PREPARING ROW
|
STA
|
683.000
|
$500.000
|
$174.660
|
$1,764.130
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
20.000
|
$10.000
|
$363.330
|
$55.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
746.000
|
$9.000
|
$56.940
|
$22.000
|
|
|
REMOVING STAB BASE & ASPH PAV (10"-12")
|
SY
|
40,364.000
|
$3.000
|
$1.990
|
$2.460
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
39,036.000
|
$15.000
|
$12.950
|
$12.930
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
80,735.000
|
$20.000
|
$16.240
|
$10.180
|
|
|
BACKFILL (TY A OR B)
|
STA
|
695.000
|
$100.000
|
$125.900
|
$388.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
206,266.000
|
$0.150
|
$0.180
|
$0.190
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
103,133.000
|
$0.120
|
$0.130
|
$0.130
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
103,133.000
|
$0.110
|
$0.130
|
$0.130
|
|
|
FL BS (CMP IN PLC)(TY A GR 5)(6")
|
SY
|
4,121.000
|
$27.000
|
$15.890
|
$9.520
|
|
|
FL BS (RDWY DEL)(TY A GR 5)
|
TON
|
112,658.000
|
$15.000
|
$17.470
|
$28.570
|
|
|
FL BS (CMP IN PLC)(TY A GR 5)(9")
|
SY
|
52,566.000
|
$11.000
|
$15.400
|
$14.290
|
|
|
FOG SEAL (CSS-1H)
|
GAL
|
24,244.000
|
$4.000
|
$7.060
|
$4.540
|
|
|
ASPH (CRS-2P)
|
GAL
|
96,795.000
|
$3.500
|
$4.250
|
$4.810
|
|
|
AGGR(TY-PB GR-3 SAC-B)
|
CY
|
5,333.000
|
$92.000
|
$220.810
|
$136.900
|
|
|
ASPH (AC-20-5TR OR AC-20XP)
|
GAL
|
60,581.000
|
$4.250
|
$5.390
|
$5.360
|
|
|
CONC PVMT (CONT REINF - CRCP) (12")
|
SY
|
176.000
|
$75.000
|
$180.600
|
$189.200
|
|
|
CEM STABIL BKFL
|
CY
|
365.000
|
$165.000
|
$374.980
|
$379.020
|
|
|
CUT & RESTORING PAV
|
SY
|
870.000
|
$95.000
|
$120.760
|
$72.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
246.000
|
$15.000
|
$10.750
|
$10.870
|
|
|
TEMPORARY SPL SHORING
|
SF
|
20,281.000
|
$15.000
|
$22.650
|
$60.500
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
9.000
|
$500.000
|
$705.600
|
$713.210
|
|
|
RIPRAP (STONE COMMON)(DRY)(12 IN)
|
CY
|
143.000
|
$80.000
|
$192.420
|
$60.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
135.000
|
$500.000
|
$716.350
|
$770.000
|
|
|
GABIONS (3' X 3')(GALV)
|
CY
|
56.000
|
$275.000
|
$317.340
|
$110.000
|
|
|
CONC BOX CULV (7 FT X 4 FT)
|
LF
|
98.000
|
$525.000
|
$797.880
|
$1,079.550
|
|
|
CONC BOX CULV (8 FT X 4 FT)
|
LF
|
186.000
|
$550.000
|
$889.280
|
$1,197.750
|
|
|
CONC BOX CULV (10 FT X 4 FT)
|
LF
|
275.000
|
$850.000
|
$1,164.800
|
$1,578.130
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
406.000
|
$60.000
|
$112.490
|
$135.430
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
358.000
|
$80.000
|
$141.720
|
$173.130
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
924.000
|
$130.000
|
$211.610
|
$276.380
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
10.000
|
$5,500.000
|
$9,206.400
|
$9,305.730
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
12.000
|
$7,800.000
|
$10,550.400
|
$10,664.230
|
|
|
WINGWALL (PW - 1) (HW=6 FT)
|
EA
|
4.000
|
$20,000.000
|
$24,796.800
|
$25,064.330
|
|
|
WINGWALL (PW - 2) (HW=6 FT)
|
EA
|
2.000
|
$13,000.000
|
$24,864.000
|
$25,132.250
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (P)
|
EA
|
137.000
|
$1,215.000
|
$1,948.800
|
$1,969.830
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,300.000
|
$1,948.800
|
$1,969.830
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
2.000
|
$2,100.000
|
$2,419.200
|
$2,445.300
|
|
|
REMOV STR (PIPE)
|
EA
|
6.000
|
$500.000
|
$1,048.320
|
$1,179.300
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,183,400.000
|
$1,058,740.600
|
$1,106,572.600
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
24.000
|
$6,500.000
|
$15,688.400
|
$28,341.270
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
1,563.000
|
$30.000
|
$56.740
|
$36.300
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,563.000
|
$11.000
|
$16.990
|
$11.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
110.000
|
$3.800
|
$4.200
|
$4.400
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
110.000
|
$0.900
|
$1.050
|
$1.100
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
45,457.000
|
$7.000
|
$4.200
|
$6.600
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
45,457.000
|
$1.000
|
$1.870
|
$1.100
|
|
|
CONSTRUCTING DETOURS
|
SY
|
5,506.000
|
$61.000
|
$47.620
|
$66.000
|
|
|
ONE-WAY TRAF CONT (PILOT CAR)
|
HR
|
1,492.000
|
$100.000
|
$172.160
|
$264.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
6.000
|
$5,000.000
|
$6,776.440
|
$3,685.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
7,040.000
|
$35.000
|
$99.180
|
$76.300
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$50.000
|
$134.630
|
$94.500
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
18,040.000
|
$6.000
|
$11.900
|
$4.800
