REEVES IH 20 (0003-07-061)
Items: 55
County: REEVES
Length: N/A
Highway: IH 20
District: ODESSA
Control Number: 0003-07-061
DBE Goal: N/A
Project: C 3-7-61
Guaranty: N/A
Time: 283 WORKING DAYS
Engineer's Estimate: $24,055,038.72
Date: 01/05/2023 (3 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$24,055,038.72 | |||
| $18,857,193.76 |
-21.61%
-$5,197,844.96
|
|||
| $25,040,546.20 |
4.1%
$985,507.48
|
32.79%
$6,183,352.44
|
||
| $25,684,842.31 |
6.78%
$1,629,803.59
|
36.21%
$6,827,648.55
|
-2.57%
-$644,296.11
|
E
Engineer's Estimate
$24,055,038.72
1
Awarded
$18,857,193.76
Over/Under Est:
-21.61%
-$5,197,844.96
$25,040,546.20
Over/Under Est:
4.1%
$985,507.48
Amt Left:
32.79%
$6,183,352.44
$25,684,842.31
Over/Under Est:
6.78%
$1,629,803.59
Amt Left:
36.21%
$6,827,648.55
Delta:
-2.57%
-$644,296.11
| Subcontractor | Percentage | Amount |
|---|---|---|
| WILD WEST TRUCKING, LLC | 7.74% | $1,555,382.70 |
| STRUCTURAL INTEGRITY GROUP LLC | 2.69% | $540,565.82 |
| HJC FARMS, INC. | 2.52% | $506,403.67 |
| DUSTROL, INC. | 2.30% | $462,193.83 |
| TRP CONSTRUCTION GROUP, LLC | 1.21% | $243,154.14 |
| FC TRAFFIC CONTROL, INC. | 0.95% | $190,906.15 |
| V-TECH ENVIROMENTAL SERVICES | 0.16% | $32,152.61 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 0.15% | $30,143.08 |
| Total: | 17.72% | $3,560,902.00 |