RED RIVER VARIOUS (0901-27-054)

Items: 40

County: RED RIVER
Length: 0.0000 MILES
Highway: VARIOUS
District: PARIS
Control Number: 0901-27-054
DBE Goal: 0.0%
Project: STP 2024(106)TAPS
Guaranty: $48,000.00
Time: 161 WORKING DAYS
Engineer's Estimate: $2,424,501.35
Date: 01/08/2025 (1 year ago)
Contract Number: 1253218
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00187241
Contract Type: Federal
Project Description: CONSTRUCT 10-FOOT-WIDE SHARED USE PATH ON FORMER RAILROAD RIGHT-OF-WAY; ASPHALT SURFACE PATH WILL INCLUDE BENCHES, BIKE RACKS, TRASH RECEPTACLES, BOLLARDS, AND/OR SIGNAGE AND SIGNAGE/PAVEMENT MARKINGS, IMPROVES PART OF NETT
Mail/Deliver Bids To: N/A
DANIEL TAYLOR
ZACHARY SMITH
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$2,424,501.35
1
$2,074,733.10
Over/Under Est: -14.43% -$349,768.25
Over/Under Est: -13.99% -$339,153.58
Amt Left: 0.51% $10,614.67
$2,398,975.09
Over/Under Est: -1.05% -$25,526.26
Amt Left: 15.63% $324,241.99
Delta: -15.04% -$313,627.32
$2,697,012.50
Over/Under Est: 11.24% $272,511.15
Amt Left: 29.99% $622,279.40
Delta: -12.42% -$298,037.41
Over/Under Est: 19.21% $465,805.80
Amt Left: 39.31% $815,574.05
Delta: -7.17% -$193,294.65
Over/Under Est: 68.85% $1,669,360.65
Amt Left: 97.32% $2,019,128.90
Delta: -41.64% -$1,203,554.85
Subcontractor Percentage Amount
DUSTIN ALLEN, INC. 9.50% $232,458.96
RB CONTRACTING, LLC 8.76% $214,351.63
WITHERS CONSTRUCTION, LLC 7.96% $194,776.14
J. H. ODEN CONTRACTING COMPANY 3.59% $87,845.02
SOUTHERN CROSS CONTRACTORS, LLC 2.34% $57,258.31
PANOLA SIGN & BARRICADE, INC. 1.04% $25,448.14
STRIPE-A-ZONE, LLC 0.26% $6,362.03
Total: 33.45% $818,500.23

