PRESIDIO US 67 (0104-10-006)

Items: 107

County: PRESIDIO
Length: N/A
Highway: US 67
District: EL PASO
Control Number: 0104-10-006
DBE Goal: N/A
Project: NH 1702(686)
Guaranty: N/A
Time: 260 WORKING DAYS
Engineer's Estimate: $6,318,695.68
Date: 08/09/2017 (8 years ago)
Contract Number: N/A
Type: NEW TWO-LANE TWIN BRIDGE STRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$6,318,695.68
$6,854,362.50
Over/Under Est: 8.48% $535,666.82
$7,310,837.30
Over/Under Est: 15.7% $992,141.62
Amt Left: 6.66% $456,474.80
$8,626,566.44
Over/Under Est: 36.52% $2,307,870.76
Amt Left: 25.86% $1,772,203.94
Delta: -18.00% -$1,315,729.14
Over/Under Est: 43.26% $2,733,463.44
Amt Left: 32.06% $2,197,796.62
Delta: -4.93% -$425,592.68

Bid Items & Bid Tabulations

107 Total 0 of 107
PRESIDIO  |  US 67  |  EL PASO  |  0104-10-006  |  08/09/2017  |  $6,318,695.68  |  NH 1702(686)  |  NEW TWO-LANE TWIN BRIDGE STRUCT  |  260 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EARTH BUILDERS, L.P.
DAN WILLIAMS COMPANY
FNF CONSTRUCTION, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
PREPARING ROW
STA 32.300 $422.500 $17,500.000 $7,200.000 $450.000 $900.000
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 11.000 $3,000.000 $1,000.000 $1,500.000 $2,400.000 $725.000
REMOVING CONC (RIPRAP)
SY 148.000 $19.500 $5.000 $10.000 $45.000 $64.940
REMOVING CONC (DRIVEWAYS)
SY 35.000 $52.000 $5.000 $11.500 $70.000 $89.390
REMOVING CONC (CURB AND GUTTER)
LF 2,094.000 $7.150 $2.000 $3.500 $22.000 $11.690
REMOVING CONC (CTB)
LF 320.000 $32.500 $5.000 $20.000 $50.000 $71.400
REMOVING CONC (FLUME)
SY 40.000 $26.000 $5.000 $11.500 $95.000 $87.140
REMOVING STAB BASE AND ASPH PAV(8")
SY 1,529.000 $8.450 $5.000 $4.000 $40.000 $24.020
EXCAVATION (ROADWAY)
CY 733.000 $13.000 $10.000 $20.000 $50.000 $36.970
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 6,020.000 $15.000 $20.000 $6.000 $46.000 $41.930
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 5,286.000 $27.300 $50.000 $30.000 $38.000 $35.000
PRIME COAT (MC-30)
GAL 885.000 $9.750 $10.000 $5.000 $6.000 $6.470
ASPH (TIER I)
GAL 3,988.000 $6.500 $10.000 $5.000 $4.000 $5.400
AGGR(TY-PB GR-4 SAC-A)
CY 40.000 $175.000 $400.000 $300.000 $380.000 $188.770
AGGR(TY-B GR-3 SAC-B)
CY 50.000 $149.500 $400.000 $300.000 $297.000 $188.770
CEM STABIL BKFL
CY 68.000 $170.000 $600.000 $650.000 $750.000 $797.390
FLOWABLE BACKFILL
CY 10.000 $260.000 $600.000 $650.000 $800.000 $747.220
TEMPORARY SPL SHORING
SF 446.420 $13.000 $25.000 $5.000 $50.000 $200.000
DRILL SHAFT (36 IN)
LF 300.000 $190.000 $300.000 $550.000 $700.000 $356.230
DRILL SHAFT (42 IN)
LF 612.000 $300.000 $400.000 $700.000 $800.000 $485.890
DRILL SHAFT (48 IN)
LF 426.000 $320.000 $500.000 $800.000 $1,100.000 $627.630
DRILL SHAFT (HIGH MAST POLE) (54 IN)
LF 90.000 $1,105.000 $650.000 $650.000 $755.000 $729.750
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 30.000 $390.000 $350.000 $250.000 $304.000 $488.040
CL A CONC (FLUME)
CY 25.000 $1,500.000 $1,000.000 $2,000.000 $1,557.000 $1,779.820
CL C CONC (ABUT)(HPC)
CY 28.500 $1,300.000 $2,000.000 $1,700.000 $1,900.000 $2,527.470
CL C CONC (CAP)(HPC)
CY 138.200 $1,400.000 $2,000.000 $3,500.000 $1,850.000 $2,320.600
CL C CONC (COLUMN)(HPC)
CY 111.800 $1,700.000 $2,000.000 $1,700.000 $1,800.000 $2,404.140
REINF CONC SLAB (HPC)
SF 23,165.000 $30.000 $27.000 $37.500 $36.000 $49.000
APPROACH SLAB (HPC)
CY 32.900 $750.000 $1,500.000 $1,100.000 $1,531.000 $1,337.910
RETAINING WALL (MSE)
SF 9,421.000 $90.000 $70.000 $85.000 $146.000 $89.250
