REAGAN RM1676 (6352-40-001)

Items: 16

County: REAGAN
Length: N/A
Highway: RM1676
District: SAN ANGELO
Control Number: 6352-40-001
DBE Goal: N/A
Project: RMC - 635240001
Guaranty: N/A
Time: 31 W
Engineer's Estimate: $736,594.50
Date: 01/09/2020 (6 years ago)
Contract Number: N/A
Type: RETRACE PAVEMENT MARKINGS AND MARKERS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$736,594.50
1
$621,295.80
Over/Under Est: -15.65% -$115,298.70
$636,289.10
Over/Under Est: -13.62% -$100,305.40
Amt Left: 2.41% $14,993.30
Over/Under Est: -13.36% -$98,431.50
Amt Left: 2.71% $16,867.20
Delta: -0.29% -$1,873.90
Over/Under Est: -9.05% -$66,667.80
Amt Left: 7.83% $48,630.90
Delta: -4.98% -$31,763.70
$676,747.50
Over/Under Est: -8.12% -$59,847.00
Amt Left: 8.93% $55,451.70
Delta: -1.02% -$6,820.80
Over/Under Est: 4.91% $36,141.50
Amt Left: 24.37% $151,440.20
Delta: -14.18% -$95,988.50

Bid Items & Bid Tabulations

16 Total 0 of 16
REAGAN  |  RM1676  |  SAN ANGELO  |  6352-40-001  |  01/09/2020  |  $736,594.50  |  RMC - 635240001  |  RETRACE PAVMT MRK AND MARKERS  |  31 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
L&L COMPANY
VIZCAINO, L.P.
TOTAL HIGHWAY MAINTENANCE, LLC
D. I. J. CONSTRUCTION, INC.
STRIPE-A-ZONE, INC.
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $56,000.000 $1.000 $1.000 $18,000.000 $13,750.000 $9,500.000 $25,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $1,500.000 $1.000 $1.000 $3,500.000 $100.000 $2,300.000 $1,500.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 235.000 $0.600 $1.000 $1.000 $1.000 $2.500 $2.000 $2.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 657.000 $5.500 $4.000 $5.000 $7.000 $12.000 $12.500 $8.000
PAVEMENT SEALER 24"
LF 225.000 $1.200 $1.000 $3.000 $1.500 $2.000 $1.000 $1.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 5,250.000 $0.240 $0.350 $0.280 $0.450 $0.400 $0.380 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,390.000 $0.240 $0.350 $0.280 $0.450 $0.450 $0.380 $0.450
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 4,200.000 $0.240 $0.350 $0.280 $0.450 $0.400 $0.380 $0.400
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 682,400.000 $0.530 $0.510 $0.520 $0.510 $0.510 $0.540 $0.600
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 74,030.000 $0.530 $0.510 $0.530 $0.550 $0.540 $0.540 $0.650
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 264,150.000 $0.530 $0.510 $0.520 $0.510 $0.510 $0.540 $0.600
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 3.000 $30.000 $50.000 $30.000 $100.000 $100.000 $0.600 $45.000
ELIM EXT PAV MRK & MRKS (24")
LF 7.000 $3.000 $5.000 $30.000 $40.000 $12.000 $4.400 $10.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 80.000 $45.000 $30.000 $10.000 $10.000 $20.000 $4.200 $4.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 22,670.000 $5.000 $4.000 $4.200 $3.450 $5.200 $4.200 $5.000
TMA (MOBILE OPERATION)
DAY 65.000 $200.000 $10.000 $20.000 $1.000 $1.000 $45.000 $65.000
Totals: $736,594.500 $621,295.800 $636,289.100 $638,163.000 $669,926.700 $676,747.500 $772,736.000