Bid Items & Bid Tabulations

40 Total 0 of 40
RED RIVER  |  VARIOUS  |  PARIS  |  0901-27-054  |  01/08/2025  |  $2,424,501.35  |  STP 2024(106)TAPS  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  161 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CDM HOLDINGS
H. H. HOWARD & SONS, INC.
H. V. CAVER, INC.
FNH CONSTRUCTION, LLC
SAMMY GIST ENTERPRISES, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
PREPARING ROW
STA 150.600 $1,500.000 $1,360.000 $1,200.000 $1,200.000 $3,000.000 $1,463.000 $2,500.000
EXCAV (ROADWAY)
CY 1,955.000 $20.000 $12.000 $10.000 $30.000 $20.000 $20.000 $150.000
EMBANK (FNL)(OC)(TY B)
CY 4,158.000 $30.000 $20.000 $20.000 $35.000 $40.000 $40.000 $100.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 19,001.000 $0.250 $0.200 $0.190 $0.190 $0.500 $0.198 $4.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 38,002.000 $0.150 $0.200 $0.190 $0.180 $0.500 $0.176 $4.000
VEGETATIVE WATERING
TGL 2,827.200 $1.500 $5.000 $1.000 $1.000 $30.000 $1.000 $50.000
RDSIDE AMENITY (TRASH/RECYCLE BIN)
EA 9.000 $850.000 $750.000 $850.000 $500.000 $5,000.000 $907.000 $5,000.000
RDSIDE AMENITY (BENCH)
EA 7.000 $2,000.000 $2,000.000 $2,000.000 $1,611.430 $5,000.000 $2,112.000 $6,500.000
RDSIDE AMENITY
EA 3.000 $2,000.000 $1,650.000 $2,000.000 $894.000 $5,000.000 $2,056.000 $6,500.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 57,756.000 $20.000 $14.500 $17.500 $20.780 $15.000 $24.500 $20.000
RC PIPE (CL III)(18 IN)
LF 19.000 $170.000 $431.000 $60.000 $60.000 $85.000 $451.000 $125.000
RC PIPE (CL III)(48 IN)
LF 36.000 $300.000 $850.000 $250.000 $267.000 $250.000 $880.000 $300.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,400.000 $4,420.000 $1,000.000 $995.000 $1,850.000 $4,620.000 $1,000.000
SET (TY II) (48 IN) (RCP) (6: 1) (C)
EA 2.000 $11,500.000 $25,500.000 $15,000.000 $10,388.000 $4,500.000 $26,400.000 $3,500.000
CLEAN EXIST CULVERTS
EA 1.000 $2,000.000 $800.000 $1,000.000 $3,200.000 $1,500.000 $3,000.000 $2,500.000
REMOV STR (PIPE)
LF 55.000 $25.000 $28.000 $15.000 $40.000 $50.000 $27.500 $30.000
MOBILIZATION
LS 1.000 $220,000.000 $180,000.000 $125,000.000 $140,000.000 $250,000.000 $275,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $5,000.000 $3,500.000 $3,000.000 $3,000.000 $8,500.000 $6,000.000 $3,500.000
TMA (STATIONARY)
DAY 30.000 $250.000 $10.000 $200.000 $250.000 $250.000 $100.000 $350.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 495.000 $50.000 $50.000 $50.000 $36.000 $40.000 $38.500 $75.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 305.000 $75.000 $80.000 $70.000 $61.000 $40.000 $66.000 $75.000
ROCK FILTER DAMS (REMOVE)
LF 800.000 $17.000 $11.000 $10.000 $12.500 $20.000 $13.200 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,845.000 $5.000 $4.500 $4.000 $3.600 $4.000 $3.850 $20.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,845.000 $1.000 $2.000 $1.000 $0.770 $2.000 $0.830 $5.000
CONC SIDEWALKS (4")
SY 200.000 $120.000 $180.000 $150.000 $197.000 $75.000 $181.000 $100.000
FIXED BOLLARD
EA 72.000 $500.000 $1,100.000 $850.000 $1,500.000 $1,000.000 $850.000 $2,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 19.000 $750.000 $1,000.000 $710.000 $750.000 $1,500.000 $743.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 18.000 $750.000 $1,000.000 $800.000 $800.000 $1,500.000 $808.000 $1,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $300.000 $720.000 $1,000.000 $900.000 $1,100.000 $655.000 $500.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 30.000 $22.000 $20.500 $55.000 $51.000 $20.000 $55.000 $25.000
PAVEMENT SLER 24"
LF 30.000 $12.000 $5.500 $55.000 $51.000 $20.000 $55.000 $4.000
PAVEMENT SLER (WORD)
EA 4.000 $200.000 $78.000 $225.000 $205.000 $250.000 $220.000 $500.000
PAVEMENT SLER (BIKE SYMBOL)
EA 4.000 $200.000 $78.000 $225.000 $205.000 $250.000 $220.000 $500.000
PREFAB PM TY C (W)(WORD)
EA 4.000 $400.000 $325.000 $550.000 $505.000 $250.000 $550.000 $500.000
PREFAB PM TY C (W)(BIKE SYMBOL)
EA 4.000 $400.000 $325.000 $550.000 $505.000 $250.000 $550.000 $500.000
PAV SURF PREP FOR MRK (24")
LF 30.000 $11.000 $3.300 $30.000 $26.000 $20.000 $27.500 $250.000
PAV SURF PREP FOR MRK (WORD)
EA 4.000 $250.000 $33.000 $300.000 $255.000 $250.000 $275.000 $250.000
PAV SURF PREP FOR MRK (BIKE SYMBOL)
EA 4.000 $250.000 $33.000 $300.000 $255.000 $250.000 $275.000 $250.000
POST AND CABLE FENCE (NEW INSTALLATION)
LF 11,620.000 $25.000 $20.000 $25.000 $22.000 $30.000 $26.000 $50.000
REMOVABLE BOLLARD
EA 36.000 $1,100.000 $2,200.000 $1,200.000 $1,500.000 $500.000 $1,350.000 $500.000
Totals: $2,424,501.350 $2,074,733.100 $2,085,347.770 $2,398,975.090 $2,697,012.500 $2,890,307.150 $4,093,862.000