PRESTR CONC GIRDER (TX54)
LF 2,812.820 $175.000 $200.000 $175.000 $210.000 $180.000
RIPRAP (CONC)(4 IN)
CY 9.000 $910.000 $1,000.000 $1,600.000 $1,500.000 $1,500.090
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 19.000 $429.000 $1,000.000 $1,600.000 $1,400.000 $580.380
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 16.000 $357.500 $200.000 $200.000 $275.000 $531.730
STR STEEL (MISC NON - BRIDGE)
LB 4,130.000 $13.000 $20.000 $4.000 $4.500 $5.220
RAIL (TY T221)(HPC)
LF 1,142.000 $140.000 $100.000 $115.000 $140.000 $279.780
RAIL (TY T551)
LF 647.000 $97.500 $125.000 $100.000 $135.000 $355.540
RAIL (TY C221)(HPC)
LF 565.000 $125.000 $100.000 $130.000 $175.000 $328.750
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 82.000 $120.000 $100.000 $85.000 $170.000 $159.410
RC PIPE (CL III)(18 IN)
LF 134.000 $97.500 $100.000 $90.000 $300.000 $150.050
RC PIPE (CL IV)(18 IN)
LF 12.000 $162.500 $125.000 $130.000 $670.000 $372.400
INLET (COMPL)(PCU)(5FT)(LEFT)
EA 2.000 $13,000.000 $7,500.000 $10,000.000 $13,000.000 $10,248.000
INLET(COMPL)(PSL)(SFG)(3FTX5FT-3FTX5FT)
EA 3.000 $13,650.000 $7,500.000 $8,000.000 $12,000.000 $7,425.520
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 1.000 $1,430.000 $2,500.000 $1,600.000 $4,500.000 $2,416.470
MOBILIZATION
LS 1.000 $750,000.000 $650,000.000 $700,000.000 $816,484.590 $900,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $23,400.000 $7,500.000 $5,000.000 $10,000.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 120.000 $45.500 $40.000 $110.000 $55.000 $18.340
ROCK FILTER DAMS (REMOVE)
LF 120.000 $15.600 $10.000 $15.000 $22.000 $10.790
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,812.000 $3.120 $5.000 $2.250 $10.000 $7.010
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,812.000 $1.630 $1.000 $0.500 $2.000 $1.620
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 130.000 $6.500 $10.000 $10.000 $8.000 $5.120
BIODEG EROSN CONT LOGS (REMOVE)
LF 130.000 $2.600 $1.000 $1.500 $4.500 $2.160
CONSTRUCTING DETOURS
SY 156.000 $45.500 $150.000 $70.000 $100.000 $75.000
CONSTRUCTING DETOURS (TY 1)
SY 750.000 $104.000 $150.000 $1.000 $100.000 $75.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 2,580.000 $32.500 $100.000 $90.000 $68.000 $203.470
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 360.000 $45.500 $100.000 $90.000 $59.000 $175.060
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 60.000 $6.500 $10.000 $6.000 $8.000 $7.790
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 80.000 $7.800 $10.000 $6.000 $12.000 $7.790
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 2,580.000 $9.750 $25.000 $8.000 $18.000 $12.570
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 360.000 $10.400 $25.000 $8.000 $27.000 $12.570
PERM CTB (F-SHAPE) (TY 1)
LF 246.000 $98.800 $100.000 $175.000 $160.000 $672.350
PERM CTB (F-SHAPE)(SPL)
LF 491.000 $195.000 $100.000 $650.000 $490.000 $671.870
CONC CURB & GUTTER (TY I)
LF 71.000 $13.000 $20.000 $75.000 $75.000 $118.650
CONC CURB & GUTTER (TY II)
LF 2,121.000 $15.600 $20.000 $60.000 $60.000 $71.190
DRIVEWAYS (CONC)
SY 48.000 $97.500 $80.000 $250.000 $200.000 $148.320
CONC SIDEWALKS (4")
SY 1,627.000 $39.000 $50.000 $150.000 $105.000 $106.790
CURB RAMPS (TY 2)
EA 1.000 $1,495.000 $5,000.000 $2,000.000 $2,500.000 $3,559.640
CURB RAMPS (TY 10)
EA 4.000 $1,300.000 $5,000.000 $2,000.000 $1,800.000 $3,559.640
CONC MEDIAN
SY 6.000 $91.000 $75.000 $300.000 $400.000 $148.320
REMOVE METAL BEAM GUARD FENCE
