ROBERTSON CS (0917-18-082)

Items: 42

County: ROBERTSON
Length: N/A
Highway: CS
District: BRYAN
Control Number: 0917-18-082
DBE Goal: N/A
Project: BR 2021(235)
Guaranty: N/A
Time: 71 WORKING DAYS
Engineer's Estimate: $481,798.72
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JAMES ROBBINS
JOSEPH GREIVE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$481,798.72
$663,959.11
Over/Under Est: 37.81% $182,160.39
Over/Under Est: 41.54% $200,117.84
Amt Left: 2.7% $17,957.45
$701,352.12
Over/Under Est: 45.57% $219,553.40
Amt Left: 5.63% $37,393.01
Delta: -2.85% -$19,435.56
Over/Under Est: 79.96% $385,269.28
Amt Left: 30.59% $203,108.89
Delta: -23.63% -$165,715.88
Subcontractor Percentage Amount
HEMPHILL WBE PILE DRIVING CO. 5.26% $34,924.25
CEN TEX HYDROSEED, INC. 3.13% $20,781.92
RAY'S CRANE SERVICE 1.06% $7,037.97
LONESTAR TRAFFIC SAFETY, LLC 0.59% $3,917.36
Total: 10.04% $66,661.50

Bid Items & Bid Tabulations

42 Total 0 of 42
ROBERTSON  |  CS  |  BRYAN  |  0917-18-082  |  08/03/2023  |  $481,798.72  |  BR 2021(235)  |  BRIDGE REPL  |  71 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FUQUA CONSTRUCTION CO., INC.
TEXAS MATERIALS GROUP, INC.
TREVWAY, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 3.500 $2,200.000 $10,318.230 $20,300.000 $3,000.000 $5,800.000
EXCAVATION (ROADWAY)
CY 357.000 $20.000 $12.440 $37.000 $12.500 $25.000
EXCAVATION (CHANNEL)
CY 500.000 $25.000 $12.670 $24.000 $11.900 $25.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 315.000 $25.000 $15.530 $44.000 $26.000 $30.000
COMPOST MANUF TOPSOIL (4")
SY 571.000 $3.250 $1.780 $6.000 $16.730 $10.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 571.000 $0.830 $0.580 $2.000 $2.530 $5.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 286.000 $0.820 $0.490 $2.000 $2.530 $1.000
CELL FBR MLCH SEED(TEMP)(COOL)
SY 286.000 $0.820 $0.450 $2.000 $2.530 $1.000
VEGETATIVE WATERING
MG 17.000 $32.000 $15.090 $45.000 $500.000 $1.000
FL BS (CMP IN PLC)(TY D GR 1-2) (6")
SY 966.000 $16.500 $11.170 $22.000 $63.000 $45.000
CEM STABIL BKFL
CY 53.000 $210.000 $115.200 $270.000 $150.000 $300.000
TRENCH EXCAVATION PROTECTION
LF 22.000 $10.000 $3.920 $50.000 $100.000 $5.000
PRESTR CONC PIL (18 IN SQ)
LF 224.000 $150.000 $81.110 $200.000 $304.000 $300.000
CL C CONC (ABUT)
CY 19.600 $1,350.000 $1,628.550 $2,300.000 $1,000.000 $2,000.000
REINF CONC SLAB (SLAB BEAM)
SF 1,040.000 $24.000 $25.800 $53.000 $30.000 $30.000
PRESTR CONC SLAB BEAM (5SB12)
LF 197.500 $250.000 $321.960 $296.000 $304.000 $350.000
RIPRAP (CONC)(4 IN)
CY 2.000 $625.000 $619.980 $1,400.000 $2,000.000 $850.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 326.000 $200.000 $217.800 $140.000 $200.000 $225.000
RAIL (TY T223)
LF 104.000 $150.000 $166.200 $215.000 $192.000 $180.000
CONC BOX CULV (10 FT X 4 FT)
LF 35.000 $1,000.000 $1,666.830 $1,375.000 $2,314.000 $3,500.000
WINGWALL (PW - 2) (HW=6 FT)
EA 2.000 $19,000.000 $20,473.590 $22,000.000 $25,000.000 $30,000.000
REMOV STR (BOX CULVERT)
LF 22.000 $80.000 $94.820 $336.000 $400.000 $2,500.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $36,926.000 $14,000.000 $30,000.000 $50,000.000
MOBILIZATION
LS 1.000 $44,000.000 $86,000.000 $70,000.000 $70,000.000 $65,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $12,816.220 $5,000.000 $1,136.000 $11,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 46.000 $40.000 $46.940 $47.000 $90.000 $1.000
ROCK FILTER DAMS (REMOVE)
LF 46.000 $11.000 $15.040 $15.000 $32.000 $1.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $30.000 $35.470 $36.000 $14.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $10.480 $14.000 $8.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 735.000 $4.000 $4.060 $4.500 $5.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 735.000 $1.000 $1.000 $1.500 $1.000 $1.000
DRIVEWAYS (SURF TREAT)
SY 63.000 $40.000 $22.110 $27.000 $34.000 $70.000
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $27.000 $39.140 $38.460 $49.000 $30.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,400.000 $2,043.660 $1,648.350 $1,501.000 $1,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,500.000 $2,003.600 $879.120 $3,671.000 $2,000.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 22.000 $100.000 $126.160 $82.420 $204.000 $40.000
TL-2 31" SHORT RADIUS (W/O DAT)
EA 1.000 $2,000.000 $26,339.250 $1,648.350 $16,444.000 $4,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,250.000 $4,695.300 $3,846.150 $3,392.000 $3,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $500.000 $609.830 $800.000 $1,642.000 $2,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $27.000 $34.250 $75.000 $20.000 $50.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 4.000 $27.000 $40.250 $75.000 $20.000 $50.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $500.000 $483.080 $300.000 $1,000.000 $500.000
Totals: $481,798.720 $663,959.115 $681,916.560 $701,352.120 $867,068.000