ROBERTS FM 282 (0798-01-025)

Items: 73

County: ROBERTS
Length: N/A
Highway: FM 282
District: AMARILLO
Control Number: 0798-01-025
DBE Goal: N/A
Project: BR 2018(223)
Guaranty: N/A
Time: 242 WORKING DAYS
Engineer's Estimate: $2,395,204.70
Date: 02/02/2018 (8 years ago)
Contract Number: N/A
Type: REPLACE EXISTING BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$2,395,204.70
$2,093,931.75
Over/Under Est: -12.58% -$301,272.95
$2,168,659.60
Over/Under Est: -9.46% -$226,545.10
Amt Left: 3.57% $74,727.85
Over/Under Est: -4.09% -$97,864.30
Amt Left: 9.71% $203,408.65
Delta: -5.93% -$128,680.80
$2,356,358.40
Over/Under Est: -1.62% -$38,846.30
Amt Left: 12.53% $262,426.65
Delta: -2.57% -$59,018.00
Over/Under Est: 2.2% $52,727.75
Amt Left: 16.91% $354,000.70
Delta: -3.89% -$91,574.05
$2,640,000.00
Over/Under Est: 10.22% $244,795.30
Amt Left: 26.08% $546,068.25
Delta: -7.85% -$192,067.55
$2,802,854.85
Over/Under Est: 17.02% $407,650.15
Amt Left: 33.86% $708,923.10
Delta: -6.17% -$162,854.85
$2,819,391.45
Over/Under Est: 17.71% $424,186.75
Amt Left: 34.65% $725,459.70
Delta: -0.59% -$16,536.60

Bid Items & Bid Tabulations

73 Total 0 of 73
ROBERTS  |  FM 282  |  AMARILLO  |  0798-01-025  |  02/02/2018  |  $2,395,204.70  |  BR 2018(223)  |  REPLACE EXIST BRIDGE AND APPROACHES  |  242 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
GILVIN-TERRILL, LTD.
HODGES AND SON CONSTRUCTION COMPANY, INC.
EARTH BUILDERS, L.P.
COPPELL CONSTRUCTION CO., INC.
PIERCE R & B LLC
J. LEE MILLIGAN, INC.
DCI CONTRACTING, INC.
PREPARING ROW
STA 6.000 $2,000.000 $3,200.000 $490.000 $10,000.000 $18,000.000 $9,000.000 $5,000.000 $3,050.000 $4,162.530
PREPARING ROW (TREE) (0" TO 6" DIA)
EA 123.000 $250.000 $100.000 $42.000 $400.000 $50.000 $268.000 $250.000 $60.000 $204.250
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 16.000 $1,250.000 $500.000 $42.000 $1,800.000 $200.000 $650.000 $1,000.000 $560.000 $936.570
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 1.000 $1,250.000 $1,500.000 $42.000 $2,200.000 $800.000 $1,500.000 $2,081.300 $2,475.000 $5,130.000
PREPARING ROW (HAND CLEARING)
AC 0.400 $2,500.000 $2,000.000 $22,000.000 $100,000.000 $5,000.000 $22,700.000 $12,000.000 $12,000.000 $30,375.000
PREPARING ROW (TREE) (36" TO 48" DIA)
EA 1.000 $5,000.000 $2,500.000 $42.000 $2,600.000 $1,500.000 $2,900.000 $5,000.000 $5,000.000 $7,695.000
REMOVING CONC (RIPRAP)
SY 408.000 $12.000 $8.000 $50.000 $20.000 $12.000 $13.700 $30.000 $15.500 $53.960
REMOVING CONC (SIDEWALKS)
SY 26.000 $20.000 $25.000 $511.000 $20.000 $12.000 $94.000 $30.000 $26.000 $54.000
REMOVING STAB BASE & ASPH PAV (8"-12")
SY 337.000 $10.000 $28.000 $35.000 $20.000 $30.000 $35.000 $32.000 $24.000 $45.510
EXCAVATION (ROADWAY)
CY 536.000 $25.000 $15.000 $35.000 $30.000 $25.000 $18.500 $35.000 $40.300 $40.320
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 126.000 $50.000 $35.000 $45.000 $100.000 $50.000 $165.000 $50.000 $54.700 $54.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 0.880 $2,500.000 $1,900.000 $1,820.000 $2,400.000 $3,000.000 $2,185.000 $2,025.000 $3,700.000 $2,788.980
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 0.880 $2,500.000 $1,900.000 $1,750.000 $2,400.000 $3,000.000 $2,185.000 $1,965.000 $3,700.000 $2,684.670
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 2,055.000 $4.000 $1.500 $2.000 $3.000 $2.500 $2.150 $1.500 $5.000 $1.760
D-GR HMA(SQ) TY-C PG70-28
TON 166.000 $600.000 $210.000 $230.000 $250.000 $240.000 $352.000 $360.000 $315.000 $303.750
PLANE ASPH CONC PAV(0" TO 2")
SY 750.000 $10.000 $12.500 $27.000 $12.000 $10.000 $25.000 $20.000 $13.150 $17.390