LF 65.000 $7.150 $5.000 $4.500 $9.000 $2.700
CRASH CUSH ATTEN (INSTL)
EA 3.000 $16,900.000 $20,000.000 $12,000.000 $17,900.000 $34,837.310
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 2.000 $17,550.000 $20,000.000 $13,000.000 $18,900.000 $34,837.310
CHAIN LINK FENCE (REMOVE)
LF 1,566.000 $5.200 $5.000 $4.000 $8.300 $6.670
GATE (REMOVE)
EA 1.000 $715.000 $1,000.000 $400.000 $400.000 $737.260
CHAIN LINK FENCE (INSTALL) (8')
LF 1,142.000 $97.500 $30.000 $35.000 $50.000 $48.940
CHAIN LINK FENCE(INSTALL)(6 )(BARB TOP)
LF 1,527.000 $65.000 $30.000 $22.000 $30.000 $22.090
GATE (INSTALL)(DOUBLE)(6'X22')
EA 1.000 $5,000.000 $2,500.000 $3,000.000 $6,000.000 $2,000.000
REMOVE RD IL ASM (SHOE-BASE)
EA 11.000 $2,470.000 $600.000 $550.000 $650.000 $623.480
IN RD IL (TY SA) 50B-8 (400W EQ) LED
EA 3.000 $5,200.000 $6,000.000 $5,800.000 $5,200.000 $5,609.140
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 3.000 $5,200.000 $6,000.000 $4,000.000 $5,000.000 $5,172.270
HI MST IL POLE (100 FT)( 80 MPH)
EA 3.000 $45,500.000 $25,000.000 $28,000.000 $33,690.000 $24,701.770
CONDT (PVC) (SCH 40) (2")
LF 3,015.000 $26.000 $20.000 $15.000 $19.000 $21.250
ELEC CONDR (NO.8) INSULATED
LF 12,220.000 $6.760 $3.000 $1.750 $2.000 $2.490
GROUND BOX TY A (122311)
EA 6.000 $1,495.000 $2,000.000 $1,000.000 $1,200.000 $1,725.890
GROUND BOX TY A (122311)W/APRON
EA 3.000 $1,690.000 $3,000.000 $1,050.000 $1,300.000 $2,869.290
ELC SRV TY A 240/480 060(NS)SS(E)GC(O)
EA 1.000 $9,080.500 $20,000.000 $6,000.000 $8,000.000 $20,494.920
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 3.000 $52.000 $500.000 $25.000 $41.000 $490.800
INSTL DEL ASSM (D-DY)SZ 1(FLX)GND
EA 1.000 $71.500 $1,200.000 $40.000 $276.000 $1,143.400
INSTL OM ASSM (OM-3L)(FLX)SRF
EA 2.000 $260.000 $1,000.000 $60.000 $483.000 $992.390
INSTL OM ASSM (OM-3R)(FLX)SRF
EA 1.000 $117.000 $1,500.000 $60.000 $550.000 $1,477.790
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
EA 17.000 $32.500 $250.000 $35.000 $69.000 $258.880
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BR)
EA 6.000 $23.400 $500.000 $35.000 $69.000 $480.010
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 1,231.000 $1.630 $2.500 $2.000 $2.700 $1.940
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 879.000 $1.760 $2.500 $2.000 $2.700 $1.940
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 3,101.000 $1.890 $3.000 $2.000 $2.850 $2.050
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 2,266.000 $1.890 $3.000 $2.000 $2.850 $2.050
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,015.000 $0.780 $2.500 $0.750 $1.000 $0.760
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 5,395.000 $0.720 $2.500 $0.750 $1.000 $0.760
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 5,340.000 $0.590 $2.500 $0.750 $1.000 $0.760
REFL PAV MRKR TY I-C
EA 104.000 $4.550 $5.000 $3.800 $5.500 $4.050
REFL PAV MRKR TY II-A-A
EA 170.000 $4.550 $5.000 $3.800 $5.500 $4.050
TRAFFIC BUTTON TY Y
EA 156.000 $5.200 $5.000 $4.050 $6.000 $4.310
ELIM EXT PAV MRK & MRKS (4")
LF 7,238.000 $0.460 $2.000 $0.650 $0.900 $0.650
PAV SURF PREP FOR MRK (4")
LF 11,836.000 $0.390 $1.000 $0.250 $0.300 $0.220
LANDSCAPE AMENITY
EA 1.000 $2,000.000 $10,000.000 $6,500.000 $19,000.000 $10,786.800
RMV, STCKPL, CLEAN, RELAY LOOSE AGGRGT
STA 1.500 $3,900.000 $10,000.000 $1,000.000 $6,000.000 $8,598.630
LED HI MST IL ASM(12 FIXT)(ASYM)(TY B)
EA 3.000 $65,000.000 $45,000.000 $38,000.000 $49,000.000 $43,886.100
Totals: $6,318,695.680 $6,854,362.500 $7,310,837.300 $8,626,566.440 $9,052,159.141