REFUGIO US 77 (0371-03-137)

Items: 19

County: REFUGIO
Length: N/A
Highway: US 77
District: CORPUS CHRISTI
Control Number: 0371-03-137
DBE Goal: 0.0%
Project: STP 2B24(151)HES
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $3,555,675.00
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ROBERT ISASSI
CHANDLER WILLIAMS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,555,675.00
$2,270,268.00
Over/Under Est: -36.15% -$1,285,407.00
Over/Under Est: -35.98% -$1,279,338.00
Amt Left: 0.27% $6,069.00
Over/Under Est: -9.23% -$328,036.70
Amt Left: 42.17% $957,370.30
Delta: -41.79% -$951,301.30
$3,597,380.00
Over/Under Est: 1.17% $41,705.00
Amt Left: 58.46% $1,327,112.00
Delta: -11.46% -$369,741.70
Subcontractor Percentage Amount
J. H. ODEN CONTRACTING COMPANY 5.73% $130,251.90
JB PINNACLE GROUP, LLC 5.59% $127,069.48
HIGHWAY BARRICADES AND SERVICES, LLC 0.54% $12,275.05
Total: 11.86% $269,596.43

Bid Items & Bid Tabulations

19 Total 0 of 19
REFUGIO  |  US 77  |  CORPUS CHRISTI  |  0371-03-137  |  06/06/2024  |  $3,555,675.00  |  STP 2B24(151)HES  |  HAZARD ELIM & SAFETY  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCR CIVIL CONSTRUCTION, LLC
MASSANA CONSTRUCTION INC.
MB WESTERN INDUSTRIAL CONTRACTING CO.
FNH CONSTRUCTION, LLC
BACKFILL (TY A OR B)
STA 431.000 $785.000 $145.000 $220.000 $450.000 $450.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 10.000 $900.000 $1,940.000 $1,400.000 $2,268.000 $5,000.000
FERTILIZER
AC 10.000 $3,000.000 $850.000 $400.000 $648.000 $5,000.000
VEGETATIVE WATERING
MG 1,900.000 $52.000 $45.000 $27.000 $40.000 $50.000
RIPRAP (MOW STRIP)(5 IN)
CY 2,060.000 $485.000 $488.000 $360.000 $650.000 $600.000
MOBILIZATION
LS 1.000 $323,000.000 $122,000.000 $305,087.000 $475,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $4,000.000 $13,750.000 $1,966.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,120.000 $5.000 $5.150 $5.000 $7.290 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,120.000 $2.000 $2.300 $1.000 $1.620 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 3,430.000 $7.000 $13.000 $6.000 $8.100 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,430.000 $2.000 $3.400 $1.000 $1.620 $9.000
PERM CONC TRF BARR (SGL SLP) (TY 1 SPL)
LF 1,290.000 $450.000 $139.000 $150.000 $225.000 $300.000
CABLE BARRIER SYSTEM (TL-4)
LF 40,325.000 $14.000 $11.560 $14.000 $12.620 $16.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 54.000 $7,500.000 $2,000.000 $2,700.000 $3,824.000 $4,250.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $1,200.000 $10,000.000 $7,000.000 $2,500.000 $6,500.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 14.000 $20.000 $45.000 $50.000 $50.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 120.000 $70.000 $120.000 $45.000 $105.000 $150.000
TMA (STATIONARY)
DAY 240.000 $170.000 $200.000 $60.000 $100.000 $250.000
TMA (MOBILE OPERATION)
DAY 120.000 $400.000 $400.000 $60.000 $100.000 $550.000
Totals: $3,555,675.000 $2,270,268.000 $2,276,337.000 $3,227,638.300 $3,597,380.000