RED RIVER FM 1158 (0427-02-009)
Items: 72
County: RED RIVER
Length: N/A
Highway: FM 1158
District: PARIS
Control Number: 0427-02-009
DBE Goal: N/A
Project: STP 2018(279)
Guaranty: N/A
Time: 110 WORKING DAYS
Engineer's Estimate: $2,703,451.22
Date: 11/03/2017 (8 years ago)
Contract Number: N/A
Type: REHABILITATION OF EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,703,451.22 | |||
| $2,040,371.54 |
-24.53%
-$663,079.68
|
|||
| $2,087,695.11 |
-22.78%
-$615,756.11
|
2.32%
$47,323.57
|
||
| $2,286,484.56 |
-15.42%
-$416,966.66
|
12.06%
$246,113.02
|
-9.52%
-$198,789.45
|
|
| $2,328,686.93 |
-13.86%
-$374,764.29
|
14.13%
$288,315.39
|
-1.85%
-$42,202.37
|
|
| $2,345,933.98 |
-13.22%
-$357,517.24
|
14.98%
$305,562.44
|
-0.74%
-$17,247.05
|
|
| $2,403,629.81 |
-11.09%
-$299,821.41
|
17.8%
$363,258.27
|
-2.46%
-$57,695.83
|
|
| $2,443,067.92 |
-9.63%
-$260,383.30
|
19.74%
$402,696.38
|
-1.64%
-$39,438.11
|
|
| $2,867,194.25 |
6.06%
$163,743.03
|
40.52%
$826,822.71
|
-17.36%
-$424,126.33
|
|
| $3,289,671.00 |
21.68%
$586,219.78
|
61.23%
$1,249,299.46
|
-14.73%
-$422,476.75
|
|
| $4,655,774.50 |
72.22%
$1,952,323.28
|
128.18%
$2,615,402.96
|
-41.53%
-$1,366,103.50
|
E
Engineer's Estimate
$2,703,451.22
1
$2,040,371.54
Over/Under Est:
-24.53%
-$663,079.68
$2,087,695.11
Over/Under Est:
-22.78%
-$615,756.11
Amt Left:
2.32%
$47,323.57
$2,286,484.56
Over/Under Est:
-15.42%
-$416,966.66
Amt Left:
12.06%
$246,113.02
Delta:
-9.52%
-$198,789.45
$2,328,686.93
Over/Under Est:
-13.86%
-$374,764.29
Amt Left:
14.13%
$288,315.39
Delta:
-1.85%
-$42,202.37
$2,345,933.98
Over/Under Est:
-13.22%
-$357,517.24
Amt Left:
14.98%
$305,562.44
Delta:
-0.74%
-$17,247.05
$2,403,629.81
Over/Under Est:
-11.09%
-$299,821.41
Amt Left:
17.8%
$363,258.27
Delta:
-2.46%
-$57,695.83
$2,443,067.92
Over/Under Est:
-9.63%
-$260,383.30
Amt Left:
19.74%
$402,696.38
Delta:
-1.64%
-$39,438.11
$2,867,194.25
Over/Under Est:
6.06%
$163,743.03
Amt Left:
40.52%
$826,822.71
Delta:
-17.36%
-$424,126.33
$3,289,671.00
Over/Under Est:
21.68%
$586,219.78
Amt Left:
61.23%
$1,249,299.46
Delta:
-14.73%
-$422,476.75
$4,655,774.50
Over/Under Est:
72.22%
$1,952,323.28
Amt Left:
128.18%
$2,615,402.96
Delta:
-41.53%
-$1,366,103.50
Bid Items & Bid Tabulations
72
Total
0 of 72