CEM STABIL BKFL
CY 108.000 $160.000 $225.000 $172.000 $300.000 $200.000 $260.000 $250.000 $200.000 $267.520
TEMPORARY SPL SHORING
SF 2,508.000 $9.010 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
TEMPORARY SPL SHORING (SOIL NAIL)
SF 548.000 $40.000 $35.000 $72.000 $40.000 $20.000 $80.000 $60.000 $62.000 $105.940
PRESTR CONC PIL (16 IN SQ)
LF 3,690.000 $70.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
CL C CONC (ABUT)(HPC)
CY 51.300 $1,000.000 $960.000 $1,598.000 $1,200.000 $1,800.000 $1,750.000 $1,600.000 $1,450.000 $1,059.500
CL C CONC (CAP)(HPC)
CY 59.200 $1,200.000 $1,075.000 $1,710.000 $1,200.000 $1,800.000 $1,450.000 $1,800.000 $1,630.000 $1,909.890
CL C CONC (COLUMN)(HPC)
CY 37.800 $1,500.000 $1,125.000 $652.000 $1,300.000 $1,000.000 $1,300.000 $1,800.000 $1,100.000 $1,914.350
CL C CONC (FOOTING)(HPC)
CY 75.000 $700.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
REINF CONC SLAB (HPC)
SF 11,172.000 $30.000 $20.250 $34.000 $28.000 $32.000 $27.500 $28.000 $32.050 $21.550
BRIDGE SIDEWALK (HPC)
SF 2,280.000 $20.000 $12.450 $14.000 $26.000 $10.000 $9.000 $52.000 $13.000 $8.440
APPROACH SLAB (HPC)
CY 76.500 $680.000 $675.000 $850.000 $600.000 $700.000 $600.000 $600.000 $625.000 $652.970
PRESTR CONC GIRDER (TX28)
LF 1,572.000 $200.000 $185.000 $151.000 $180.000 $175.000 $177.750 $200.000 $185.000 $291.580
RIPRAP (CONC)(5 IN)
CY 122.000 $576.000 $500.000 $367.000 $500.000 $650.000 $600.000 $500.000 $600.000 $730.400
RIPRAP (MOW STRIP)(4 IN)
CY 33.000 $500.000 $450.000 $367.000 $500.000 $650.000 $660.000 $475.000 $1,000.000 $797.760
STR STEEL (MISC NON - BRIDGE)
LB 237.000 $7.000 $35.000 $10.000 $30.000 $12.000 $16.500 $30.000 $35.250 $4.650
RAIL (TY T223)(HPC)
LF 288.000 $114.000 $110.000 $83.000 $110.000 $100.000 $125.000 $150.000 $110.000 $119.100
RAIL (TY C223)(HPC)
LF 288.000 $140.000 $155.000 $108.000 $165.000 $150.000 $200.000 $150.000 $150.000 $175.640
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 105.000 $130.000 $95.000 $100.000 $100.000 $100.000 $100.000 $120.000 $145.000 $115.730
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $95,000.000 $125,000.000 $225,000.000 $120,000.000 $176,000.000 $126,000.000 $175,000.000 $155,000.000 $142,425.000
REMOVE STR (RAIL)
LF 47.000 $25.000 $40.000 $145.000 $20.000 $100.000 $40.000 $150.000 $120.000 $66.070
MOBILIZATION
LS 1.000 $174,700.000 $200,000.000 $180,000.000 $205,000.000 $220,000.000 $240,000.000 $250,000.000 $280,000.000 $349,515.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $10,000.000 $8,550.000 $2,000.000 $6,000.000 $3,000.000 $4,000.000 $4,000.000 $17,740.000 $2,519.350
TEMP SEDMT CONT FENCE (INSTALL)
LF 392.000 $4.200 $3.000 $5.000 $4.000 $3.500 $3.000 $4.000 $4.500 $4.150
TEMP SEDMT CONT FENCE (REMOVE)
LF 392.000 $1.500 $1.000 $1.000 $2.000 $1.000 $0.750 $1.000 $3.000 $1.350
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 521.000 $7.500 $3.000 $6.000 $12.000 $6.000 $4.500 $4.000 $9.150 $6.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 521.000 $2.000 $1.000 $1.000 $2.000 $1.000 $0.750 $1.000 $2.250 $1.350
CONSTRUCTING DETOURS
SY 384.000 $150.000 $195.000 $125.000 $80.000 $100.000 $263.000 $265.000 $111.000 $109.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 720.000 $15.000 $18.000 $35.000 $30.000 $15.000 $16.250 $22.000 $14.000 $33.400
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 660.000 $10.000 $14.000 $6.000 $20.000 $8.000 $12.500 $17.500 $13.000 $6.360
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 720.000 $10.300 $18.000 $8.000 $30.000 $12.000 $13.750 $22.000 $14.000 $33.400
