ROCKWALL FM 35 (1017-02-014)
Items: 52
County: ROCKWALL
Length: 1.5230 MILES
Highway: FM 35
District: DALLAS
Control Number: 1017-02-014
DBE Goal: 0.0%
Project: C 1017-2-14
Guaranty: $32,000.00
Time: 61 WORKING DAYS
Engineer's Estimate: $1,622,451.08
Date: 03/04/2025 (1 year ago)
Contract Number: 3253026
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00196059
Project Description: BASE REPAIR, MILL, AND INLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
LANE SELMAN
NICHOLAS WADLINGTON
ROCKWALL FM 35 (1017-02-014)
Project Name: N/A
Project: C 1017-2-14
Length: 1.5230 MILES
Project Type: CONSTRUCTION
Limits From: IH 30
Limits To: HUNT COUNTY LINE
Project Description: BASE REPAIR, MILL, AND INLAY
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,622,451.08 | |||
| $1,317,483.82 |
-18.8%
-$304,967.26
|
|||
| $1,439,051.76 |
-11.3%
-$183,399.32
|
9.23%
$121,567.94
|
||
| $1,565,721.08 |
-3.5%
-$56,730.00
|
18.84%
$248,237.26
|
-8.80%
-$126,669.32
|
|
| $1,576,492.60 |
-2.83%
-$45,958.48
|
19.66%
$259,008.78
|
-0.69%
-$10,771.52
|
|
| $1,839,515.00 |
13.38%
$217,063.92
|
39.62%
$522,031.18
|
-16.68%
-$263,022.40
|
E
Engineer's Estimate
$1,622,451.08
1
$1,317,483.82
Over/Under Est:
-18.8%
-$304,967.26
$1,439,051.76
Over/Under Est:
-11.3%
-$183,399.32
Amt Left:
9.23%
$121,567.94
$1,565,721.08
Over/Under Est:
-3.5%
-$56,730.00
Amt Left:
18.84%
$248,237.26
Delta:
-8.80%
-$126,669.32
$1,576,492.60
Over/Under Est:
-2.83%
-$45,958.48
Amt Left:
19.66%
$259,008.78
Delta:
-0.69%
-$10,771.52
$1,839,515.00
Over/Under Est:
13.38%
$217,063.92
Amt Left:
39.62%
$522,031.18
Delta:
-16.68%
-$263,022.40
| Subcontractor | Percentage | Amount |
|---|---|---|
| LINEAR TRAFFIC MARKINGS LLC | 3.75% | $52,656.11 |
| CATOCON, INC. | 2.14% | $30,049.08 |
| STRIPE-A-ZONE, LLC | 2.06% | $28,925.75 |
| TRAFFIC HIGHWAY MAINTENANCE, LLC | 2.06% | $28,925.75 |
| USA SWPPP INSPECTIONS, INC.DBA USA EROSION | 2.00% | $28,083.26 |
| HILBASH INVESTMENT LLC | 1.79% | $25,134.51 |
| FORTSON CONTRACTING, INC. | 1.75% | $24,572.85 |
| TEXAS TRAFFIC AND BARRICADE, LLC | 0.48% | $6,739.98 |
| Total: | 16.03% | $225,087.29 |
Bid Items & Bid Tabulations
52
Total
0 of 52
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $15,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| Total: | $35,000.00 |