POTTER IH0040 (6461-70-001)
Items: 38
County: POTTER
Length: 0.0100 MILES
Highway: IH0040
District: AMARILLO
Control Number: 6461-70-001
DBE Goal: N/A
Project: BPM - A00206078
Guaranty: $40,000.00
Time: 140 WORKING DAYS
Engineer's Estimate: $2,003,276.25
Date: 02/06/2025 (1 year ago)
Contract Number: 2254001
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00206078
Project Description: FY 2025 BRIDGE PREVENTATIVE MAIN
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
POTTER IH0040 (6461-70-001)
Project Name: N/A
Project: BPM - A00206078
Length: 0.0100 MILES
Project Type: MAINTENANCE
Limits From: VARIOUS LOCATIONS ~ SEE PLAN SHEETS
Limits To: VARIOUS LOCATIONS ~ SEE PLAN SHEETS
Project Description: FY 2025 BRIDGE PREVENTATIVE MAIN
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,003,276.25 | |||
| $1,595,496.40 |
-20.36%
-$407,779.85
|
|||
| $1,958,958.00 |
-2.21%
-$44,318.25
|
22.78%
$363,461.60
|
||
| $2,222,923.60 |
10.96%
$219,647.35
|
39.32%
$627,427.20
|
-13.47%
-$263,965.60
|
|
| $2,244,810.74 |
12.06%
$241,534.49
|
40.7%
$649,314.34
|
-0.98%
-$21,887.14
|
|
| $2,320,724.00 |
15.85%
$317,447.75
|
45.45%
$725,227.60
|
-3.38%
-$75,913.26
|
|
| $2,397,783.00 |
19.69%
$394,506.75
|
50.28%
$802,286.60
|
-3.32%
-$77,059.00
|
|
| $3,239,847.00 |
61.73%
$1,236,570.75
|
103.06%
$1,644,350.60
|
-35.12%
-$842,064.00
|
E
Engineer's Estimate
$2,003,276.25
$1,595,496.40
Over/Under Est:
-20.36%
-$407,779.85
$1,958,958.00
Over/Under Est:
-2.21%
-$44,318.25
Amt Left:
22.78%
$363,461.60
$2,222,923.60
Over/Under Est:
10.96%
$219,647.35
Amt Left:
39.32%
$627,427.20
Delta:
-13.47%
-$263,965.60
$2,244,810.74
Over/Under Est:
12.06%
$241,534.49
Amt Left:
40.7%
$649,314.34
Delta:
-0.98%
-$21,887.14
$2,320,724.00
Over/Under Est:
15.85%
$317,447.75
Amt Left:
45.45%
$725,227.60
Delta:
-3.38%
-$75,913.26
$2,397,783.00
Over/Under Est:
19.69%
$394,506.75
Amt Left:
50.28%
$802,286.60
Delta:
-3.32%
-$77,059.00
$3,239,847.00
Over/Under Est:
61.73%
$1,236,570.75
Amt Left:
103.06%
$1,644,350.60
Delta:
-35.12%
-$842,064.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| S & S BRIDGE PAINTING, INC. | 3.48% | $57,156.35 |
| TRP CONSTRUCTION GROUP, LLC | 3.23% | $53,050.29 |
| DUSTIN ALLEN, INC. | 3.02% | $49,601.20 |
| BARRICADES UNLIMITED | 1.88% | $30,877.57 |
| Total: | 11.61% | $190,685.41 |