Show Job Controls
Bid Cobra

POTTER IH0040 (6442-14-001)

Items: 25

County: POTTER
Length: N/A
Highway: IH0040
District: AMARILLO
Control Number: 6442-14-001
DBE Goal: N/A
Project: BPM - 644214001
Guaranty: N/A
Time: 100 W
Engineer's Estimate: $1,625,122.00
Date: 10/05/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
ZACHARY MAYER
IVAN FUENTES
WES KIMMELL
BRAD BUCHANAN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,625,122.00
$1,569,569.00
Over/Under Est: -3.42% -$55,553.00
Over/Under Est: 10.17% $165,232.58
Amt Left: 14.07% $220,785.58
Over/Under Est: 35.99% $584,931.00
Amt Left: 40.81% $640,484.00
Delta: -23.44% -$419,698.42
Subcontractor Percentage Amount
MACIAS SPECIALTY CONTRACTING LLC 22.96% $376,704.49
FC TRAFFIC CONTROL, INC. 7.14% $117,145.91
TRP CONSTRUCTION GROUP, LLC 4.01% $65,792.03
Total: 34.11% $559,642.43

Bid Items & Bid Tabulations

25 Total 0 of 25
POTTER  |  IH0040  |  AMARILLO  |  6442-14-001  |  10/05/2023  |  $1,625,122.00  |  BPM - 644214001  |  BRIDGE PREVENT MAINT  |  100 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE TRUESDELL CORPORATION
GIBSON & ASSOCIATES, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
REMOVING CONC (PAV)
SY 11.000 $50.000 $904.000 $720.000 $100.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 38.000 $50.000 $532.000 $600.000 $100.000
FLOWABLE BACKFILL
CY 18.000 $2.000 $850.000 $565.000 $500.000
EPOXY WATERPROOF FINISH (TY X)
SF 3,952.000 $13.000 $13.000 $8.800 $15.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 3,176.000 $9.000 $18.500 $22.000 $12.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 1,010.000 $175.000 $53.000 $50.000 $275.000
RIPRAP (CONC)(4 IN)
CY 4.000 $900.000 $900.000 $2,000.000 $800.000
RIPRAP (CONC)(FLUME)
CY 4.000 $900.000 $900.000 $2,500.000 $800.000
RIPRAP (MOW STRIP)(4 IN)
CY 1.000 $900.000 $1,400.000 $3,500.000 $800.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 2,973.000 $40.000 $47.000 $16.000 $55.000
CLEANING EXISTING JOINTS
LF 1,270.000 $10.000 $17.000 $40.000 $20.000
MULTI-LAYER POLYMER OVERLAY
SY 17,707.000 $40.000 $39.500 $54.190 $70.000
RAIL (MN)
LF 228.000 $200.000 $35.000 $176.000 $150.000
HEADER TYPE EXPANSION JOINT
CF 2.000 $1,285.000 $750.000 $2,000.000 $1,000.000
SHOT BLASTING
SY 17,782.000 $7.000 $2.750 $4.500 $5.000
MOBILIZATION
LS 1.000 $140,000.000 $206,602.500 $185,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $25,000.000 $16,500.000 $32,500.000 $5,000.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 492.000 $2.000 $6.500 $5.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 290.000 $2.000 $6.500 $5.000 $1.000
REFL PAV MRK TY I (W)8"(BRK)(090MIL)
LF 747.000 $2.000 $5.500 $2.750 $6.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 6,286.000 $2.000 $4.250 $2.750 $6.000
REFL PAV MRK TY I (Y)8"(SLD)(090MIL)
LF 6,286.000 $2.000 $4.250 $2.750 $6.000
REFL PAV MRKR TY II-C-R
EA 158.000 $10.000 $43.000 $8.800 $50.000
CLEANING STRUCTURE (BENT)
EA 35.000 $1,500.000 $1,600.000 $990.000 $100.000
CLEANING STRUCTURE (ABUTMENT)
EA 32.000 $1,500.000 $1,600.000 $990.000 $100.000
Totals: $1,625,122.000 $1,569,569.000 $1,790,354.580 $2,210,053.000