PREPARING ROW (TREE) (0" TO 6" DIA)
|
EA
|
257.000
|
$400.000
|
$159.040
|
$226.800
|
$100.000
|
$180.000
|
$98.000
|
|
|
PREPARING ROW (TREE) (6" TO 24" DIA)
|
EA
|
35.000
|
$600.000
|
$795.200
|
$594.000
|
$500.000
|
$1,400.000
|
$1,040.000
|
|
|
PREPARING ROW(TREE)(24" TO 36" DIA.)
|
EA
|
1.000
|
$2,100.000
|
$1,590.400
|
$1,620.000
|
$2,500.000
|
$2,800.000
|
$2,608.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
115.000
|
$40.000
|
$25.970
|
$22.680
|
$50.000
|
$42.000
|
$27.000
|
|
|
REMOVING STAB BASE & ASPH PAV (12")
|
SY
|
11,550.000
|
$14.000
|
$9.040
|
$9.970
|
$8.000
|
$13.850
|
$7.250
|
|
|
REMOVING STAB BASE AND ASPH PAV (4")
|
SY
|
8,334.000
|
$7.000
|
$7.990
|
$4.520
|
$8.000
|
$7.750
|
$43.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
27,324.000
|
$15.000
|
$10.660
|
$20.260
|
$20.000
|
$17.900
|
$11.500
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
530.000
|
$40.000
|
$59.040
|
$42.220
|
$50.000
|
$29.000
|
$33.500
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
18,441.000
|
$15.000
|
$10.000
|
$13.320
|
$20.000
|
$17.800
|
$12.750
|
|
|
BACKFILL (TY A)
|
STA
|
35.610
|
$225.000
|
$200.000
|
$309.780
|
$200.000
|
$420.000
|
$872.000
|
|
|
BLADING
|
HR
|
365.000
|
$170.000
|
$313.440
|
$339.440
|
$120.000
|
$355.000
|
$399.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
AC
|
28.930
|
$600.000
|
$500.680
|
$459.000
|
$425.000
|
$580.000
|
$871.000
|
|
|
DRILL SEEDING (TEMP)(WARM OR COOL)
|
AC
|
29.710
|
$500.000
|
$471.230
|
$432.000
|
$400.000
|
$475.000
|
$756.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY C)
|
SY
|
2,068.000
|
$1.500
|
$2.950
|
$2.700
|
$2.500
|
$2.650
|
$3.200
|
|
|
FL BS (CMP IN PLC)(TY A OR B GR4)(10")
|
SY
|
79,598.000
|
$20.000
|
$21.080
|
$28.170
|
$25.000
|
$22.900
|
$24.500
|
|
|
CEMENT
|
TON
|
553.000
|
$210.000
|
$308.660
|
$219.470
|
$200.000
|
$184.250
|
$261.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
49,669.000
|
$3.000
|
$2.000
|
$3.930
|
$3.000
|
$3.800
|
$6.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
22,004.000
|
$5.000
|
$6.160
|
$4.950
|
$4.200
|
$4.350
|
$5.500
|
|
|
EMULS ASPH (EROSN CONT)(MS-2)
|
GAL
|
6,942.000
|
$4.000
|
$5.290
|
$3.740
|
$4.300
|
$4.500
|
$5.250
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
33,433.000
|
$3.700
|
$4.530
|
$4.100
|
$4.100
|
$4.100
|
$5.250
|
|
|
AGGR(TY-B GR-4 SAC-B)
|
CY
|
826.000
|
$140.000
|
$172.850
|
$245.170
|
$110.000
|
$137.000
|
$438.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
|
SY
|
22,655.000
|
$20.000
|
$4.090
|
$16.340
|
$16.500
|
$22.200
|
$19.500
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
10,756.000
|
$5.000
|
$2.550
|
$2.040
|
$3.600
|
$2.900
|
$2.400
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
873.000
|
$5.000
|
$12.260
|
$2.040
|
$4.000
|
$11.600
|
$2.600
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
69.000
|
$750.000
|
$765.750
|
$737.100
|
$600.000
|
$613.000
|
$767.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
22.000
|
$750.000
|
$765.750
|
$737.100
|
$750.000
|
$760.000
|
$1,060.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
160.000
|
$100.000
|
$94.250
|
$90.720
|
$250.000
