REEVES IH 20 (0003-07-061)

Items: 55

County: REEVES
Length: N/A
Highway: IH 20
District: ODESSA
Control Number: 0003-07-061
DBE Goal: N/A
Project: C 3-7-61
Guaranty: N/A
Time: 283 WORKING DAYS
Engineer's Estimate: $24,055,038.72
Date: 01/05/2023 (3 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$24,055,038.72
$18,857,193.76
Over/Under Est: -21.61% -$5,197,844.96
$25,040,546.20
Over/Under Est: 4.1% $985,507.48
Amt Left: 32.79% $6,183,352.44
$25,684,842.31
Over/Under Est: 6.78% $1,629,803.59
Amt Left: 36.21% $6,827,648.55
Delta: -2.57% -$644,296.11
Subcontractor Percentage Amount
WILD WEST TRUCKING, LLC 7.74% $1,555,382.70
STRUCTURAL INTEGRITY GROUP LLC 2.69% $540,565.82
HJC FARMS, INC. 2.52% $506,403.67
DUSTROL, INC. 2.30% $462,193.83
TRP CONSTRUCTION GROUP, LLC 1.21% $243,154.14
FC TRAFFIC CONTROL, INC. 0.95% $190,906.15
V-TECH ENVIROMENTAL SERVICES 0.16% $32,152.61
PROFESSIONAL TRAFFIC CONTROL LLC 0.15% $30,143.08
Total: 17.72% $3,560,902.00

Bid Items & Bid Tabulations

55 Total 0 of 55
REEVES  |  IH 20  |  ODESSA  |  0003-07-061  |  01/05/2023  |  $24,055,038.72  |  C 3-7-61  |  HWY IMPRV  |  283 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KIEWIT INFRASTRUCTURE SOUTH CO.
FNF CONSTRUCTION, INC.
DAN WILLIAMS COMPANY
REMOVING STAB BASE AND ASPH PAV(8")
SY 61,790.000 $8.000 $5.250 $14.000 $6.000
BACKFILL (TY B)
STA 680.000 $325.000 $150.000 $298.000 $135.000
BLADING
HR 70.000 $175.000 $275.810 $250.000 $150.000
PROOF ROLLING
HR 70.000 $150.000 $206.560 $150.000 $72.000
REWORK BS MTL (TY D)(SURF)(ORD COMP)
SY 61,790.000 $1.500 $1.480 $2.500 $1.000
PRIME COAT (AE-P)
GAL 12,359.000 $4.950 $5.640 $8.000 $6.500
ASPH (AC-20-5TR)
GAL 147,513.000 $4.900 $4.400 $4.600 $5.050
AGGR(TY-PB GR-4 SAC-A)
CY 3,360.000 $199.000 $142.000 $140.000 $150.000
PLANE ASPH CONC PAV (3")
SY 368,770.000 $5.700 $2.120 $5.500 $1.500
PLANE ASPH CONC PAV (2 1/2")
SY 48,262.000 $5.700 $1.890 $5.250 $1.500
RIPRAP (MOW STRIP)(4 IN)
CY 146.000 $735.000 $780.910 $880.000 $650.000
MOBILIZATION
LS 1.000 $2,169,367.520 $1,961,152.310 $2,620,000.000 $1,500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $12,000.000 $25,000.000 $100,000.000 $25,500.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 2,480.000 $10.000 $10.720 $12.000 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,480.000 $1.150 $3.410 $2.300 $3.000
RUMBLE STRIPS (SHOULDER)
LF 152,376.000 $0.200 $0.220 $0.250 $0.160
MTL W-BEAM GD FEN (STEEL POST)
LF 3,300.000 $40.000 $36.260 $39.000 $36.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $3,135.000 $3,067.860 $3,285.000 $3,200.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 7.000 $2,250.000 $1,896.490 $2,030.000 $1,500.000
MTL BM GD FEN TRANS (NON - SYM)
EA 1.000 $3,200.000 $1,338.700 $1,435.000 $1,450.000
REMOVE METAL BEAM GUARD FENCE
LF 3,300.000 $3.900 $3.350 $4.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $315.000 $334.680 $415.000 $400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $3,780.000 $3,653.540 $3,910.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 7.000 $450.000 $334.680 $415.000 $400.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 58.000 $900.000 $1,098.850 $1,000.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $1,000.000 $1,115.580 $1,020.000 $855.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,300.000 $1,729.160 $1,745.000 $1,455.000
REMOVE SM RD SN SUP&AM
EA 63.000 $175.000 $111.560 $205.000 $155.000
IN SM RD SN SUP&AM TY10BWG(2)SA(T)
EA 3.000 $1,350.000 $2,342.730 $1,720.000 $1,450.000
INSTALL LRSS (STRUCT STEEL)
LB 10,245.000 $10.000 $8.920 $9.400 $7.850
REMOVE LRSA
EA 19.000 $1,500.000 $1,394.480 $1,000.000 $750.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 32.000 $85.000 $20.640 $22.000 $45.000
INSTL DEL ASSM (D-SY)SZ (BRF)GF1
EA 18.000 $45.000 $20.640 $22.000 $45.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 150.000 $35.000 $11.160 $34.000 $55.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 80.000 $100.000 $167.340 $90.000 $75.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND
EA 85.000 $147.000 $167.340 $91.000 $76.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 40.000 $83.000 $167.340 $92.000 $77.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 19,060.000 $1.000 $0.550 $0.800 $0.850
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 76,188.000 $0.750 $0.500 $0.750 $0.700
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 76,188.000 $0.800 $0.500 $0.750 $0.700
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,432.000 $1.750 $2.230 $2.000 $2.200
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,500.000 $1.150 $1.280 $1.200 $0.950
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 19,060.000 $0.800 $0.950 $0.900 $0.800
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 91,899.000 $0.800 $0.840 $0.750 $0.800
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 91,899.000 $0.750 $0.840 $0.750 $0.800
REFL PAV MRKR TY II-C-R
EA 1,039.000 $5.000 $5.580 $5.000 $4.250
SP MIXES SP-B SAC-B PG70-22
TON 33,827.000 $125.000 $95.000 $150.000 $200.000
TACK COAT
GAL 14,108.000 $4.500 $3.890 $5.550 $7.000
STONE-MTRX-ASPH SMA-D PG76-22
TON 60,855.000 $185.000 $148.910 $155.000 $215.000
BONDING COURSE
GAL 15,722.000 $5.500 $4.100 $14.000 $7.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $19,250.000 $24,061.620 $20,000.000 $15,000.000
AUTO PORT SMRT TRF MONITOR SYS (PLAN 1)
DAY 283.000 $770.000 $500.000 $100.000 $350.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $10,450.000 $8,701.560 $30,000.000 $10,000.000
TMA (STATIONARY)
DAY 283.000 $200.000 $500.000 $158.000 $315.000
TMA (MOBILE OPERATION)
DAY 283.000 $500.000 $850.000 $465.000 $520.000
Totals: $24,055,038.720 $18,857,193.760 $25,040,546.200 $25,684,842.310