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
520.000
|
$12.000
|
$38.740
|
$7.200
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
7,040.000
|
$6.700
|
$14.820
|
$9.600
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$9.000
|
$41.800
|
$9.600
|
|
|
DRIVEWAYS (CONC)
|
SY
|
746.000
|
$100.000
|
$172.400
|
$145.200
|
|
|
DRIVEWAYS AND TURNOUTS (SURF TREAT)
|
SY
|
6,259.000
|
$25.000
|
$55.860
|
$39.840
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
136,548.000
|
$0.190
|
$0.090
|
$0.090
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
68,274.000
|
$0.190
|
$0.090
|
$0.090
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,750.000
|
$35.000
|
$36.750
|
$41.800
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
LF
|
100.000
|
$50.000
|
$28.350
|
$58.300
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
12.000
|
$3,000.000
|
$3,202.500
|
$3,850.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 1
|
EA
|
4.000
|
$280.000
|
$504.000
|
$440.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
1.000
|
$660.000
|
$766.500
|
$770.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
6.000
|
$225.000
|
$388.500
|
$330.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
93.000
|
$600.000
|
$703.500
|
$1,072.500
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
34.000
|
$710.000
|
$819.000
|
$1,204.500
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
2.000
|
$880.000
|
$1,018.500
|
$1,413.500
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
6.000
|
$800.000
|
$1,417.500
|
$1,683.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
5.000
|
$1,000.000
|
$1,312.500
|
$1,727.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
35.000
|
$31.000
|
$25.200
|
$165.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
12.000
|
$90.000
|
$131.250
|
$137.500
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
37,964.000
|
$0.650
|
$0.950
|
$0.990
|
|
|
WK ZN PAV MRK REMOV (W)12"(SLD)
|
LF
|
75.000
|
$3.800
|
$21.000
|
$22.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
24,004.000
|
$0.650
|
$0.950
|
$0.990
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,710.000
|
$0.700
|
$10.640
|
$2.200
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
1,416.000
|
$1.250
|
$1.050
|
$1.100
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,748.000
|
$0.660
|
$1.370
|
$1.430
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
347.000
|
$7.000
|
$8.400
|
$8.800
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
8,012.000
|
$0.140
|
$0.160
|
$0.170
|
|
REFL PAV MRK TY II (W) 4" (DOT)
|
LF
|
1,416.000
|
$0.500
|
$0.530
|
$0.550
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
135,468.000
|
$0.100
|
$0.130
|
$0.130
|
|
REFL PAV MRK TY II (W) 8" (SLD)
|
LF
|
1,748.000
|
$0.300
|
$0.530
|
$0.550
|
|
REFL PAV MRK TY II (W) 24" (SLD)
|
LF
|
347.000
|
$2.750
|
$2.100
|
$2.200
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
223,536.000
|
$0.130
|
$0.120
|
$0.120
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
8,012.000
|
$0.300
|
$0.550
|
$0.570
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
135,468.000
|
$0.300
|
$0.530
|
$0.550
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
223,536.000
|
$0.300
|
$0.530
|
$0.550
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
6.000
|
$205.000
|
$315.000
|
$330.000
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
8.000
|
$280.000
|
$787.500
|
$825.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
6.000
|
$230.000
|
$472.500
|
$495.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
600.000
|
$3.500
|
$4.200
|
$4.400
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
2,795.000
|
$3.000
|
$3.680
|
$3.850
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
1,486.000
|
$0.500
|
$2.100
|
$2.200
|
|
|
FULL - WIDTH MOWING
|
CYC
|
2.000
|
$3,900.000
|
$6,647.870
|
$110,000.000
|
|
|
LITTER REMOVAL
|
CYC
|
2.000
|
$1,800.000
|
$18,124.820
|
$55,000.000
|
|
|
SP MIXES SP-B SAC-B PG64-22
|
TON
|
57,626.000
|
$95.000
|
$103.000
|
$113.170
|
|
|
SP MIXES SP-C SAC-A PG70-22
|
TON
|
37,699.000
|
$100.000
|
$129.310
|
$129.660
|
|
|
TACK COAT
|
GAL
|
42,045.000
|
$3.000
|
$5.000
|
$4.060
|
|
|
CEMENT
|
TON
|
777.000
|
$195.000
|
$388.000
|
$302.500
|
|
|
ASPHALT BINDER (PG 64-22)
|
TON
|
1,825.000
|
$570.000
|
$1,250.370
|
$964.550
|
|
|
FOAMED ASPHALT TREAT (9")(DC)
|
SY
|
346,043.000
|
$3.000
|
$5.710
|
$4.080
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
870.000
|
$100.000
|
$74.120
|
$110.000
|
|
|
TMA (STATIONARY)
|
DAY
|
439.000
|
$200.000
|
$231.710
|
$168.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
30.000
|
$200.000
|
$511.280
|
$1,045.000
|
|
Totals: |
$24,085,404.910
|
$29,854,259.380
|
$32,240,907.990
|