RED RIVER FM 2120 (2041-01-018)
Items: 94
County: RED RIVER
Length: N/A
Highway: FM 2120
District: PARIS
Control Number: 2041-01-018
DBE Goal: N/A
Project: F 2023(957)
Guaranty: N/A
Time: 366 WORKING DAYS
Engineer's Estimate: $10,392,750.80
Date: 06/27/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
DANIEL TAYLOR
ZACHARY SMITH
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$10,392,750.80 | |||
| $9,798,191.22 |
-5.72%
-$594,559.58
|
|||
| $9,828,455.14 |
-5.43%
-$564,295.66
|
0.31%
$30,263.92
|
||
| $10,052,884.55 |
-3.27%
-$339,866.25
|
2.6%
$254,693.33
|
-2.28%
-$224,429.41
|
|
| $12,750,037.15 |
22.68%
$2,357,286.35
|
30.13%
$2,951,845.93
|
-26.83%
-$2,697,152.60
|
E
Engineer's Estimate
$10,392,750.80
1
Awarded
$9,798,191.22
Over/Under Est:
-5.72%
-$594,559.58
$9,828,455.14
Over/Under Est:
-5.43%
-$564,295.66
Amt Left:
0.31%
$30,263.92
$10,052,884.55
Over/Under Est:
-3.27%
-$339,866.25
Amt Left:
2.6%
$254,693.33
Delta:
-2.28%
-$224,429.41
$12,750,037.15
Over/Under Est:
22.68%
$2,357,286.35
Amt Left:
30.13%
$2,951,845.93
Delta:
-26.83%
-$2,697,152.60
| Subcontractor | Percentage | Amount |
|---|---|---|
| WITHERS CONSTRUCTION, LLC | 7.30% | $718,105.16 |
| BAHENA CONSTRUCTION CO., INC. | 5.45% | $536,119.60 |
| STRIPING TECHNOLOGY, L.P. | 2.93% | $288,225.77 |
| A. E. MOORE CONSTRUCTION, INC. | 2.69% | $264,616.83 |
| SOUTHERN CROSS CONTRACTORS, LLC | 0.84% | $82,631.28 |
| ANCHOR CONTRACTING, LLC | 0.64% | $62,957.16 |
| PANOLA SIGN & BARRICADE, INC. | 0.49% | $48,201.58 |
| Total: | 20.34% | $2,000,857.38 |
Bid Items & Bid Tabulations
94
Total
0 of 94