,251.110
|
$17.000
|
$17.500
|
$16.250
|
$19.000
|
$18.000
|
|
|
FL BS (CMP IN PLC)(TY D GR 1-2)(17")
|
SY
|
17,299.640
|
$25.000
|
$26.000
|
$24.000
|
$29.000
|
$31.000
|
|
|
REWORK BS MATL(TY C)(13")(ORD COMP)
|
SY
|
16,011.110
|
$2.750
|
$1.750
|
$2.200
|
$4.000
|
$8.000
|
|
|
CEMENT
|
TON
|
136.100
|
$150.000
|
$175.000
|
$135.000
|
$170.000
|
$125.000
|
|
|
CEMENT TREAT (MX EXST MTL & NW BS) (6")
|
SY
|
24,016.660
|
$2.100
|
$1.100
|
$2.800
|
$5.000
|
$6.000
|
|
|
EMULS ASPH (PRIME)(MS-2 OR SS-1)
|
GAL
|
7,943.050
|
$3.600
|
$6.720
|
$3.000
|
$3.300
|
$5.000
|
|
|
ASPH (CRS-2P)
|
GAL
|
27,403.490
|
$3.000
|
$3.200
|
$0.010
|
$3.800
|
$4.250
|
|
|
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
|
GAL
|
22,637.650
|
$3.000
|
$3.500
|
$0.010
|
$4.400
|
$4.750
|
|
|
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
|
CY
|
378.230
|
$115.000
|
$140.000
|
$550.000
|
$180.000
|
$150.000
|
|
|
SUPERPAVE MIXTURES SP-D SAC-B PG64-22
|
TON
|
4,368.680
|
$76.000
|
$86.000
|
$90.000
|
$91.000
|
$81.810
|
|
|
CEM STABIL BKFL
|
CY
|
4.100
|
$150.000
|
$210.000
|
$355.000
|
$400.000
|
$350.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
586.500
|
$110.000
|
$63.000
|
$155.000
|
$170.000
|
$150.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
244.000
|
$5.000
|
$10.000
|
$13.000
|
$13.000
|
$20.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,367.000
|
$25.000
|
$25.000
|
$26.000
|
$40.000
|
$40.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
10.250
|
$420.000
|
$630.000
|
$510.000
|
$560.000
|
$450.000
|
|
|
RIPRAP (STONE COMMON)(GROUT)(8 IN)
|
CY
|
5.000
|
$250.000
|
$525.000
|
$155.000
|
$170.000
|
$688.000
|
|
|
RIPRAP (STONE COMMON)(GROUT)(12 IN)
|
CY
|
5.200
|
$350.000
|
$1,365.000
|
$190.000
|
$210.000
|
$688.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
56.000
|
$210.000
|
$240.000
|
$355.000
|
$390.000
|
$325.000
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
81.000
|
$210.000
|
$225.000
|
$390.000
|
$430.000
|
$415.000
|
|
|
CONC BOX CULV (4 FT X 4 FT)
|
LF
|
65.000
|
$250.000
|
$280.000
|
$430.000
|
$480.000
|
$550.000
|
|
|
CONC BOX CULV (7 FT X 7 FT)
|
LF
|
50.000
|
$500.000
|
$800.000
|
$690.000
|
$770.000
|
$1,000.000
|
|
|
CONC BOX CULV (7 FT X 6 FT)(EXTEND)
|
LF
|
13.000
|
$750.000
|
$850.000
|
$705.000
|
$790.000
|
$750.000
|
|
|
CONC BOX CULV (7 FT X 7 FT)(EXTEND)
|
LF
|
64.000
|
$800.000
|
$900.000
|
$755.000
|
$840.000
|
$850.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
1,540.000
|
$52.000
|
$70.000
|
$50.000
|
$54.000
|
$50.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
418.000
|
$65.000
|
$90.000
|
$90.000
|
$98.000
|
$60.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
224.000
|
$82.000
|
$120.000
|
$125.000
|
$134.000
|
$75.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
50.000
|
$115.000
|
$130.000
|
$165.000
|
$179.000
|
$110.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 30 IN)
|
EA
|
2.000
|
$6,000.000
|
$8,000.000
|
$5,700.000
|
$6,200.000
|
$4,500.000
|
|
|
WINGWALL (PW - 2) (HW=10 FT)
|
EA
|
3.000
|
$26,000.000
|
$30,000.000
|
$26,000.000
|
$29,000.000
|
$34,000.000
|
|
|
WINGWALL (PW - 2) (HW=3 FT)
|
EA
|
1.000
|
$4,800.000
|
$10,250.000
|
$3,800.000
|
$4,100.000
|
$6,500.000
|
|
|
WINGWALL (PW - 2) (HW=5 FT)
|
EA
|
4.000
|
$8,000.000
|
$13,000.000
|
$6,700.000
|
$7,300.000
|
$12,000.000
|
|
|
WINGWALL (PW - 2) (HW=7 FT)
|
EA
|
1.000
|
$15,000.000
|
$18,000.000
|
$10,500.000
|
$13,000.000
|
$20,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
