REEVES PR 30B (0626-01-007)

Items: 12

County: REEVES
Length: N/A
Highway: PR 30B
District: ODESSA
Control Number: 0626-01-007
DBE Goal: N/A
Project: C 626-1-7
Guaranty: N/A
Time: 18 WORKING DAYS
Engineer's Estimate: $438,564.87
Date: 05/02/2018 (8 years ago)
Contract Number: N/A
Type: REHAB PARK ROADS,PARKING LOTS AND CAMPSITE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$438,564.87
$560,740.00
Over/Under Est: 27.86% $122,175.13
Over/Under Est: 38.76% $170,007.23
Amt Left: 8.53% $47,832.10
Over/Under Est: 48.21% $211,435.13
Amt Left: 15.92% $89,260.00
Delta: -6.81% -$41,427.90
Over/Under Est: 91.16% $399,790.63
Amt Left: 49.51% $277,615.50
Delta: -28.98% -$188,355.50

Bid Items & Bid Tabulations

12 Total 0 of 12
REEVES  |  PR 30B  |  ODESSA  |  0626-01-007  |  05/02/2018  |  $438,564.87  |  C 626-1-7  |  REHAB PARK ROADS,PARKING LOTS AND CA...  |  18 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNH CONSTRUCTION, LLC
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
FNF CONSTRUCTION, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
REMOVING STAB BASE AND ASPH PAV (2")
SY 9,407.000 $15.000 $20.000 $7.500 $5.000 $3.500
PRIME COAT (AE-P)
GAL 1,882.000 $7.600 $8.000 $9.250 $8.000 $4.000
ASPH (AC-20XP)
GAL 2,823.000 $6.600 $8.000 $13.500 $6.000 $5.000
AGGR(TY-PB GR-4 SAC-B)
CY 87.000 $156.000 $300.000 $650.000 $300.000 $500.000
D-GR HMA(SQ) TY-C SAC-A PG70-22
TON 1,036.000 $160.000 $200.000 $200.000 $350.000 $350.000
MOBILIZATION
LS 1.000 $52,299.270 $40,000.000 $160,000.000 $85,549.000 $279,368.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $25,000.000 $7,500.000 $20,000.000 $25,000.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 30.000 $6.000 $10.000 $6.900 $9.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 12.000 $210.000 $200.000 $115.000 $163.000 $125.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 1,852.000 $2.000 $2.000 $4.600 $6.000 $5.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 2,128.000 $0.700 $2.000 $2.300 $3.000 $2.500
PRE PM TY B (ACC PRK)(WHT)(SYMBOL ONLY)
EA 10.000 $500.000 $100.000 $2,875.000 $3,700.000 $3,200.000
Totals: $438,564.870 $560,740.000 $608,572.100 $650,000.000 $838,355.500