POTTER IH0040 (6468-76-001)

Items: 25

County: POTTER
Length: N/A
Highway: IH0040
District: AMARILLO
Control Number: 6468-76-001
DBE Goal: 0.0%
Project: RMC - 646876001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $762,150.00
Date: 07/09/2024 (1 year ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$762,150.00
$642,555.00
Over/Under Est: -15.69% -$119,595.00
$655,210.00
Over/Under Est: -14.03% -$106,940.00
Amt Left: 1.97% $12,655.00
$657,350.60
Over/Under Est: -13.75% -$104,799.40
Amt Left: 2.3% $14,795.60
Delta: -0.33% -$2,140.60
Subcontractor Percentage Amount
ELITE CASTLE RESOURCES LLC 42.66% $578,300.67
Total: 42.66% $578,300.67

Bid Items & Bid Tabulations

25 Total 0 of 25
POTTER  |  IH0040  |  AMARILLO  |  6468-76-001  |  07/09/2024  |  $762,150.00  |  RMC - 646876001  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROSS SA ENTERPRISE LLC
E.V.G. ENTERPRISE
HJC FARMS, INC.
MOBILIZATION (CALLOUT)
EA 12.000 $2,500.000 $2,000.000 $1,000.000 $2,000.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 5,000.000 $40.000 $40.000 $21.000 $30.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 80.000 $32.500 $34.000 $7.000 $20.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 50.000 $45.000 $44.000 $7.000 $30.000
RAISE RAIL ELEMENT
LF 400.000 $15.000 $7.000 $25.000 $5.000
REM / REPL TIMBER POST W / O CONC FND
EA 50.000 $45.000 $25.000 $20.000 $25.000
REM / REPL STEEL POST W / O CONC FND
EA 250.000 $150.000 $150.000 $400.000 $140.000
REM / REPL TIMBER POST W / CONC FND
EA 10.000 $45.000 $50.000 $20.000 $25.000
REM / REPL STEEL POST W / CONC FND
EA 35.000 $145.000 $125.000 $150.000 $140.000
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $500.000 $200.000 $10.000 $50.000
REALIGN POSTS
EA 150.000 $15.000 $10.000 $25.000 $5.000
REMOVE & REPLACE BLOCKOUT
EA 400.000 $25.000 $20.000 $100.000 $10.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 250.000 $55.000 $40.000 $24.000 $50.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 25.000 $125.000 $120.000 $200.000 $50.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 10.000 $50.000 $1.000 $10.000 $0.010
REPLACE HINGED TOP SGT STEEL POST
EA 50.000 $200.000 $150.000 $100.000 $200.000
RESET HINGED TOP SGT STL POST
EA 50.000 $75.000 $50.000 $100.000 $0.010
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 60.000 $5,800.000 $5,000.000 $5,000.000 $6,000.000
REM & RESET SGT IMPACT HEAD
EA 35.000 $800.000 $500.000 $300.000 $1,000.000
REPLACE SGT CABLE ASSEMBLY
EA 20.000 $80.000 $100.000 $20.000 $100.000
REPLACE SGT CABLE ANCHOR
EA 20.000 $80.000 $100.000 $20.000 $100.000
REPLACE SGT STRUT
EA 5.000 $70.000 $200.000 $20.000 $100.000
REPLACE SGT OBJECT MARKER
EA 20.000 $30.000 $30.000 $100.000 $100.000
REMOVE AND REPLACE DAT
EA 5.000 $2,500.000 $1,900.000 $1,500.000 $1,250.000
TMA (STATIONARY)
DAY 100.000 $350.000 $1.000 $350.000 $1.000
Totals: $762,150.000 $642,555.000 $655,210.000 $657,350.600