106.000
|
$700.000
|
$850.000
|
$750.000
|
$750.000
|
$700.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
28.000
|
$1,000.000
|
$1,000.000
|
$850.000
|
$900.000
|
$1,000.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,950.000
|
$1,800.000
|
$2,100.000
|
$2,200.000
|
$2,100.000
|
|
|
SET (TY II) (36 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$2,150.000
|
$1,400.000
|
$3,200.000
|
$3,400.000
|
$1,900.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
5.000
|
$1,200.000
|
$1,200.000
|
$1,050.000
|
$1,600.000
|
$1,500.000
|
|
|
REMOV STR (INLET)
|
EA
|
1.000
|
$700.000
|
$420.000
|
$525.000
|
$560.000
|
$750.000
|
|
|
REMOV STR (SET)
|
EA
|
27.000
|
$370.000
|
$315.000
|
$425.000
|
$500.000
|
$200.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
3.000
|
$1,500.000
|
$1,575.000
|
$1,050.000
|
$1,400.000
|
$750.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,800.000
|
$15.000
|
$10.500
|
$16.000
|
$20.000
|
$15.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$349,771.950
|
$392,000.000
|
$461,400.000
|
$470,000.000
|
$415,500.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
11.000
|
$11,000.000
|
$25,000.000
|
$31,560.000
|
$19,700.000
|
$13,960.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
220.000
|
$25.000
|
$24.680
|
$26.000
|
$25.000
|
$24.400
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
220.000
|
$7.000
|
$10.500
|
$7.000
|
$6.000
|
$8.480
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
222.000
|
$22.000
|
$21.000
|
$20.000
|
$12.000
|
$25.770
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
222.000
|
$8.000
|
$10.500
|
$8.000
|
$2.000
|
$8.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
10,900.000
|
$1.750
|
$1.470
|
$2.200
|
$2.500
|
$2.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
10,900.000
|
$0.750
|
$0.110
|
$0.500
|
$0.750
|
$0.440
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
300.000
|
$5.000
|
$4.150
|
$6.000
|
$6.500
|
$5.750
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
300.000
|
$1.000
|
$1.050
|
$1.000
|
$3.000
|
$1.150
|
|
|
CONSTRUCTING DETOURS
|
SY
|
89.310
|
$50.000
|
$50.000
|
$70.000
|
$50.000
|
$85.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
180.000
|
$30.000
|
$31.500
|
$108.000
|
$100.000
|
$105.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$40.000
|
$25.200
|
$115.000
|
$100.000
|
$105.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
180.000
|
$6.000
|
$6.300
|
$23.000
|
$15.000
|
$15.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$10.000
|
$8.400
|
$26.000
|
$15.000
|
$15.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
180.000
|
$7.000
|
$6.300
|
$41.000
|
$17.000
|
$95.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$8.000
|
$9.450
|
$42.000
|
$17.000
|
$95.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
2,100.530
|
$35.000
|
$47.500
|
$54.000
|
$35.000
|
$40.250
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
3,115.580
|
$90.000
|
$94.500
|
$115.000
|
$125.000
|
$90.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
375.000
|
$25.000
|
$18.110
|
$18.000
|
$18.000
|
$18.750
|
|
|
SHORT RADIUS
|
LF
|
21.000
|
$30.000
|
$19.690
|
$19.000
|
$20.000
|
$35.000
|
|
|
DRIVEWAY TERMINAL ANCHOR SECTION
|
EA
|
1.000
|
$800.000
|
$551.250
|
$550.000
|
$560.000
|
$890.000
|
|
|
MTL W - BEAM GD FEN (LOW FILL CULVERT)
|
LF
|
50.000
|
$70.000
|
$43.840
|
$42.000
|
$45.000
|
$46.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
EA
|
1.000
|
$600.000
|
$518.440
|
$500.000
|
