RED RIVER FM 1487 (1177-01-025)
Items: 83
County: RED RIVER
Length: N/A
Highway: FM 1487
District: PARIS
Control Number: 1177-01-025
DBE Goal: N/A
Project: STP 2020(888)
Guaranty: N/A
Time: 172 WORKING DAYS
Engineer's Estimate: $2,522,409.64
Date: 06/04/2020 (6 years ago)
Contract Number: N/A
Type: REHABILITATION OF EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,522,409.64 | |||
| $2,459,270.50 |
-2.5%
-$63,139.14
|
|||
| $2,473,936.26 |
-1.92%
-$48,473.38
|
0.6%
$14,665.76
|
||
| $2,524,647.16 |
0.09%
$2,237.52
|
2.66%
$65,376.66
|
-2.05%
-$50,710.90
|
|
| $2,570,321.80 |
1.9%
$47,912.16
|
4.52%
$111,051.30
|
-1.81%
-$45,674.64
|
|
| $2,625,718.48 |
4.1%
$103,308.84
|
6.77%
$166,447.98
|
-2.16%
-$55,396.68
|
|
| $2,983,104.08 |
18.26%
$460,694.44
|
21.3%
$523,833.58
|
-13.61%
-$357,385.60
|
|
| $3,714,220.00 |
47.25%
$1,191,810.36
|
51.03%
$1,254,949.50
|
-24.51%
-$731,115.92
|
E
Engineer's Estimate
$2,522,409.64
1
$2,459,270.50
Over/Under Est:
-2.5%
-$63,139.14
$2,473,936.26
Over/Under Est:
-1.92%
-$48,473.38
Amt Left:
0.6%
$14,665.76
$2,524,647.16
Over/Under Est:
0.09%
$2,237.52
Amt Left:
2.66%
$65,376.66
Delta:
-2.05%
-$50,710.90
$2,570,321.80
Over/Under Est:
1.9%
$47,912.16
Amt Left:
4.52%
$111,051.30
Delta:
-1.81%
-$45,674.64
$2,625,718.48
Over/Under Est:
4.1%
$103,308.84
Amt Left:
6.77%
$166,447.98
Delta:
-2.16%
-$55,396.68
$2,983,104.08
Over/Under Est:
18.26%
$460,694.44
Amt Left:
21.3%
$523,833.58
Delta:
-13.61%
-$357,385.60
$3,714,220.00
Over/Under Est:
47.25%
$1,191,810.36
Amt Left:
51.03%
$1,254,949.50
Delta:
-24.51%
-$731,115.92
Bid Items & Bid Tabulations