PRESIDIO VARIOUS (0924-07-025)

Items: 26

County: PRESIDIO
Length: 1.2000 MILES
Highway: VARIOUS
District: EL PASO
Control Number: 0924-07-025
DBE Goal: 0.0%
Project: C 924-7-25
Guaranty: $14,000.00
Time: 92 WORKING DAYS
Engineer's Estimate: $848,847.00
Date: 07/01/2025 (11 months ago)
Contract Number: 7253027
Type: LANDSCAPE DEVELOPMENT
Project ID: A00213131
Project Description: FY 2025 GREEN RIBBON PROGRAM (PRESIDIO COUNTY)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ARMANDO RAMIREZ
ALDO MADRID
MONICA RUIZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$848,847.00
$1,179,327.80
Over/Under Est: 38.93% $330,480.80
$1,190,821.00
Over/Under Est: 40.29% $341,974.00
Amt Left: 0.97% $11,493.20
$1,278,802.00
Over/Under Est: 50.65% $429,955.00
Amt Left: 8.43% $99,474.20
Delta: -7.39% -$87,981.00
Subcontractor Percentage Amount
RH SERVICES #1, LLC 11.11% $131,023.32
AMERICHOICE CONSTRUCTION LLC 3.76% $44,342.73
BARRICADES UNLIMITED 3.66% $43,163.40
Total: 18.53% $218,529.45

Bid Items & Bid Tabulations

26 Total 0 of 26
PRESIDIO  |  VARIOUS  |  EL PASO  |  0924-07-025  |  07/01/2025  |  $848,847.00  |  C 924-7-25  |  LANDSCAPE DEVELOPMENT  |  92 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ABESCAPE LANDSCAPING, LLC
DIGG COMMERCIAL, LLC
RELMCO, INC.
PREPARING ROW
AC 1.310 $4,000.000 $6,106.870 $100,000.000 $25,000.000
EMBANK (FNL)(OC)(TY A)
CY 70.000 $200.000 $142.857 $100.000 $150.000
GENERAL USE COMPOST (1")
SY 5,514.000 $3.000 $0.725 $5.000 $5.000
IRRIGATION SYSTEM
LS 1.000 $150,000.000 $16,556.560 $200,000.000 $112,500.000
MULCH
SY 5,571.000 $8.000 $13.642 $5.000 $5.000
PLANT SOIL MIX (PLANTING SOIL)
CY 306.000 $20.000 $6.536 $200.000 $165.000
PLANT BED PREP (TY I)
SY 4,994.000 $13.000 $1.500 $2.000 $10.000
PLANT BED PREP (TY II)
SY 521.000 $15.000 $3.500 $5.000 $10.000
VEGETATION BARRIER
SY 6,903.000 $1.500 $1.159 $5.000 $4.000
LANDSCAPE EDGE
LF 9,089.000 $12.000 $19.309 $22.000 $15.000
LOOSE AGGR GRND COVER (TY I)
CY 46.000 $70.000 $217.391 $150.000 $200.000
LOOSE AGGR GRND COVER (TY II)
CY 99.000 $90.000 $141.414 $196.000 $200.000
PLANT MATERIAL (5 GAL)
EA 225.000 $90.000 $52.000 $38.000 $200.000
PLANT MATERIAL (15 GAL) (TREE)
EA 22.000 $275.000 $420.000 $222.000 $1,200.000
PLANT MATERIAL (20 GAL) (TREE)
EA 130.000 $500.000 $550.000 $400.000 $1,800.000
PLANT MATERIAL (3 GAL) (SHRUB)
EA 613.000 $60.000 $40.000 $39.000 $115.000
PLANT MATERIAL (MIN 8' TRNK HT)(PALM)
EA 18.000 $2,500.000 $1,400.000 $1,300.000 $2,200.000
LANDSCAPE ESTABLISH
MO 6.000 $1,500.000 $1,500.000 $4,220.000 $10,000.000
IRRIG SYS OPER AND MAINT
MO 6.000 $1,200.000 $2,000.000 $5,500.000 $10,000.000
MOBILIZATION
LS 1.000 $95,000.000 $204,444.440 $100,000.000 $95,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $9,000.000 $82,500.000 $5,000.000 $6,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $7,000.000 $6,600.000 $1,000.000 $17,000.000
TMA (STATIONARY)
DAY 35.000 $600.000 $420.000 $4,000.000 $300.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,095.000 $4.500 $6.500 $5.000 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,095.000 $4.000 $2.500 $2.000 $3.000
STUMP REMOVAL
EA 7.000 $1,500.000 $500.000 $300.000 $1,500.000
Totals: $848,847.000 $1,179,327.788 $1,190,821.000 $1,278,802.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $2,000.00
Total: $8,000.00