$530.000
|
$1,200.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
125.000
|
$3.000
|
$2.100
|
$2.000
|
$2.500
|
$3.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
1.000
|
$220.000
|
$141.750
|
$140.000
|
$150.000
|
$230.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
3.000
|
$250.000
|
$288.750
|
$300.000
|
$300.000
|
$275.000
|
|
|
GDRAIL END TRT(INST)(WOOD POST)(TY I)
|
EA
|
5.000
|
$2,500.000
|
$2,677.500
|
$2,600.000
|
$2,700.000
|
$2,375.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
46.000
|
$250.000
|
$210.000
|
$230.000
|
$250.000
|
$225.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
1.000
|
$300.000
|
$367.500
|
$300.000
|
$260.000
|
$275.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
57.000
|
$465.000
|
$551.250
|
$515.000
|
$540.000
|
$495.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
2.000
|
$800.000
|
$771.750
|
$800.000
|
$820.000
|
$950.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
1.000
|
$849.000
|
$992.250
|
$1,000.000
|
$1,000.000
|
$950.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
|
EA
|
14.000
|
$75.000
|
$210.000
|
$60.000
|
$70.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
9.000
|
$30.000
|
$36.750
|
$28.000
|
$35.000
|
$18.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
104.000
|
$4.000
|
$3.870
|
$3.250
|
$3.000
|
$6.000
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
21.000
|
$6.500
|
$7.190
|
$13.000
|
$11.000
|
$10.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
1,920.000
|
$0.750
|
$1.840
|
$1.500
|
$1.250
|
$3.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
988.000
|
$1.000
|
$1.880
|
$1.050
|
$0.750
|
$3.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
100.000
|
$0.770
|
$3.150
|
$1.450
|
$1.200
|
$1.000
|
|
REFL PAV MRK TY I (W)18"(SLD)(100MIL)
|
LF
|
28.000
|
$5.040
|
$10.500
|
$4.900
|
$4.000
|
$5.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
2.000
|
$127.000
|
$173.250
|
$124.000
|
$100.000
|
$150.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
2.000
|
$154.000
|
$194.250
|
$162.000
|
$133.000
|
$200.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
18,410.000
|
$0.230
|
$0.500
|
$0.410
|
$0.320
|
$0.450
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
200.000
|
$0.630
|
$1.520
|
$1.310
|
$1.100
|
$2.000
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
5,990.000
|
$0.360
|
$0.750
|
$0.550
|
$0.440
|
$0.700
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
26,270.000
|
$0.250
|
$0.500
|
$0.410
|
$0.320
|
$0.450
|
|
REFL PAV MRKR TY I-C
|
EA
|
10.000
|
$5.000
|
$10.500
|
$6.490
|
$6.000
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
352.000
|
$3.440
|
$4.780
|
$4.550
|
$4.000
|
$4.000
|
|
|
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
|
EA
|
1.000
|
$5,000.000
|
$6,615.000
|
$3,000.000
|
$10,000.000
|
$3,000.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
3.000
|
$2,700.000
|
$1,200.000
|
$5,000.000
|
$2,200.000
|
$750.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$11,500.000
|
$4,500.000
|
$9,526.000
|
$6,000.000
|
$20,000.000
|
|
|
PORTABLE TRAFFIC SIGNAL
|
MO
|
0.500
|
$5,000.000
|
$5,000.000
|
$6,000.000
|
$15,000.000
|
$10,000.000
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$15,000.000
|
$2,500.000
|
$12,000.000
|
$15,000.000
|
$20,000.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
50.000
|
$50.000
|
$75.000
|
$65.000
|
$65.000
|
$35.000
|
|
Totals: |
$3,968,491.701
|
$4,349,076.735
|
$4,614,443.540
|
$4,773,395.432
|
$4,901,893.528
|