|
$133.000
|
$153.000
|
|
|
CMP (GAL STL 30 IN)
|
LF
|
26.000
|
$125.000
|
$117.810
|
$113.400
|
$275.000
|
$136.000
|
$187.000
|
|
|
CMP (GAL STL 48 IN)
|
LF
|
51.000
|
$150.000
|
$188.490
|
$181.440
|
$350.000
|
$158.000
|
$354.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
174.000
|
$90.000
|
$106.030
|
$102.060
|
$200.000
|
$134.000
|
$142.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
780.000
|
$125.000
|
$153.150
|
$147.420
|
$225.000
|
$162.000
|
$91.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
434.000
|
$175.000
|
$200.270
|
$192.780
|
$250.000
|
$150.000
|
$183.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
84.000
|
$250.000
|
$335.750
|
$323.190
|
$350.000
|
$295.000
|
$307.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
108.000
|
$350.000
|
$435.890
|
$419.580
|
$400.000
|
$310.000
|
$431.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
2.000
|
$1,000.000
|
$20,027.240
|
$19,278.000
|
$15,000.000
|
$14,000.000
|
$18,630.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
4.000
|
$1,000.000
|
$37,698.340
|
$36,288.000
|
$30,000.000
|
$23,300.000
|
$21,072.140
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
12.000
|
$1,500.000
|
$1,413.690
|
$1,360.800
|
$4,000.000
|
$2,550.000
|
$2,680.000
|
|
|
SET (TY II) (24 IN) (CMP) (4: 1) (C)
|
EA
|
10.000
|
$1,500.000
|
$1,767.110
|
$1,701.000
|
$4,500.000
|
$2,050.000
|
$7,250.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (C)
|
EA
|
2.000
|
$2,000.000
|
$2,061.630
|
$1,984.500
|
$4,500.000
|
$2,300.000
|
$12,362.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
5.000
|
$3,000.000
|
$1,943.820
|
$1,871.100
|
$4,500.000
|
$2,685.000
|
$6,029.290
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
6.000
|
$3,000.000
|
$2,096.970
|
$2,018.520
|
$4,500.000
|
$3,000.000
|
$7,212.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
43.000
|
$3,000.000
|
$2,120.530
|
$2,041.200
|
$4,500.000
|
$3,000.000
|
$2,960.000
|
|
|
SET (TY II) (30 IN) (CMP) (4: 1) (C)
|
EA
|
2.000
|
$2,000.000
|
$3,769.830
|
$3,628.800
|
$5,000.000
|
$2,400.000
|
$5,810.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
9.000
|
$3,000.000
|
$3,769.830
|
$3,628.800
|
$7,500.000
|
$3,365.000
|
$14,328.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (C)
|
EA
|
1.000
|
$2,500.000
|
$4,123.260
|
$3,969.000
|
$7,500.000
|
$3,900.000
|
$12,904.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$2,500.000
|
$4,123.260
|
$3,969.000
|
$5,500.000
|
$3,900.000
|
$4,443.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
2.000
|
$3,000.000
|
$4,535.580
|
$4,365.900
|
$10,000.000
|
$6,000.000
|
$10,476.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (C)
|
EA
|
1.000
|
$3,500.000
|
$5,301.330
|
$5,103.000
|
$11,500.000
|
$8,000.000
|
$8,999.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
15.000
|
$2,250.000
|
$2,945.180
|
$2,700.000
|
$2,000.000
|
$2,600.000
|
$2,890.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
42.000
|
$1,000.000
|
$589.040
|
$567.000
|
$1,000.000
|
$1,000.000
|
$2,530.000
|
|
|
REMOV STR (PIPE)
|
LF
|
862.000
|
$15.000
|
$17.670
|
$17.010
|
$30.000
|
$26.000
|
$17.500
