Show Job Controls
Bid Cobra

POTTER RM 1061 (1245-02-050)

Items: 46

County: POTTER
Length: N/A
Highway: RM 1061
District: AMARILLO
Control Number: 1245-02-050
DBE Goal: N/A
Project: F 2023(053)
Guaranty: N/A
Time: 79 WORKING DAYS
Engineer's Estimate: $7,835,330.00
Date: 09/08/2022 (3 years ago)
Contract Number: N/A
Type: PREVENTIVE MAINTENANCE
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$7,835,330.00
1
$7,909,237.48
Over/Under Est: 0.94% $73,907.48
$8,332,385.40
Over/Under Est: 6.34% $497,055.40
Amt Left: 5.35% $423,147.92
$8,563,707.92
Over/Under Est: 9.3% $728,377.92
Amt Left: 8.27% $654,470.44
Delta: -2.78% -$231,322.52
$8,649,185.55
Over/Under Est: 10.39% $813,855.55
Amt Left: 9.36% $739,948.07
Delta: -1.00% -$85,477.63
Over/Under Est: 23.2% $1,817,453.73
Amt Left: 22.04% $1,743,546.25
Delta: -11.60% -$1,003,598.18

Bid Items & Bid Tabulations

46 Total 0 of 46
POTTER  |  RM 1061  |  AMARILLO  |  1245-02-050  |  09/08/2022  |  $7,835,330.00  |  F 2023(053)  |  PREVENT MAINT  |  79 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
DUININCK, INC.
GILVIN-TERRILL, LTD.
J. LEE MILLIGAN, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
PREPARING ROW
AC 24.770 $200.000 $278.290 $105.000 $500.000 $490.000 $369.500
REMOVING CONCRETE(MOW STRIP)
LF 4,455.000 $9.000 $15.900 $5.150 $5.000 $8.550 $5.070
BACKFILL (TY A)
STA 542.000 $200.000 $259.540 $340.000 $250.000 $265.000 $288.770
DRILL SEEDING (TEMP) (WARM)
AC 24.860 $600.000 $441.300 $440.000 $450.000 $580.000 $704.080
EMULS ASPH (EROSN CONT)(MULTI)
GAL 12,040.000 $4.000 $4.000 $3.900 $5.000 $5.000 $5.950
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 7,470.000 $21.000 $20.910 $26.500 $30.000 $31.450 $30.920
PLANE ASPH CONC PAV (0"-2.75")
SY 3,272.000 $5.000 $4.940 $5.650 $5.000 $5.000 $3.840
RIPRAP (MOW STRIP)(4 IN)
CY 58.000 $750.000 $1,272.000 $845.000 $800.000 $740.000 $1,126.520
MOBILIZATION
LS 1.000 $650,000.000 $197,730.930 $480,000.000 $850,000.000 $859,000.000 $959,761.790
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $21,000.000 $9,894.290 $25,500.000 $19,200.000 $22,350.000 $35,000.000
INTERSECTIONS (ACP)
SY 892.000 $75.000 $25.960 $29.500 $65.000 $58.250 $72.790
RUMBLE STRIPS (SHOULDER)
LF 107,560.000 $0.300 $0.160 $0.100 $0.300 $0.250 $0.100
RUMBLE STRIPS (CENTERLINE)
LF 53,780.000 $0.300 $0.180 $0.150 $0.300 $0.300 $0.100
MTL W-BEAM GD FEN (STEEL POST)
LF 3,075.000 $45.000 $37.100 $38.000 $35.000 $37.200 $39.430
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $4,000.000 $3,299.810 $2,800.000 $2,675.000 $4,000.000 $3,013.440
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $2,500.000 $1,590.000 $1,500.000 $1,500.000 $1,700.000 $1,689.780
REMOVE METAL BEAM GUARD FENCE
LF 2,595.000 $5.000 $4.240 $2.650 $4.000 $3.150 $4.510
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 8.000 $300.000 $424.000 $265.000 $400.000 $315.000 $450.610
GUARDRAIL END TREATMENT (INSTALL)
EA 24.000 $4,200.000 $3,312.500 $3,300.000 $3,125.000 $3,700.000 $3,520.380
GUARDRAIL END TREATMENT (REMOVE)
EA 24.000 $500.000 $424.000 $265.000 $400.000 $315.000 $450.610
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 41.000 $850.000 $832.100 $675.000 $820.000 $1,055.000 $884.320
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 11.000 $1,100.000 $1,018.660 $830.000 $37.000 $1,185.000 $1,082.590
REMOVE SM RD SN SUP&AM
EA 14.000 $130.000 $134.480 $21.000 $110.000 $110.000 $168.980
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 12.000 $16.000 $36.040 $21.000 $34.000 $21.100 $38.300
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 57.000 $50.000 $47.700 $38.500 $45.000 $44.850 $50.690
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 24.000 $160.000 $128.260 $185.000 $145.000 $163.500 $136.310
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 5,760.000 $0.250 $0.210 $0.210 $0.200 $0.210 $0.230
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 6,805.000 $0.250 $0.210 $0.210 $0.200 $0.210 $0.230
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 85,180.000 $0.250 $0.180 $0.180 $0.170 $0.180 $0.190
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,179.000 $1.500 $1.290 $1.050 $1.000 $1.600 $2.250
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 12,612.000 $1.500 $1.290 $1.050 $1.000 $1.650 $2.250
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
LF 285.000 $0.500 $1.060 $1.050 $1.000 $1.050 $1.130
REFL PAV MRKR TY I-C
EA 290.000 $3.250 $6.360 $6.300 $6.000 $6.350 $6.760
REFL PAV MRKR TY II-A-A
EA 1,411.000 $3.250 $5.300 $5.250 $5.000 $5.250 $5.630
REINFORMT GRID FOR ASPHALT PVMT OVERLAY
SY 188,864.000 $7.000 $8.060 $8.000 $8.000 $8.000 $8.730
D-GR HMA TY-F SAC-A PG70-22
TON 9,144.000 $140.000 $137.230 $145.000 $135.000 $135.000 $170.490
TACK COAT
GAL 28,817.000 $5.500 $4.390 $3.400 $4.500 $4.750 $4.970
SP MIXES SP-D SAC-A PG70-28
TON 24,430.000 $122.000 $137.030 $141.600 $140.000 $134.750 $148.380
TACK COAT
GAL 39,620.000 $5.500 $7.490 $7.200 $4.500 $7.400 $7.140
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $24,837.800 $10,500.000 $20,000.000 $16,500.000 $24,383.720
HPPM W/RET REQ TY I(W)4"(BRK)(090MIL)
LF 5,760.000 $0.600 $0.510 $0.510 $0.480 $0.500 $0.540
HPPM W/RET REQ TY I(W)4"(SLD)(090MIL)
LF 108,354.000 $0.500 $0.460 $0.450 $0.430 $0.450 $0.480
HPPM W/RET REQ TY I(Y)4"(BRK)(090MIL)
LF 6,805.000 $0.600 $0.510 $0.510 $0.480 $0.500 $0.540
HPPM W/RET REQ TY I(Y)4"(SLD)(090MIL)
LF 85,180.000 $0.500 $0.460 $0.450 $0.430 $0.450 $0.480
TMA (STATIONARY)
DAY 83.000 $200.000 $446.490 $210.000 $670.000 $515.000 $606.390
TMA (MOBILE OPERATION)
HR 110.000 $80.000 $82.220 $95.000 $95.000 $86.000 $107.350
Totals: $7,835,330.000 $7,909,237.491 $8,332,385.400 $8,563,707.920 $8,649,185.550 $9,652,783.744