CONC CURB & GUTTER (TY II)
LF 124.000 $30.000 $32.000 $27.000 $20.000 $35.000 $41.000 $40.000 $31.100 $40.500
CONC SIDEWALKS (4")
SY 109.000 $100.000 $38.000 $55.000 $60.000 $70.000 $78.000 $65.000 $67.150 $87.750
MTL W-BEAM GD FEN (STEEL POST)
LF 150.000 $27.000 $22.000 $20.000 $30.000 $24.000 $20.000 $30.000 $26.350 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,149.000 $1,650.000 $1,440.000 $2,000.000 $1,600.000 $2,200.000 $2,300.000 $2,215.000 $1,944.000
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $3.250 $2.000 $55.000 $5.000 $2.000 $1.750 $4.500 $4.250 $2.370
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $287.000 $250.000 $150.000 $500.000 $200.000 $200.000 $450.000 $425.000 $202.500
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,675.000 $2,200.000 $1,995.000 $2,600.000 $2,500.000 $2,000.000 $2,985.000 $3,000.000 $2,693.250
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $620.000 $900.000 $560.000 $1,000.000 $400.000 $650.000 $1,140.000 $1,055.000 $1,080.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 1.000 $475.000 $900.000 $610.000 $1,000.000 $350.000 $700.000 $1,250.000 $1,160.000 $1,080.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $850.000 $900.000 $555.000 $1,000.000 $250.000 $700.000 $1,275.000 $1,215.000 $1,080.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 3.000 $750.000 $1,200.000 $775.000 $1,200.000 $500.000 $800.000 $1,316.000 $1,265.000 $1,080.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,000.000 $900.000 $890.000 $1,200.000 $380.000 $1,050.000 $1,325.000 $1,265.000 $1,080.000
REMOVE SM RD SN SUP&AM
EA 12.000 $120.000 $350.000 $70.000 $200.000 $50.000 $100.000 $200.000 $130.000 $135.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $60.000 $25.000 $20.000 $60.000 $20.000 $18.000 $40.000 $26.350 $67.500
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 6.000 $60.000 $25.000 $20.000 $60.000 $20.000 $18.000 $40.000 $26.350 $67.500
REMOVE DELIN & OBJECT MARKER ASSMS
EA 5.000 $15.000 $25.000 $2.000 $20.000 $2.500 $2.000 $23.500 $10.000 $67.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $60.000 $25.000 $25.000 $60.000 $25.000 $21.000 $54.000 $42.000 $67.500
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 3,165.000 $1.000 $3.750 $4.000 $1.000 $3.500 $3.250 $1.500 $3.450 $2.700
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $30.000 $28.000 $25.000 $20.000 $28.000 $25.000 $25.000 $26.350 $22.510
PAVEMENT SEALER 4"
LF 1,141.000 $1.000 $1.100 $1.000 $0.300 $1.200 $1.000 $1.100 $1.050 $2.660
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 1,121.000 $1.000 $2.200 $2.000 $0.600 $2.400 $2.000 $2.200 $2.100 $2.700
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,462.000 $1.000 $2.200 $2.000 $0.600 $2.400 $2.000 $2.200 $2.100 $2.700
ELIM EXT PAV MRK & MRKS (4")
LF 840.000 $1.000 $5.500 $5.000 $1.000 $6.000 $5.000 $5.500 $5.250 $2.700
PAV SURF PREP FOR MRK (4")
LF 1,141.000 $0.800 $3.300 $3.000 $0.300 $3.500 $3.000 $3.300 $3.150 $2.700
TEMP TRAF SIGNALS
EA 1.000 $60,000.000 $45,000.000 $28,000.000 $40,000.000 $48,000.000 $60,000.000 $60,000.000 $100,600.000 $73,035.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $18,000.000 $15,000.000 $6,000.000 $10,000.000 $15,000.000 $12,000.000 $15,500.000 $24,375.000 $20,250.000
1
DRILL SHAFT (36 IN)
LF 1,244.000 $268.000 $210.000 $207.000 $200.000 $240.000 $252.000 $240.000 $290.000 $348.760
Totals: $2,728,601.780 $2,093,931.750 $2,168,659.600 $2,297,340.400 $2,356,358.400 $2,447,932.450 $2,640,000.000 $2,802,854.850 $2,819,391.475