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
4.000
|
$75.000
|
$117.810
|
$113.400
|
$100.000
|
$350.000
|
$368.200
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$970,000.000
|
$1,342,035.450
|
$670,281.540
|
$1,350,000.000
|
$1,380,000.000
|
$1,512,110.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
17.000
|
$21,000.000
|
$20,000.000
|
$9,673.200
|
$25,000.000
|
$30,000.000
|
$2,390.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
1,200.000
|
$5.000
|
$5.890
|
$5.400
|
$5.000
|
$8.450
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,200.000
|
$2.000
|
$1.180
|
$1.080
|
$1.000
|
$2.500
|
$2.000
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
555.000
|
$75.000
|
$286.870
|
$150.660
|
$150.000
|
$147.250
|
$155.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,148.000
|
$45.000
|
$90.420
|
$32.720
|
$32.000
|
$60.400
|
$72.500
|
|
|
DRIVEWAYS (BASE)
|
SY
|
2,231.000
|
$20.000
|
$31.430
|
$26.280
|
$30.000
|
$45.000
|
$51.500
|
|
|
TURNOUTS (RAP)
|
SY
|
645.000
|
$25.000
|
$28.300
|
$20.820
|
$50.000
|
$23.000
|
$11.250
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
77,586.000
|
$0.150
|
$0.120
|
$0.120
|
$0.200
|
$0.200
|
$0.300
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
39,056.000
|
$0.500
|
$0.150
|
$0.120
|
$0.200
|
$0.200
|
$0.350
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
2,040.000
|
$37.000
|
$38.880
|
$35.640
|
$35.000
|
$39.350
|
$43.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
11.000
|
$2,500.000
|
$2,709.570
|
$2,484.000
|
$2,500.000
|
$3,000.000
|
$3,000.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
800.000
|
$4.000
|
$4.710
|
$4.320
|
$4.000
|
$3.150
|
$5.250
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
3.000
|
$350.000
|
$471.230
|
$432.000
|
$400.000
|
$320.000
|
$522.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
15.000
|
$3,500.000
|
$3,917.090
|
$3,591.000
|
$3,350.000
|
$3,700.000
|
$4,330.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
7.000
|
$400.000
|
$471.230
|
$432.000
|
$400.000
|
$320.000
|
$522.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
|
EA
|
1.000
|
$20,000.000
|
$66,561.120
|
$61,020.000
|
$60,000.000
|
$66,000.000
|
$83,975.500
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
28.000
|
$200.000
|
$220.300
|
$201.960
|
$200.000
|
$355.000
|
$244.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
15.000
|
$225.000
|
$265.070
|
$243.000
|
$225.000
|
$405.000
|
$293.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 2
|
EA
|
1.000
|
$300.000
|
$530.130
|
$486.000
|
$450.000
|
$715.000
|
$587.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
91.000
|
$750.000
|
$794.020
|
$727.920
|
$700.000
|
$935.000
|
$879.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
63.000
|
$900.000
|
$935.390
|
$857.520
|
$800.000
|
$1,100.000
|
$1,040.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
69.000
|
$100.000
|
$176.710
|
$108.000
|
$100.000
|
$105.000
|
$228.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
15.000
|
$25.000
|
$6.540
|
$43.200
|
$6.000
|
$21.000
|
$26.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
233.000
|
$25.000
|
$38.880
|
$37.800
|
$35.000
|
$11.000
