Bid Cobra

ROBERTSON SH 6 (0049-06-079)

Items: 52

County: ROBERTSON
Length: N/A
Highway: SH 6
District: BRYAN
Control Number: 0049-06-079
DBE Goal: N/A
Project: NH 2019(977)
Guaranty: N/A
Time: 93 WORKING DAYS
Engineer's Estimate: $8,634,711.91
Date: 04/03/2019 (7 years ago)
Contract Number: N/A
Type: OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$8,634,711.91
$7,687,390.67
Over/Under Est: -10.97% -$947,321.24
Over/Under Est: -4.38% -$378,249.84
Amt Left: 7.4% $569,071.40
Over/Under Est: 18.94% $1,635,359.51
Amt Left: 33.6% $2,582,680.75
Delta: -24.39% -$2,013,609.35
Over/Under Est: 34.65% $2,991,512.17
Amt Left: 51.24% $3,938,833.41
Delta: -13.20% -$1,356,152.66

Bid Items & Bid Tabulations

52 Total 0 of 52
ROBERTSON  |  SH 6  |  BRYAN  |  0049-06-079  |  04/03/2019  |  $8,634,711.91  |  NH 2019(977)  |  OVERLAY  |  93 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
ANGEL BROTHERS HOLDINGS CORP.
TEXAS MATERIALS GROUP, INC.
REMOVING CONC (RIPRAP)
SY 44.000 $75.000 $40.000 $32.000 $50.000 $24.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY A)
CY 220.000 $25.000 $40.000 $56.250 $100.000 $20.000
BACKFILL (TY A OR B)
STA 718.000 $115.000 $150.000 $91.000 $100.000 $180.000
SUPERPAVE MIXTURES SP-D SAC-A PG70-22
TON 81,081.000 $70.000 $70.000 $64.500 $93.000 $100.000
PLANE ASPH CONC PAV(0" TO 2")
SY 737,101.000 $0.900 $0.600 $1.750 $1.000 $2.100
RIPRAP (MOW STRIP)(4 IN)
CY 239.000 $500.000 $450.000 $358.000 $550.000 $592.000
CLEANING AND SEALING EXISTING JOINTS
LF 1,094.000 $30.000 $40.000 $29.500 $32.000 $29.500
RETROFIT RAIL (TY T631)
LF 1,298.000 $117.000 $150.000 $129.000 $115.000 $125.000
MOBILIZATION
LS 1.000 $530,000.000 $105,000.000 $130,500.000 $450,000.000 $291,910.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $5,000.000 $23,470.000 $2,500.000 $2,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,735.000 $3.500 $3.000 $2.680 $2.000 $1.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,735.000 $1.500 $0.250 $0.680 $1.000 $0.600
INTERSECTIONS (ACP)
SY 6,349.000 $30.000 $15.000 $19.950 $23.000 $16.500
DRIVEWAYS (ACP)
SY 8,420.000 $25.000 $15.000 $19.310 $26.000 $24.000
TURNOUTS (ACP)
SY 300.000 $60.000 $15.000 $24.500 $30.000 $24.000
DRIVEWAYS (BASE)
SY 105.000 $60.000 $10.000 $8.250 $30.000 $10.300
RUMBLE STRIPS (SHOULDER)
LF 279,152.000 $0.200 $0.150 $0.090 $0.140 $0.100
MTL W-BEAM GD FEN (TIM POST)
LF 2,094.000 $20.000 $24.000 $24.210 $24.000 $21.750
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $1,900.000 $2,000.000 $2,412.000 $1,900.000 $1,550.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 14.000 $1,200.000 $1,500.000 $1,263.000 $1,250.000 $1,325.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 231.000 $50.000 $100.000 $63.160 $65.000 $88.500
REMOVE METAL BEAM GUARD FENCE
LF 1,650.000 $3.000 $3.000 $3.160 $2.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $250.000 $150.000 $368.000 $250.000 $125.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $260.000 $300.000 $368.000 $250.000 $250.000
RM MTL BM GD FEN TRANS (T101)
EA 6.000 $250.000 $300.000 $160.000 $125.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 20.000 $2,100.000 $2,700.000 $2,821.000 $2,750.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 12.000 $250.000 $300.000 $264.000 $275.000 $250.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 94.000 $20.000 $40.000 $27.000 $27.500 $30.000
INSTL DEL ASSM (D-SY)SZ (BRF)GF1 (BR)
EA 67.000 $20.000 $40.000 $27.000 $27.500 $12.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 38,460.000 $0.200 $0.150 $0.170 $0.140 $0.140
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 151,235.000 $0.200 $0.150 $0.170 $0.140 $0.140
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 155,591.000 $0.180 $0.150 $0.170 $0.140 $0.140
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,206.000 $1.180 $1.000 $1.000 $1.000 $1.250
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 276.000 $1.000 $1.000 $1.000 $1.000 $1.250
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 438.000 $1.300 $1.250 $1.050 $1.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 44,894.000 $0.800 $0.800 $0.930 $0.750 $0.720
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 665.000 $3.000 $4.000 $3.680 $3.000 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 837.000 $6.000 $6.000 $7.600 $6.000 $5.650
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 544.000 $25.000 $25.000 $7.890 $18.000 $17.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 775.000 $6.250 $6.000 $7.600 $6.000 $5.650
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 38,460.000 $0.300 $0.360 $0.360 $0.350 $0.340
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 151,235.000 $0.300 $0.320 $0.360 $0.350 $0.310
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 155,591.000 $0.300 $0.320 $0.360 $0.350 $0.310
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 904.000 $10.000 $12.000 $11.790 $10.750 $10.250
PREFAB PAV MRK TY C (W) (ARROW)
EA 76.000 $180.000 $225.000 $237.000 $200.000 $195.000
PREFAB PAV MRK TY C (W) (WORD)
EA 7.000 $300.000 $250.000 $237.000 $225.000 $225.000
REFL PAV MRKR TY II-A-A
EA 276.000 $3.500 $4.000 $4.210 $3.250 $3.100
REFL PAV MRKR TY II-C-R
EA 4,206.000 $3.000 $3.500 $4.210 $3.000 $2.950
BONDING COURSE
GAL 73,710.000 $4.000 $2.500 $3.200 $3.000 $3.600
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $9,000.000 $3,500.000 $2,430.000 $2,500.000 $19,800.000
TMA (STATIONARY)
EA 2.000 $10,000.000 $5,000.000 $18,715.000 $5,000.000 $21,600.000
TMA (MOBILE OPERATION)
DAY 100.000 $300.000 $150.000 $30.000 $50.000 $350.000
Totals: $8,634,711.910 $7,687,390.670 $8,256,462.070 $10,270,071.420 $11,626,224.080