|
$32.500
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
29.000
|
$35.000
|
$10.070
|
$43.200
|
$9.000
|
$48.000
|
$28.500
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
|
EA
|
127.000
|
$150.000
|
$88.360
|
$131.760
|
$122.000
|
$158.000
|
$159.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
137.000
|
$150.000
|
$143.720
|
$131.760
|
$122.000
|
$158.000
|
$159.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
3,830.000
|
$0.350
|
$0.290
|
$0.270
|
$0.250
|
$0.260
|
$0.330
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(DOT)
|
LF
|
679.000
|
$1.000
|
$1.180
|
$1.080
|
$1.000
|
$1.050
|
$1.300
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
72,813.000
|
$0.250
|
$0.290
|
$0.270
|
$0.250
|
$0.260
|
$0.330
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
1,915.000
|
$0.500
|
$1.180
|
$1.080
|
$1.000
|
$1.050
|
$1.300
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,556.000
|
$1.000
|
$2.360
|
$1.740
|
$1.000
|
$1.250
|
$2.550
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
3,014.000
|
$1.000
|
$2.360
|
$1.740
|
$1.000
|
$1.300
|
$2.600
|
|
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
|
LF
|
679.000
|
$0.600
|
$1.180
|
$1.080
|
$1.000
|
$1.050
|
$1.300
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
1,915.000
|
$1.000
|
$1.180
|
$1.080
|
$1.000
|
$1.050
|
$1.300
|
|
REFL PAV MRK TY I (W)(ARROW)(090MIL)
|
EA
|
8.000
|
$200.000
|
$471.230
|
$432.000
|
$400.000
|
$425.000
|
$522.000
|
|
REFL PAV MRK TY I (W)(WORD)(090MIL)
|
EA
|
4.000
|
$200.000
|
$589.040
|
$540.000
|
$500.000
|
$525.000
|
$652.000
|
|
REFL PAV MRK TY I (Y)24"(SLD)(090MIL)
|
LF
|
229.000
|
$10.000
|
$11.780
|
$10.800
|
$10.000
|
$10.550
|
$13.000
|
|
|
SP MIXES SP-D SAC-A PG70-28
|
TON
|
40,285.000
|
$117.000
|
$133.010
|
$145.400
|
$127.500
|
$131.500
|
$142.050
|
|
|
TACK COAT
|
GAL
|
11,291.000
|
$5.000
|
$4.870
|
$5.560
|
$4.500
|
$3.800
|
$4.550
|
|
|
UNDERSEAL COURSE
|
GAL
|
48,162.000
|
$4.250
|
$3.000
|
$3.080
|
$3.250
|
$2.900
|
$6.750
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$15,000.000
|
$24,674.340
|
$27,874.120
|
$17,500.000
|
$20,400.000
|
$26,108.500
|
|
|
HPPM W/RET REQ TY I(W)4"(BRK)(090MIL)
|
LF
|
3,830.000
|
$0.500
|
$0.590
|
$0.540
|
$0.500
|
$0.530
|
$0.650
|
|
|
HPPM W/RET REQ TY I(W)4"(SLD)(090MIL)
|
LF
|
78,109.000
|
$0.500
|
$0.570
|
$0.520
|
$0.480
|
$0.510
|
$0.630
|
|
|
HPPM W/RET REQ TY I(Y)4"(BRK)(090MIL)
|
LF
|
6,214.000
|
$0.500
|
$0.590
|
$0.540
|
$0.500
|
$0.530
|
$0.650
|
|
|
HPPM W/RET REQ TY I(Y)4"(SLD)(090MIL)
|
LF
|
48,432.000
|
$0.500
|
$0.570
|
$0.520
|
$0.480
|
$0.510
|
$0.630
|
|
|
TMA (STATIONARY)
|
DAY
|
288.000
|
$400.000
|
$299.870
|
$394.760
|
$240.000
|
$640.000
|
$632.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
100.000
|
$80.000
|
$93.870
|
$105.470
|
$95.000
|
$90.000
|
$137.000
|
|
|
REC REFL PAV MRKR TY I-C
|
EA
|
330.000
|
$3.000
|
$64.790
|
$59.400
|
$55.000
|
$58.000
|
$71.500
|
|
|
REC REFL PAV MRKR TY II-A-A
|
EA
|
992.000
|
$3.000
|
$64.790
|
$59.400
|
$55.000
|
$58.000
|
$71.500
|
|
Totals: |
$11,717,877.900
|
$12,755,021.416
|
$13,405,630.926
|
$13,527,791.380
|
$13,807,257.410
|
$15,020,633.490
|